TE10.27 - Construction Staging Area Time Extension - Phase 2 - Yonge Street and Bloor Street West - 1 Bloor Street West

Decision Type:
ACTION
Status:
Adopted on Consent
Ward:
11 - University - Rosedale

City Council Decision

City Council on November 26 and 27, 2019, adopted the following:

 

1. City Council authorize the continuation of the closure of the west sidewalk and a 3 metre wide portion of the southbound curb lane on Yonge Street, and the provision of a temporary sidewalk in the curb lane, between Bloor Street West and a point 66 metres south, from November 1, 2019 to August 31, 2020.

 

2. City Council authorize the continuation of the closure of the south sidewalk and a 1.2 metre wide portion of the eastbound curb lane on Bloor Street West, and the provision of a temporary sidewalk in the curb lane, between Yonge Street and a point 49 metres west, from November 1, 2019 to August 31, 2020.

 

3. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

4. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

5. City Council direct the applicant to continue sweeping the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe.

 

6. City Council direct the applicant to continue pressure washing the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe.

 

7. City Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night.

 

8. City Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications.

 

9. City Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

10. City Council direct that Bloor Street West and Yonge Street be returned to its pre-construction traffic regulations and lane configurations when the project is completed.

Background Information (Community Council)

(October 17, 2019) Report and Attachment 1 from the Acting Director, Traffic Management, Transportation Services - Construction Staging Area Time Extension - Phase 2 - Yonge Street and Bloor Street West - 1 Bloor Street West
https://www.toronto.ca/legdocs/mmis/2019/te/bgrd/backgroundfile-139106.pdf

TE10.27 - Construction Staging Area Time Extension - Phase 2 - Yonge Street and Bloor Street West - 1 Bloor Street West

Decision Type:
ACTION
Status:
Amended
Ward:
11 - University - Rosedale

Community Council Recommendations

The Toronto and East York Community Council recommends that:  

 

1. City Council authorize the continuation of the closure of the west sidewalk and a 3 metre wide portion of the southbound curb lane on Yonge Street, and the provision of a temporary sidewalk in the curb lane, between Bloor Street West and a point 66 metres south, from November 1, 2019 to August 31, 2020.

 

2. City Council authorize the continuation of the closure of the south sidewalk and a 1.2 metre wide portion of the eastbound curb lane on Bloor Street West, and the provision of a temporary sidewalk in the curb lane, between Yonge Street and a point 49 metres west, from November 1, 2019 to August 31, 2020.

 

3. City Council direct the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

4. City Council direct the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

5. City Council direct the applicant to continue sweeping the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe.

 

6. City Council direct the applicant to continue pressure washing the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe.

 

7. City Council direct the applicant to continue ensuring that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night.

 

8. City Council direct the applicant to continue consulting and communicating all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications.

 

9. City Council direct the applicant to continue installing appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

10. City Council direct that Bloor Street West and Yonge Street be returned to its pre-construction traffic regulations and lane configurations when the project is completed.

Origin

(October 17, 2019) Report from the Acting Director, Traffic Management, Transportation Services

Summary

As the Toronto Transit Commission (TTC) operates a transit service on Yonge Street and Bloor Street West, City Council approval of this report is required.

 

Mizrahi Developments is constructing a mixed-use development at 1 Bloor Street West. The site is located on the southwest corner of Yonge Street and Bloor Street West. The development will consist of an 8-storey high retail podium and an 86-storey high residential tower.

 

Construction staging operations for the development currently take place within the road right-of-way on the south side of Bloor Street West and on the west side of Yonge Street. Phase 1 of construction involved excavation, piling and shoring operations and building to the ground level, which is nearing completion. City Council, at its meeting on October 2, 2017, authorized the subject construction staging areas from October 9, 2017 to October 31, 2019.

 

Transportation Services is requesting authorization to extend the construction staging areas on Yonge Street and Bloor Street West for an additional ten months (i.e. from November 1, 2019 to August 31, 2020), in order to facilitate the construction of the 8-storey high podium (Phase 2).

Background Information

(October 17, 2019) Report and Attachment 1 from the Acting Director, Traffic Management, Transportation Services - Construction Staging Area Time Extension - Phase 2 - Yonge Street and Bloor Street West - 1 Bloor Street West
https://www.toronto.ca/legdocs/mmis/2019/te/bgrd/backgroundfile-139106.pdf

Motions

1 - Motion to Amend Item moved by Councillor Mike Layton (Carried)

That Recommendation 1 and 2 be deleted and replaced with the following new Recommendations 1 and 2:

 

1.  City Council authorize the continuation of the closure of the west sidewalk and a 3 metre wide portion of the southbound curb lane on Yonge Street, and the provision of a temporary sidewalk in the curb lane, between Bloor Street West and a point 66 metres south, from November 1, 2019 to August 31, 2020.

 

2.  City Council authorize the continuation of the closure of the south sidewalk and a 1.2 metre wide portion of the eastbound curb lane on Bloor Street West, and the provision of a temporary sidewalk in the curb lane, between Yonge Street and a point 49 metres west, from November 1, 2019 to August 31, 2020.

 


2 - Motion to Adopt Item as Amended moved by Councillor Gord Perks (Carried)
Source: Toronto City Clerk at www.toronto.ca/council