Item - 2018.EY32.20
Tracking Status
- City Council adopted this item on July 23, 24, 25, 26, 27 and 30, 2018 with amendments.
- This item was considered by Etobicoke York Community Council on July 4, 2018 and was adopted with amendments. It will be considered by City Council on July 23, 24, 25, 26, 27 and 30, 2018.
EY32.20 - Request for Directions Report - 900 and 980 Lansdowne Avenue and 30 Powerhouse Street - Official Plan Amendment and Zoning By-law Amendment Application
- Decision Type:
- ACTION
- Status:
- Amended
- Ward:
- 17 - Davenport
City Council Decision
City Council on July 23, 24, 25, 26, 27 and 30, 2018, adopted the following:
1. City Council direct the City Solicitor, together with City Planning and any other appropriate staff to attend and oppose the application for 900 and 980 Lansdowne Avenue and 30 Powerhouse Street in its current form, should the application be appealed to the Local Planning Appeal Tribunal on the basis of City Council's failure to make a decision on the application within the statutory timeframe of the Planning Act, and retain such experts as the City Solicitor may determine are appropriate.
2. City Council direct staff to continue to work with the applicant to find a design solution to the built form issues, as well as the other outstanding issues outlined in the report (June 29, 2018) from the Director of Community Planning, Etobicoke York District, and if successful, to target a community consultation meeting after the election with the Ward Councillor and to bring forward a report to the first Etobicoke York Community Council meeting of the next term.
3. Should the application be appealed to the Local Planning Appeal Tribunal and the Local Planning Appeal Tribunal allows the appeal, in whole or in part, City Council direct the City Solicitor to request the Local Planning Appeal Tribunal to withhold its final Order on the Official Plan Amendment and Zoning By-law Amendment application until:
a. a draft Official Plan Amendment and Zoning By-law Amendment is submitted to the satisfaction of the Chief Planner and Executive Director, City Planning and the City Solicitor;
b. the owner has addressed the applicability of the daycare in Phase 6 including the size, location, parking, loading and other matters to the satisfaction of the Chief Planner and Executive Director, City Planning and the General Manager, Children's Services;
c. the owner has submitted a revised Traffic Impact Study to the satisfaction of the General Manager, Transportation Services;
d. the owner has submitted a revised Functional Servicing Report, revised Stormwater Management Report and a revised Hydrogeological Report to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services;
e. the owner submits, to the satisfaction of the Chief Planner and Executive Director, City Planning, a Noise Study for Phase 9, and any revisions to the Phase 6 and Phase 9 Noise Studies as may be required through the peer review process that identifies all mitigation measures to be undertaken for this development, to be peer reviewed at the cost of the owner and to incorporate the recommendations in the site design;
f. the owner has submitted a revised Sun/Shadow Study to the satisfaction of the Chief Planner and Executive Director, City Planning;
g. the owner has submitted a revised Preliminary Wind Study to the satisfaction of the Chief Planner and Executive Director, City Planning; and
h. the owner has entered into an Agreement pursuant to Section 37 of the Planning Act satisfactory to the Chief Planner and Executive Director, City Planning and the City Solicitor for the purpose of securing appropriate community benefits, including those benefits detailed in Zoning By-law 728-2006 and to be registered on title to the lands at 980 Lansdowne Avenue and 30 Powerhouse Street.
4. In the event the Local Planning Appeal Tribunal allows the appeal in whole or in part, City Council direct that the following matters also be secured in Section 37 Agreement for the development as a legal convenience:
a. the owner shall maintain its commitment to work with the City of Toronto Social Housing Connections Office as required through the Secondary Plan and site specific Zoning By-law regarding affordable housing;
b. the owner shall satisfy the requirements of the Toronto Transit Commission regarding the new bus stop at Brandon Avenue and Lansdowne Avenue, and the new Transit Signal Priority along with identified payments;
c. the owner shall satisfy the requirements of the Toronto District School Board regarding warning clauses and signage with respect to school accommodation issues;
d. the owner shall satisfy the requirements of Metrolinx and the rail companies as required;
e. the owner shall enter into a financially secured Development Agreement for the construction of any improvements to the existing municipal infrastructure, should it be determined that upgrades are required to the infrastructure to support this development;
f. prior to the issuance of Final Site Plan Approval through the Site Plan Control review process and prior to the issuance of any permit for all or any part of the property at 30 Powerhouse Street (known as Building 15), including a heritage permit or a building permit but excluding interior alterations not impacting identified interior attributes, permits for repairs and maintenance and usual and minor works as acceptable to the Senior Manager, Heritage Preservation Services, the owner shall satisfy the requirements of Heritage Preservation Services including: amend the existing Heritage Easement Agreement; provide a detailed Conservation Plan including final site plan drawings in accordance with the detailed Conservation Plan; provide a Heritage Lighting Plan; provide an Interpretation Plan; and provide a Letter of Credit to the satisfaction of the Senior Manager Heritage Preservation Services; and
g. the owner shall construct and maintain the development in accordance with Tier 1 performance measures of the Toronto Green Standard, as adopted by Toronto City Council at its meeting held on October 26 and 27, 2009 through the adoption of Item PG32.3, and as updated by City Council at its meeting held on December 5, 6 and 7, 2017 through the adoption of item PG23.9 of the Planning and Growth Committee, and as may be further amended by City Council from time to time.
