EX32.7 - Rehabilitation of Western Channel Dockwall and Adjacent Waterfront Lands

Decision Type:
ACTION
Status:
Adopted
Ward:
20 - Trinity-Spadina

City Council Decision

City Council on March 26 and 27, 2018, adopted the following:

 

1.  City Council authorize the transfer of $3.220 million from the Environmental Liability Reserve Fund (XR1045) to the Facilities, Real Estate, Environment and Energy 2018-2027 Capital Budget and Plan under capital project CCA229-14, the Western Channel dockwall project.

 

2.  City Council authorize the Deputy City Manager, Cluster B, and the Deputy City Manager, Internal Corporate Services, to adjust the Facilities, Real Estate, Environment and Energy 2018-2027 Capital Budget and Plan by $3.820 million, with cash flows of $1.500 million in 2018 and $2.320 million in 2019, for project CCA229-14, the Western Channel dockwall project, funded through the following adjustments:

 

a.  $3.220 million from the Environmental Liability Reserve Fund (XR1045); and

 

b.  $0.600 million from the Toronto Port Lands Company to reflect Toronto Port Lands Company's entire project dividend in the Facilities, Real Estate, Environment and Energy 2018-2027 Capital Budget and Plan.

 

3.  City Council authorize the transfer of $0.598 million from the Environmental Liability Reserve Fund (XR1045) to the Waterfront Revitalization Initiative 2018-2027 Capital Budget and Plan under capital project CWR003-28, for costs associated with the rehabilitation of open space at the City-owned Canada Malting property.

 

4.  City Council authorize the Deputy City Manager, Cluster B, and the Deputy City Manager, Internal Corporate Services, to adjust the Waterfront Revitalization Initiative 2018-2027 Capital Budget and Plan by $1.198 million, with cash flows of $1.198 million in 2019, for project CWR003-28, the rehabilitation of open space at the City-owned Canada Malting property, funded through the following adjustments:

 

a.  $0.598 million funding from the Environmental Liability Reserve Fund (XR1045); and

 

b.  $0.600 million from a Ports Toronto contribution.

Background Information (Committee)

(March 9, 2018) Report and Attachment 1 from the Deputy City Manager, Cluster B and the Deputy City Manager, Internal Corporate Services on Rehabilitation of Western Channel Dockwall and Adjacent Waterfront Lands
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-112996.pdf

Motions (City Council)

Motion to Adopt Item (Carried)

Vote (Adopt Item) Mar-26-2018 10:21 AM

Result: Carried Majority Required - EX32.7 - Adopt the item
Total members that voted Yes: 38 Members that voted Yes are Paul Ainslie, Maria Augimeri, Jon Burnside, John Campbell, Christin Carmichael Greb, Shelley Carroll, Josh Colle, Joe Cressy, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Justin J. Di Ciano, Frank Di Giorgio, John Filion, Paula Fletcher, Michael Ford, Mary Fragedakis, Mark Grimes, Jim Hart, Michelle Holland, Stephen Holyday, Norman Kelly, Mike Layton, Josh Matlow, Mary-Margaret McMahon, Joe Mihevc, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, James Pasternak, Gord Perks, Jaye Robinson, Neethan Shan, David Shiner, Michael Thompson, John Tory, Lucy Troisi, Kristyn Wong-Tam
Total members that voted No: 0 Members that voted No are
Total members that were Absent: 7 Members that were absent are Ana Bailão, Gary Crawford, Sarah Doucette, Jim Karygiannis, Chin Lee, Giorgio Mammoliti, Anthony Perruzza

EX32.7 - Rehabilitation of Western Channel Dockwall and Adjacent Waterfront Lands

Decision Type:
ACTION
Status:
Adopted
Ward:
20 - Trinity-Spadina

Committee Recommendations

The Executive Committee recommends that:

 

1.  City Council authorize the transfer of $3.220 million from the Environmental Liability Reserve Fund (XR1045) to the Facilities, Real Estate, Environment and Energy (FREEE) 2018-2027 Capital Budget and Plan under capital project CCA229-14, the Western Channel dockwall project.

