EX35.30 - Toronto Public Library - Project Cost and Cash Flow Adjustments to the 2018 Capital Budget and 2019-2027 Capital Plan

Decision Type:
ACTION
Status:
Adopted
Wards:
All

City Council Decision

City Council on June 26, 27, 28 and 29, 2018, adopted the following:

 

1.  City Council approve the following adjustments to Toronto Public Library's 2018-2027 Capital Budget and Plan with no net impact on annual debt levels:

 

a.  increase the cost of the Wychwood Branch capital project by $5.663 million, from $10.133 million to $15.796 million, funded by $4.509 million from the Development Charges Reserve Fund (XR2115), $0.800 million operating savings from branch closure and $0.354 million from debt originally planned for the Multi-Branch State of Good Repair program; and

 

b.  decrease the project cost of the Multi-Branch State of Good Repair program in 2020 by $0.354 million gross and debt from $4.027 million to $3.673 million.

 

2.  City Council approve the following adjustments to Toronto Public Library's 2018-2027 Capital Budget and Plan with no net impact on annual debt levels:

 

a.  increase the cost of the St. Clair/Silverthorn branch project by $0.918 million, from $2.897 million to $3.815 million, funded by $0.328 million from the Development Charges Reserve Fund (XR2115) and $0.590 million from debt transferred from the Multi-Branch State of Good Repair program; and

 

b.  in-year capital budget transfer of $0.590 million gross and debt from the Multi-Branch State of Good Repair program to the St. Clair/Silverthorn branch project.

 

3.  City Council approve the 2018 Capital Budget adjustment to increase the cost of the North York Central Library Phase 1 project by $2.500 million, from $14.974 million to $17.474 million, with 2018 cash flow increasing from $2.781 million to $5.281 million funded by $2.250 million of additional operating savings due to the extended branch closure for construction in 2018 and $0.250 million of development charges, with no impact to City debt.

Background Information (Committee)

(June 1, 2018) Report from the City Librarian on Toronto Public Library - Project Cost and Cash Flow Adjustments to the 2018 Capital Budget and 2019-2027 Capital Plan
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-116076.pdf
Appendix A - Toronto Public Library Board Minute No. 18-061
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-116380.pdf
Appendix B - Toronto Public Library Board Minute No. 18-091
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-116381.pdf
Appendix C - Toronto Public Library Board Minute No. 18-092
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-116382.pdf

Motions (City Council)

Motion to Adopt Item (Carried)

Vote (Adopt Item) Jun-26-2018 3:03 PM

Result: Carried Majority Required - EX35.30 - Adopt the item
Total members that voted Yes: 40 Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Jon Burnside, John Campbell, Christin Carmichael Greb, Josh Colle, Gary Crawford, Joe Cressy, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Justin J. Di Ciano, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Mark Grimes, Jim Hart, Stephen Holyday, Jim Karygiannis, Norman Kelly, Mike Layton, Josh Matlow, Mary-Margaret McMahon, Miganoush Megardichian, Joe Mihevc, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, Gord Perks, Anthony Perruzza, Jaye Robinson, Neethan Shan, David Shiner, Michael Thompson, John Tory, Lucy Troisi, Jonathan Tsao, Kristyn Wong-Tam
Total members that voted No: 0 Members that voted No are
Total members that were Absent: 5 Members that were absent are Michael Ford, Mary Fragedakis, Michelle Holland, Giorgio Mammoliti, James Pasternak

Declared Interests (City Council)

The following member(s) declared an interest:

Councillor James Pasternak - as his wife, while on leave, is technically an employee of the Toronto Public Library.

EX35.30 - Toronto Public Library - Project Cost and Cash Flow Adjustments to the 2018 Capital Budget and 2019-2027 Capital Plan

Decision Type:
ACTION
Status:
Adopted
Wards:
All

Committee Recommendations

The Executive Committee recommends that:

 

1.  City Council approve the following adjustments to Toronto Public Library's 2018-2027 capital budget and plan with no net impact on annual debt levels:

 

a.  increase the cost of the Wychwood Branch capital project by $5.663 million, from $10.133 million to $15.796 million, funded by $4.509 million from the development charges reserve fund (XR2115), $0.800 million operating savings from branch closure and $0.354 million from debt originally planned for the Multi-Branch State of Good Repair program; and

 

b.  decrease the project cost of the Multi-Branch State of Good Repair program in 2020 by $0.354 million gross and debt from $4.027 million to $3.673 million.

 

2.  City Council approve the following adjustments to Toronto Public Library's 2018-2027 capital budget and plan with no net impact on annual debt levels:

 

a.  increase the cost of the St. Clair/Silverthorn branch project by $0.918 million, from $2.897 million to $3.815 million, funded by $0.328 million from the development charges reserve fund (XR2115) and $0.590 million from debt transferred from the Multi-Branch State of Good Repair program; and

 

b.  in-year capital budget transfer of $0.590 million gross and debt from the Multi-Branch State of Good Repair program to the St. Clair/Silverthorn branch project.

 

3.  City Council approve the 2018 capital budget adjustment to increase the cost of the North York Central Library Phase 1 project by $2.500 million, from $14.974 million to $17.474 million, with 2018 cash flow increasing from $2.781 million to $5.281 million funded by $2.250 million of additional operating savings due to the extended branch closure for construction in 2018 and $0.250 million of development charges, with no impact to City debt.

Origin

(June 1, 2018) Report from the City Librarian

Summary

The purpose of this report is to provide Executive Committee with Project Cost and Cash Flow Adjustments to the Toronto Public Library's 2018 Capital Budget and 2019-2027 Capital Plan as approved by the Toronto Public Library (TPL) Board.

Background Information

(June 1, 2018) Report from the City Librarian on Toronto Public Library - Project Cost and Cash Flow Adjustments to the 2018 Capital Budget and 2019-2027 Capital Plan
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-116076.pdf
Appendix A - Toronto Public Library Board Minute No. 18-061
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-116380.pdf
Appendix B - Toronto Public Library Board Minute No. 18-091
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-116381.pdf
Appendix C - Toronto Public Library Board Minute No. 18-092
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-116382.pdf

Motions

1 - Motion to Adopt Item moved by Councillor Gary Crawford (Carried)