Item - 2019.EX8.18
Tracking Status
- City Council adopted this item on October 2 and 3, 2019 without amendments.
- This item was considered by the Executive Committee on September 18, 2019 and adopted without amendment. It will be considered by City Council on October 2 and 3, 2019.
- See also BU8.8
EX8.18 - Solid Waste Management Services 2019 Capital Budget and 2020-2028 Capital Plan Adjustments
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
City Council Decision
City Council on October 2 and 3, 2019, adopted the following:
1. City Council authorize the reallocation of project costs and cash flows in Solid Waste Management Services' Approved 2019 Capital Budget and 2020-2028 Capital Plan in the amount of $4.109 million from projects that have been awarded under budget or delayed to those requiring additional funding in the amount as presented in Schedule A to the report (August 22, 2019) from the General Manager, Solid Waste Management Services with a zero budget impact.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2019/ex/bgrd/backgroundfile-137295.pdf
(August 22, 2019) Report from the General Manager, Solid Waste Management Services on Solid Waste Management Services 2019 Capital Budget and 2020-2028 Capital Plan Adjustments
https://www.toronto.ca/legdocs/mmis/2019/ex/bgrd/backgroundfile-137296.pdf
Revised Attachment 1 - Schedule A - Solid Waste Management Services' 2019 Budget Adjustments Reallocations
https://www.toronto.ca/legdocs/mmis/2019/ex/bgrd/backgroundfile-137297.pdf
Motions (City Council)
EX8.18 - Solid Waste Management Services 2019 Capital Budget and 2020-2028 Capital Plan Adjustments
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Executive Committee recommends that:
1. City Council authorize the reallocation of project costs and cash flows in Solid Waste Management Services' Approved 2019 Capital Budget and 2020-2028 Capital Plan in the amount of $4.109 million from projects that have been awarded under budget or delayed to those requiring additional funding in the amount as presented in Schedule A to the report (August 22, 2019) from the General Manager, Solid Waste Management Services with a zero budget impact.
Origin
Summary
This report requests City Council's authority to amend Solid Waste Management Services' Approved 2019 Capital Budget and 2020-2028 Capital Plan by adjusting project cost and cash flows contained within the Budget and Plan, respectively, to align forecasted project accelerations and deferrals. Additional reallocations to project cash flows and project costs are requested where recent project bids or estimates exceed the current approved cash flow. These reallocations will allow Solid Waste Management Services to continue to deliver projects within its capital plan. The adjustments will have a zero dollar impact on the 2019 Capital Budget and 2020-2028 Capital Plan and will align the budget and plan with Solid Waste Management Services' capital project delivery schedule and project requirements.
Background Information
https://www.toronto.ca/legdocs/mmis/2019/ex/bgrd/backgroundfile-137295.pdf
(August 22, 2019) Report from the General Manager, Solid Waste Management Services on Solid Waste Management Services 2019 Capital Budget and 2020-2028 Capital Plan Adjustments
https://www.toronto.ca/legdocs/mmis/2019/ex/bgrd/backgroundfile-137296.pdf
Revised Attachment 1 - Schedule A - Solid Waste Management Services' 2019 Budget Adjustments Reallocations
https://www.toronto.ca/legdocs/mmis/2019/ex/bgrd/backgroundfile-137297.pdf