5. City Council authorize the City Solicitor and other City staff to take any necessary steps to implement City Council's decision.
Background Information (Community Council)
https://www.toronto.ca/legdocs/mmis/2018/ey/bgrd/backgroundfile-118068.pdf
(June 15, 2018) Placeholder Report from the Director, Community Planning, Etobicoke York District regarding Official Plan Amendment and Zoning By-law Amendment Applications - 900 and 980 Lansdowne Avenue and 30 Powerhouse Street
https://www.toronto.ca/legdocs/mmis/2018/ey/bgrd/backgroundfile-117223.pdf
Background Information (City Council)
https://www.toronto.ca/legdocs/mmis/2018/cc/bgrd/backgroundfile-119124.pdf
Communications (Community Council)
Motions (City Council)
That City Council adopt the recommendation contained in the supplementary report (July 17, 2018) from the Chief Planner and Executive Director, City Planning [EY32.20], as follows:
1. City Council delete Recommendation 2 from Etobicoke York Community Council and replace with the following:
City Council direct staff to continue to work with the applicant to find a design solution to the built form issues, as well as the other outstanding issues outlined in the report (June 29, 2018) from the Director of Community Planning, Etobicoke York District, and if successful, to target a community consultation meeting after the election with the Ward Councillor and to bring forward a report to the first Etobicoke York Community Council meeting of the next term.
Vote (Amend Item) Jul-24-2018 2:43 PM
| Result: Carried | Majority Required - EY32.20 - Palacio - motion 1 |
|---|---|
| Total members that voted Yes: 41 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Jon Burnside, John Campbell, Christin Carmichael Greb, Josh Colle, Gary Crawford, Joe Cressy, Janet Davis, Glenn De Baeremaeker, Justin J. Di Ciano, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Michael Ford, Mary Fragedakis, Mark Grimes, Jim Hart, Michelle Holland, Stephen Holyday, Mike Layton, Giorgio Mammoliti, Josh Matlow, Mary-Margaret McMahon, Miganoush Megardichian, Joe Mihevc, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, James Pasternak, Gord Perks, Jaye Robinson, Neethan Shan, David Shiner, Michael Thompson, John Tory, Lucy Troisi, Jonathan Tsao, Kristyn Wong-Tam |
| Total members that voted No: 0 | Members that voted No are |
| Total members that were Absent: 4 | Members that were absent are Vincent Crisanti, Jim Karygiannis, Norman Kelly, Anthony Perruzza |
Vote (Adopt Item as Amended) Jul-24-2018 2:44 PM
| Result: Carried | Majority Required - EY32.20 - Adopt the item as amended |
|---|---|
| Total members that voted Yes: 41 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Jon Burnside, John Campbell, Christin Carmichael Greb, Josh Colle, Gary Crawford, Joe Cressy, Janet Davis, Glenn De Baeremaeker, Justin J. Di Ciano, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Michael Ford, Mary Fragedakis, Mark Grimes, Jim Hart, Michelle Holland, Stephen Holyday, Mike Layton, Giorgio Mammoliti, Josh Matlow, Mary-Margaret McMahon, Miganoush Megardichian, Joe Mihevc, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, James Pasternak, Gord Perks, Jaye Robinson, Neethan Shan, David Shiner, Michael Thompson, John Tory, Lucy Troisi, Jonathan Tsao, Kristyn Wong-Tam |
| Total members that voted No: 0 | Members that voted No are |
| Total members that were Absent: 4 | Members that were absent are Vincent Crisanti, Jim Karygiannis, Norman Kelly, Anthony Perruzza |
EY32.20 - Request for Directions Report - 900 and 980 Lansdowne Avenue and 30 Powerhouse Street - Official Plan Amendment and Zoning By-law Amendment Application
- Decision Type:
- ACTION
- Status:
- Amended
- Ward:
- 17 - Davenport
Community Council Recommendations
Etobicoke York Community Council recommends that:
1. City Council direct the City Solicitor, together with Planning staff and any other appropriate staff to attend and oppose the application in its current form, should the application be appealed to the Local Planning Appeal Tribunal (the "LPAT") on the basis of City Council's failure to make a decision on the application within the statutory timeframe of the Planning Act, and retain such experts as the City Solicitor may determine are appropriate.
