Item - 2019.BA40.4
Tracking Status
- This item was considered by Bid Award Panel on August 21, 2019 and was adopted without amendment.
BA40.4 - Award of Tender Call 298-2018 to Steelcore Construction Ltd. for Blower Building Rehabilitation and Upgrades at Ashbridges Bay Treatment Plant for Prequalified General Contractors Only from Request to Pre-Qualify 3907-18-7149
- Decision Type:
- ACTION
- Status:
- Adopted
- Ward:
- 14 - Toronto - Danforth
Panel Decision
The Bid Award Panel adopted the following:
1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (August 8, 2019) from the Chief Purchasing Officer:
Call Number:
Tender Call No. 298-2018, Contract No. 18TW-CTS-20CWD
Description:
Blower Building Rehabilitation and Upgrades at Ashbridges Bay Treatment Plant (TAB) in the City of Toronto for Prequalified General Contractors Only from Request to Pre-Qualify (RTP) No. 3907-18-7149
Recommended Bidder:
Steelcore Construction Ltd.
Contract Award Value:
$11,459,750 net of all applicable taxes and charges
$12,949,518 including HST and all applicable charges
$11,661,442 net of HST recoveries
Contract is expected to start on date of award and end in December 2021.
Origin
Summary
Call Issued: January 18, 2019 Call Closed: March 22, 2019
Number of Addenda Issued: Six (6)
Number of Bids: Four (4)
Table 2 - Summary of Bids Received for Tender Call No. 298-2018 including bid price
|
Bidder Name |
Bid Price (including H.S.T.) |
|
Steelcore Construction Ltd. |
$12,949,518 * |
|
Torbear Contracting Inc. |
$13,799,505 * |
|
Alberici Constructors, Ltd. |
$15,852,083 * |
|
Aquicon Construction Co. Ltd. |
$16,402,967 |
* Tender prices were corrected for mathematical errors. Purchasing and Materials Management has verified that the mathematical errors were corrected.