Item - 2019.EX7.27

Tracking Status

  • City Council adopted this item on July 16, 17 and 18, 2019 without amendments and without debate.
  • This item was considered by the Executive Committee on July 4, 2019 and adopted without amendment. It will be considered by City Council on July 16, 17 and 18, 2019.
  • See also BU7.8

EX7.27 - Transportation Services 2019 Capital Budget and 2019-2028 Adjustments

Decision Type:
ACTION
Status:
Adopted on Consent
Wards:
All

City Council Decision

City Council on July 16, 17 and 18, 2019, adopted the following:

 

1.  City Council amend the Transportation Services' Approved 2019 Capital Budget by reallocating funding of $1 million between projects, as presented in Attachment 1 to the report (June 19, 2019) from the General Manager, Transportation Services, with a zero Budget impact.

 

2.  City Council amend the 2019-2028 Approved Capital Budget and Plan for Transportation Services by creating a new Future of King Street project with total project costs of $1.5 million gross and $0 debt, with committed cash flows of $1 million in 2019 and $0.5 million in 2020, fully funded by the Public Realm Reserve Fund.

Background Information (Committee)

(June 19, 2019) Report and Attachment 1 from the General Manager, Transportation Services on Transportation Services 2019 Capital Budget and 2019-2028 Adjustments
https://www.toronto.ca/legdocs/mmis/2019/ex/bgrd/backgroundfile-135013.pdf

EX7.27 - Transportation Services 2019 Capital Budget and 2019-2028 Adjustments

Decision Type:
ACTION
Status:
Adopted
Wards:
All

Committee Recommendations

The Executive Committee recommends that:

 

1.  City Council amend the Transportation Services' approved 2019 Capital Budget by reallocating funding of $1 million between projects, as presented in Attachment 1 to the report (June 19, 2019) from the General Manager, Transportation Services, with a zero budget impact.

 

2.  City Council amend the 2019-2028 approved Capital Budget and Plan for Transportation Services by creating a new Future of King Street project with total project costs of $1.5 million gross and $0 debt, with committed cash flows of $1 million in 2019 and $0.5 million in 2020, fully funded by the Public Realm Reserve Fund.

Origin

(June 19, 2019) Report from the General Manager, Transportation Services

Summary

This report requests City Council's authority to amend Transportation Services' approved 2019 Capital Budget and 2019-2028 Capital Plan by reallocating cash flows within the 2019 Budget.

 

In addition, the report requests authority to amend Transportation Services' 2019 Capital Budget and 2019-2028 Plan by creating a new Future of King Street capital project with 2019 total project costs of $1.5 million gross and $0 debt with cash flows of $1 million in 2019 and $0.5 million in 2020, fully funded from the Public Realm Reserve Account.

 

These adjustments will align program requirements and project delivery schedules resulting in improved spending rates.

Background Information

(June 19, 2019) Report and Attachment 1 from the General Manager, Transportation Services on Transportation Services 2019 Capital Budget and 2019-2028 Adjustments
https://www.toronto.ca/legdocs/mmis/2019/ex/bgrd/backgroundfile-135013.pdf

Motions

1 - Motion to Adopt Item moved by Councillor Gary Crawford (Carried)
Source: Toronto City Clerk at www.toronto.ca/council