2. City Council direct City staff to continue to negotiate with the applicant to resolve the outstanding issues detailed in the report (June 29, 2018) from the Director, Community Planning, Etobicoke York District; and further, direct City staff to expedite the negotiation process, and should the application not be appealed to the Local Planning Advisory Tribunal during the break in Council's meeting schedule between July to December 2018, to bring forward a final report to the first Etobicoke York Community Council meeting of the next term.
3. Should the application be appealed to the LPAT and the LPAT allows the appeal, in whole or in part, City Council direct the City Solicitor to request the LPAT to withhold its final Order on the Official Plan Amendment and Zoning By-law Amendment application until:
a. A draft Official Plan Amendment and Zoning By-law Amendment is submitted to the satisfaction of the Chief Planner and Executive Director, City Planning and the City Solicitor.
b. The owner has addressed the applicability of the daycare in Phase 6 including the size, location, parking, loading and other matters to the satisfaction of the Chief Planner and Executive Director, City Planning and the General Manager, Children's Services.
c. The owner has submitted a revised Traffic Impact Study to the satisfaction of the General Manager, Transportation Services.
d. The owner has submitted a revised Functional Servicing Report, revised Stormwater Management Report and a revised Hydrogeological Report to the satisfaction of the Chief Engineer and Executive Director, Engineering and Construction Services.
e. The owner submits, to the satisfaction of the Chief Planner and Executive Director, City Planning, a Noise Study for Phase 9, and any revisions to the Phase 6 and Phase 9 Noise Studies as may be required through the peer review process that identifies all mitigation measures to be undertaken for this development, to be peer reviewed at the cost of the owner and to incorporate the recommendations in the site design.
f. The owner has submitted a revised Sun/Shadow Study to the satisfaction of the Chief Planner and Executive Director, City Planning.
g. The owner has submitted a revised Preliminary Wind Study to the satisfaction of the Chief Planner and Executive Director, City Planning.
h. The owner has entered into an Agreement pursuant to Section 37 of the Planning Act satisfactory to the Chief Planner and Executive Director, City Planning and the City Solicitor for the purpose of securing appropriate community benefits, including those benefits detailed in Zoning By-law No. 728-2006 and to be registered on title to the lands at 980 Lansdowne Avenue and 30 Powerhouse Street.
4. In the event the LPAT allows the appeal in whole or in part, City Council direct that the following matters also be secured in Section 37 Agreement for the development as a legal convenience:
a. The owner shall maintain its commitment to work with the City of Toronto Social Housing Connections Office as required through the Secondary Plan and site specific Zoning By-law regarding affordable housing.
b. The owner shall satisfy the requirements of the Toronto Transit Commission regarding the new bus stop at Brandon Avenue and Lansdowne Avenue, and the new Transit Signal Priority along with identified payments.
c. The owner shall satisfy the requirements of the Toronto District School Board regarding warning clauses and signage with respect to school accommodation issues.
d. The owner shall satisfy the requirements of Metrolinx and the rail companies as required.
e. The owner shall enter into a financially secured Development Agreement for the construction of any improvements to the existing municipal infrastructure, should it be determined that upgrades are required to the infrastructure to support this development.
f. Prior to the issuance of Final Site Plan Approval through the Site Plan Control review process and prior to the issuance of any permit for all or any part of the property at 30 Powerhouse Street (known as Building 15), including a heritage permit or a building permit but excluding interior alterations not impacting identified interior attributes, permits for repairs and maintenance and usual and minor works as acceptable to the Senior Manager Heritage Preservation Services, the owner shall satisfy the requirements of Heritage Preservation Services including: amend the existing Heritage Easement Agreement; provide a detailed Conservation Plan including final site plan drawings in accordance with the detailed Conservation Plan; provide a Heritage Lighting Plan; provide an Interpretation Plan; and provide a Letter of Credit to the satisfaction of the Senior Manager Heritage Preservation Services.
g. The owner shall construct and maintain the development in accordance with the Tier 1 performance measures of the Toronto Green Standard, as adopted by Toronto City Council at its meeting held on October 26 and 27, 2009 through the adoption of item PG32.3 of the Planning and Growth Management Committee, and as updated by Toronto City Council at its meeting held on December 5, 6 and 7, 2017 through the adoption of PG 23.9 of the Planning and Growth Committee, and as may be further amended by City Council from time to time.