 

2.  City Council authorize the Deputy City Manager, Cluster B, and the Deputy City Manager, Internal Corporate Services, to adjust the Facilities, Real Estate, Environment and Energy (FREEE) 2018-2027 Capital Budget and Plan by $3.820 million, with cash flows of $1.500 million in 2018 and $2.320 million in 2019, for project CCA229-14, the Western Channel dockwall project, funded through the following adjustments:

 

a.  $3.220 million from the Environmental Liability Reserve Fund (XR1045); and

 

b.  $0.600 million from the Toronto Port Lands Company (TPLC) to reflect Toronto Port Lands Company's entire project dividend in Facilities, Real Estate, Environment and Energy's 2018-2027 Capital Budget and Plan.

 

3.  City Council authorize the transfer of $0.598 million from the Environmental Liability Reserve Fund (XR1045) to the Waterfront Revitalization Initiative 2018-2027 Capital Budget and Plan under capital project CWR003-28, for costs associated with the rehabilitation of open space at the City-owned Canada Malting property.

 

4.  City Council authorize the Deputy City Manager, Cluster B, and the Deputy City Manager, Internal Corporate Services, to adjust the Waterfront Revitalization Initiative 2018-2027 Capital Budget and Plan by $1.198 million, with cash flows of $1.198 million in 2019, for project CWR003-28, the rehabilitation of open space at the City-owned Canada Malting property, funded through the following adjustments:

 

a.  $0.598 million funding from the Environmental Liability Reserve Fund (XR1045); and

 

b.  $0.600 million from a Ports Toronto contribution.

Origin

(March 9, 2018) Report from the Deputy City Manager, Cluster B and the Deputy City Manager, Internal Corporate Services

Summary

This report provides recommendations that will implement two important capital improvement projects identified in the Bathurst Quay Streetscape and Public Realm Improvement Plan: the rehabilitation of the Western Channel dockwall; and the rehabilitation of open space at the Canada Malting property (5 Eireann Quay).

 

The Bathurst Quay Streetscape and Public Realm Improvement Plan was created per City Council direction related to the adoption of the Bathurst Quay Neighbourhood Plan in July 2017. From the City assets studied for improvement, the Improvement Plan proposed six distinct but overlapping near-term capital improvement projects, each with their own separate scope, approvals, timelines, budget, and funding sources. Two of these six proposed near-term capital improvement projects require Council direction related to funding and approvals.

 

The first project is the rehabilitation of the Western Channel dockwall. Due to deterioration from exposure to wind, ice and wave conditions, a significant portion of the dockwall has been closed to public access. In May 2014, Council adopted a recommendation to establish a capital project for the rehabilitation of the dockwall between the Portland Slip and the airport ferry slip, in order to restore public access and improve safety.

 

This dockwall rehabilitation project must proceed ahead of other planned improvement projects because of construction access and staging issues. The project has been estimated at $7.72 million. Detailed design has been completed and construction can begin by Autumn 2018. In May 2014, Council directed the Toronto Port Lands Company to declare a $3 million special dividend for this project. Additional funding includes a Ports Toronto commitment of $0.5 million and City funding of $1 million for this project. Staff recommend that the balance of the funding ($3.22 million) be secured from the Environmental Liability Reserve Fund, a reserve established in 1994 for the remediation of City-owned central waterfront properties.

 

The second project is the rehabilitation of open space at the Canada Malting property, north of the Western Channel dockwall. A majority of the site is currently under-utilized, containing transportation uses and the remnants of a construction staging area. The project will almost double the public open space on the property (to approximately 2.5 acres or 1 hectares), consistent with the property's Official Plan Open Space designation.

 

The project has been estimated at $2.33 million for detailed design, environmental remediation and construction. $1.132 million in funding has been secured from a Section 37 contribution. Also, Ports Toronto has committed $0.6 million. Staff recommend that the balance of the funding ($0.598 million) be secured from the Environmental Liability Reserve Fund. Over the next year staff will continue to seek additional funding from Section 37 and other sources (approximately $1 million), so that the open space can be finished with landscape pavers (instead of limestone screenings).

 

Both projects are described further in the Comments section of this report.

Background Information

(March 9, 2018) Report and Attachment 1 from the Deputy City Manager, Cluster B and the Deputy City Manager, Internal Corporate Services on Rehabilitation of Western Channel Dockwall and Adjacent Waterfront Lands
https://www.toronto.ca/legdocs/mmis/2018/ex/bgrd/backgroundfile-112996.pdf

Motions

Motion to Adopt Item moved by Councillor David Shiner (Carried)