BA12.3 - Award of Tender Call No. 207-2018 to KAPP Infrastructure Inc. for the Construction of Sewers and Watermains Associated with the Basement Flooding Protection Program
- Decision Type:
- ACTION
- Status:
- Adopted
- Ward:
- 2 - Etobicoke Centre
Panel Decision
The Bid Award Panel adopted the following:
1. Bid Award Panel grant authority to award the contract in accordance with the Contract Details set out in the report (February 1, 2019) from the Chief Purchasing Officer:
Call Number:
Tender Call No. 207-2018; Contract No. 18ECS-LU-13FP
Description:
Storm sewers, watermain, and related improvements for Basement Flooding Protection Program Phase 4 Assignment 8-04B on Kipling Avenue, Great Oak Drive, Rathburn Road, and Random Street.
Recommended Bidder:
KAPP Infrastructure Inc.
Contract Award Value:
$6,755,146 net of all applicable taxes and charges
$7,633,314 including HST and all applicable charges
$6,874,036 net of HST recoveries
Contract is expected to start April 3, 2019 and end in December of 2020.
Origin
Summary
Call Issued: November 7, 2018 Call Closed: December 14, 2018
Number of Addenda Issued: Two (2)
Number of Bids: Eight (8)
Table 2: Bidders and Bid Prices for Tender Call No. 207-2018
|
Bidder Name |
Bid Price (including HST) |
|
KAPP Infrastructure Inc. |
$7,633,314.49 |
|
Memme Infrastructure Contractors |
$8,181,591.27 |
|
GFL Infrastructure Inc. |
$9,030,009.99* |
|
Clearway Construction Inc. |
$9,145,365.96* |
|
Drainstar Contracting Ltd. |
$9,858,717.23* |
|
Timbel Ltd. |
$9,882,177.70*,** |
|
Dom-Meridian Construction Ltd. |
$9,946,051.44*,** |
|
King Cross Contracting Ltd. |
$10,974,583.90*,** |
** The Bid was found non-compliant with the requirements of the Tender.