5. City Council authorize the City Solicitor and other City staff to take any necessary steps to implement the foregoing.
Decision Advice and Other Information
Etobicoke York Community Council:
1. Directed the Director, Community Planning, Etobicoke York District to convene a meeting with the local City Councillor (and developer, if appropriate) the week of July 16, 2018 to continue the discussion on outstanding issues including the angular planes, and report to City Council for its meeting in July 23, 2018.
Origin
Summary
This report responds to an application where staff are currently not in a position to provide a Final Report to City Council, but which could be appealed to the Local Planning Appeal Tribunal due to a lack of decision during the break in Council's meeting schedule (July to December 2018). The report sets out potential issues related to the application in its current form.
This application proposes to amend the Official Plan and Zoning By-law to permit the construction of three residential apartment buildings of 24, 28 and 32 storeys (63.1 m, 73.6 m and 84.2 m, excluding mechanical penthouses) on top of a base building that varies in height between three and six storeys (7.2 m and 15.1 m, respectively) and three blocks of three-storey (14.4 m) townhouses. The Zoning By-law would also be amended to allow for the conversion of the existing 'Building 15' into a mixed residential and commercial building and to remove the existing Holding (H) symbol that currently applies to the lands
The three residential apartment buildings would be constructed on lands that are currently referred to as Phase 6 in the Davenport Village Secondary Plan, while the proposed townhouses would be constructed on what is referred to as Phase 9 (also known as the southern half of Phase 7). The building known as 'Building 15' was included in the Phase 1 lands, but is now included in this application as a result of the proposal to convert the office building into residential apartments and add 2 storeys above.
A total of 1,070 units are proposed for Phases 6 and 9 and Building 15. The three residential apartment buildings known as Phase 6 are proposed to have 971 units, of which 5 would be bachelor units, 605 would be one-bedroom units, 179 would be two-bedroom units and 182 would be three-bedroom units. The proposal also includes a 300 m2 daycare facility, and a 69 m2 retail space.
In Phase 9, a total of 66 units are proposed in the three blocks of townhouses and all these would be three-bedroom units.
'Building 15' would contain 33 residential units above commercial space on the ground floor.
The apartment buildings and townhouses would all be built above a common underground parking garage, which would contain a total of 747 vehicular parking spaces (510 resident and 237 visitor). With respect to bicycle parking, 834 spaces are proposed, of which 639 would be for residents and 195 would be for visitors. Four Type-G loading spaces are also proposed, one for each of the apartment buildings and one for Building 15. Access to the underground parking garage would be from the south side of Brandon Avenue, approximately halfway between Lansdowne Avenue and Foundry Avenue.
The applications consistency with the Provincial Policy Statement (2014) and conformity to the Growth Plan for the Greater Golden Horseshoe (2017) are still being assessed.
This report reviews the application and recommends that City Council direct the City Solicitor and appropriate City staff to attend and oppose the application in its current form should the application be appealed to the Local Planning Appeal Tribunal. It is also recommended that City staff be directed to continue to negotiate with the applicant to resolve the outstanding issues detailed in this report.
Background Information
https://www.toronto.ca/legdocs/mmis/2018/ey/bgrd/backgroundfile-118068.pdf
(June 15, 2018) Placeholder Report from the Director, Community Planning, Etobicoke York District regarding Official Plan Amendment and Zoning By-law Amendment Applications - 900 and 980 Lansdowne Avenue and 30 Powerhouse Street
https://www.toronto.ca/legdocs/mmis/2018/ey/bgrd/backgroundfile-117223.pdf
Communications
Motions
That Etobicoke York Community Council:
1. Amend Recommendation 2 contained in the report (June 29, 2018) from the Director, Community Planning, Etobicoke York District, by adding the following:
"and further, direct City staff to expedite the negotiation process, and should the application not be appealed to the Local Planning Advisory Tribunal during the break in Council's meeting schedule between July to December 2018, to bring forward a final report to the first Etobicoke York Community Council meeting of the next term."
so that Recommendation 2 now reads:
2. City Council direct City staff to continue to negotiate with the applicant to resolve the outstanding issues detailed in the report; and further, direct City staff to expedite the negotiation process and, should the application not be appealed to the Local Planning Advisory Tribunal during the break in Council's meeting schedule between July to December 2018, to bring forward a final report to the first Etobicoke York Community Council meeting of the next term.
2. Add the following:
Etobicoke York Community Council direct the Director, Community Planning, Etobicoke York District to convene a meeting with the local City Councillor (and developer, if appropriate) the week of July 16, 2018 to continue the discussion on outstanding issues including the angular planes, and report to City Council for its meeting in July 23, 2018.