Item - 2019.NY11.16

Tracking Status

  • This item was considered by North York Community Council on December 3, 2019 and was adopted without amendment. City Council has delegated authority for this matter to the North York Community Council and therefore, the decision is final.

NY11.16 - Construction Staging Area Time Extension - Helendale Avenue

Decision Type:
ACTION
Status:
Adopted
Schedule Type:
Delegated
Ward:
8 - Eglinton - Lawrence

Community Council Decision

North York Community Council:

 

1. Approved the continuation of the closure of the south sidewalk and the full width of Helendale Avenue, between Yonge Street to 27 metres west, from December 3, 2019 to April 30, 2021.

 

2. Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

3. Directed the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

4. Directed that Helendale Avenue be returned to its pre-construction traffic regulations and lane configurations when the project is completed.

Origin

(November 5, 2019) Report from the Acting Director, Traffic Management, Transportation Services

Summary

This staff report is about a matter for which Community Council has delegated authority to make a final decision, provided that it is not amended so that it varies with City policy or by-laws.

 

Lifetime Developments is constructing a 29-storey condominium at 2360-2376 Yonge Street, on the southwest corner of Yonge Street and Helendale Avenue.  They received approval from North York Community Council to occupy the south sidewalk and full roadway on Helendale Avenue, between Yonge Street and a point 27 metres west of Yonge Street, for a one-year period from July 5, 2018 to July 5, 2019.  Due to the relocation of staffing assignments, the requirements of this site were overlooked and it came to our attention that the end date that was approved by Council had passed.  Lifetime Developments has been paying the monthly fees since July 5, 2019, in anticipation of a report being brought forward to Council to extend the duration of the construction staging area since it is still needed to construct the building safely.

 

Transportation Services is requesting approval to extend the duration of the construction staging area on Helendale Avenue from December 4, 2019 to April 30, 2021 in order to complete construction.

Background Information

(November 5, 2019) Report and Attachments 1-2 from the Acting Director, Traffic Management, Transportation Services on a Construction Staging Area Time Extension at Helendale Avenue
https://www.toronto.ca/legdocs/mmis/2019/ny/bgrd/backgroundfile-140069.pdf

Motions

Motion to Adopt Item moved by Councillor Mike Colle (Carried)
Source: Toronto City Clerk at www.toronto.ca/council