TE26.69 - Construction Staging Area (Phase 1) - Yonge Street and Bloor Street West (1 Bloor Street West)

Decision Type:
ACTION
Status:
Adopted
Ward:
27 - Toronto Centre-Rosedale

City Council Decision

City Council on October 2, 3 and 4, 2017, adopted the following:

 

1.  City Council approve the closure of the west sidewalk and a 3 metre wide portion of the southbound curb lane on Yonge Street, and the provision of a temporary sidewalk in the curb lane, between Bloor Street West and a point 66 metres south, from October 9, 2017 to October 31, 2019.

 

2.  City Council approve the closure of the south sidewalk and a 1.2 metre wide portion of the eastbound curb lane on Bloor Street West, and the provision of a temporary sidewalk in the curb lane, between Yonge Street and a point 49 metres west, from October 9, 2017 to October 31, 2019.

 

3.  City Council prohibit southbound right-turns during all times at the intersection of Yonge Street and Bloor Street West.

 

4.  City Council rescind the existing stopping prohibition in effect from 7:30 a.m. to 9:30 a.m., Monday to Friday except public holidays on the west side of Yonge Street, between Bloor Street West and a point 66 metres south.

 

5.  City Council rescind the existing parking prohibition in effect during all times on the west side of Yonge Street, between Bloor Street West and a point 66 metres south.

 

6.  City Council prohibit stopping at all times on the west side of Yonge Street, between Bloor Street West and a point 66 metres south.

 

7.  City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

8.  City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

9.  City Council direct the applicant to sweep the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe.

 

10.  City Council direct the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe.

 

11.  City Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes.

 

12.  City Council direct the applicant where no cycling lanes exist, in consultation with Transportation Services, to install sharrow markings onto the roadway and display appropriate signage on the hoarding board to inform motorists and cyclists to safely share the road.

 

13.  City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night.

 

14.  City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications.

 

15.  City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

16.  City Council direct that Bloor Street West and Yonge Street be returned to its pre-construction traffic regulations and lane configurations when the project is completed.

 

17.  City Council direct the applicant to establish a construction management working group that meets monthly and invite local stakeholders including Transportation Services, Municipal Licensing and Standards, Toronto Building, adjacent neighbours, local resident groups, and local Business Improvement Areas.

 

18.  City Council direct the applicant to create a publicly accessible website with regular construction updates and post the website address on the site.

Background Information (Community Council)

(August 17, 2017) Report and Drawing No. 421G-2631 from the Acting Director, Transportation Services, Toronto and East York District on Construction Staging Area (Phase 1) - Yonge Street and Bloor Street West (1 Bloor Street West)
https://www.toronto.ca/legdocs/mmis/2017/te/bgrd/backgroundfile-106315.pdf

Motions (City Council)

Motion to Adopt Item (Carried)

Vote (Adopt Item) Oct-04-2017 6:43 PM

Result: Carried Majority Required - TE23.69 - Adopt the item
Total members that voted Yes: 32 Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Jon Burnside, Christin Carmichael Greb, Shelley Carroll, Gary Crawford, Joe Cressy, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Frank Di Giorgio, Sarah Doucette, Paula Fletcher, Michael Ford, Jim Hart, Stephen Holyday, Norman Kelly, Mike Layton, Chin Lee, Josh Matlow, Mary-Margaret McMahon, Joe Mihevc, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, Gord Perks, Anthony Perruzza, Neethan Shan, Michael Thompson, John Tory, Kristyn Wong-Tam
Total members that voted No: 5 Members that voted No are Justin J. Di Ciano, John Filion, Mary Fragedakis, Mark Grimes, Jaye Robinson
Total members that were Absent: 7 Members that were absent are John Campbell, Josh Colle, Michelle Holland, Jim Karygiannis, Giorgio Mammoliti, James Pasternak, David Shiner

TE26.69 - Construction Staging Area (Phase 1) - Yonge Street and Bloor Street West (1 Bloor Street West)

Decision Type:
ACTION
Status:
Amended
Ward:
27 - Toronto Centre-Rosedale

Community Council Recommendations

The Toronto and East York Community Council recommends that:

 

1.  City Council approve the closure of the west sidewalk and a 3 metre wide portion of the southbound curb lane on Yonge Street, and the provision of a temporary sidewalk in the curb lane, between Bloor Street West and a point 66 metres south, from October 9, 2017 to October 31, 2019.

 

2.  City Council approve the closure of the south sidewalk and a 1.2 metre wide portion of the eastbound curb lane on Bloor Street West, and the provision of a temporary sidewalk in the curb lane, between Yonge Street and a point 49 metres west, from October 9, 2017 to October 31, 2019.

 

3.  City Council prohibit southbound right-turns during all times at the intersection of Yonge Street and Bloor Street West.

 

4.  City Council rescind the existing stopping prohibition in effect from 7:30 a.m. to 9:30 a.m., Monday to Friday except public holidays on the west side of Yonge Street, between Bloor Street West and a point 66 metres south.

 

5.  City Council rescind the existing parking prohibition in effect during all times on the west side of Yonge Street, between Bloor Street West and a point 66 metres south.

 

6.  City Council prohibit stopping at all times on the west side of Yonge Street, between Bloor Street West and a point 66 metres south.

 

7.  City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

8.  City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

9.  City Council direct the applicant to sweep the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe.

 

10.  City Council direct the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe.

 

11.  City Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes.

 

12.  City Council direct the applicant where no cycling lanes exist, in consultation with Transportation Services, to install sharrow markings onto the roadway and display appropriate signage on the hoarding board to inform motorists and cyclists to safely share the road.

 

13.  City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night.

 

14.  City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications.

 

15.  City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

16.  City Council direct that Bloor Street West and Yonge Street be returned to its pre-construction traffic regulations and lane configurations when the project is completed.

 

17.  City Council direct the applicant to establish a construction management working group that meets monthly and invite local stakeholders including Transportation Services, Municipal Licensing and Standards, Toronto Building, adjacent neighbours, local resident groups, and local Business Improvement Areas.

 

18.  City Council direct the applicant to create a publicly accessible website with regular construction updates and post the website address on the site.

Origin

(August 17, 2017) Report from the Acting Director, Transportation Services, Toronto and East York District

Summary

As the Toronto Transit Commission (TTC) operates a transit service on Yonge Street and Bloor Street West, City Council approval of this report is required.

 

Mizrahi Developments is constructing a mixed-use development at 1 Bloor Street West. The development will consist of an 8-storey high retail podium and an 86-storey high residential tower. Construction of the development will be undertaken in several phases. This report deals with matters related to Phase 1 of the construction only, which includes excavation, piling and shoring operations and building to the ground level.

 

Transportation Services is requesting approval to close the west sidewalk and a portion of the southbound curb lane on Yonge Street and the south sidewalk and a portion of the eastbound curb lane on Bloor Street West fronting the site for a period of approximately 25 months. Pedestrian operations on Yonge Street and Bloor Street West will be maintained within the closed portion of the curb lanes.

Background Information

(August 17, 2017) Report and Drawing No. 421G-2631 from the Acting Director, Transportation Services, Toronto and East York District on Construction Staging Area (Phase 1) - Yonge Street and Bloor Street West (1 Bloor Street West)
https://www.toronto.ca/legdocs/mmis/2017/te/bgrd/backgroundfile-106315.pdf

Motions

1 - Motion to Amend Item (Additional) moved by Councillor Kristyn Wong-Tam (Carried)

That the Toronto and East York Community recommends:

 

1.  City Council direct the applicant to sweep the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe.


 2.  City Council direct the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe.


 3.  City Council direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes.


 4.  In areas where no cycling lanes exist, City Council direct the applicant, in consultation with Transportation Services, to install sharrow markings onto the roadway and display appropriate signage on the hoarding board to inform motorists and cyclist to safely share the road.


 5.  City Council direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night.


 6.  City Council direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications.


 7.  City Council direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

8.  City Council direct the applicant to establish a construction management working group that meets monthly and invite local stakeholders including Transportation Services, Municipal Licensing & Standards, Toronto Buildings, adjacent neighbours, local resident groups, and local BIAs.

 

9.  City Council direct the applicant to create a publicly accessible website with regular construction updates and post the website address on the site.


2 - Motion to Adopt Item as Amended moved by Councillor Kristyn Wong-Tam (Carried)

Vote (Adopt Item as Amended) Sep-06-2017

Result: Carried Majority Required
Total members that voted Yes: 9 Members that voted Yes are Joe Cressy, Janet Davis, Paula Fletcher, Mike Layton, Josh Matlow, Mary-Margaret McMahon, Joe Mihevc, Gord Perks, Kristyn Wong-Tam (Chair)
Total members that voted No: 1 Members that voted No are Mary Fragedakis
Total members that were Absent: 1 Members that were absent are Ana Bailão