Tracking Status

  • This item was considered by Toronto and East York Community Council on September 6, 2017 and was adopted with amendments. City Council has delegated authority for this matter to the Toronto and East York Community Council and therefore, the decision is final.

TE26.65 - Construction Staging Area Time Extension - 31-35 Dundonald Street

Decision Type:
ACTION
Status:
Amended
Schedule Type:
Delegated
Ward:
27 - Toronto Centre-Rosedale

Community Council Decision

The Toronto and East York Community Council:

 

1.  Approved the continuation of the closure of the sidewalk and a portion of the westbound lane on the south side of Dundonald Street, between a point 155.08 metres east of Yonge Street and a point 190.32 metres east of Yonge Street, from October 1, 2017 to December 31, 2019.

 

2.   Approved the continuation of "No Stopping, Anytime" restriction on the south side of Dundonald Street, between a point 155.08 metres east of Yonge Street and a point 190.32 metres east of Yonge Street.

 

3.   Directed the applicant to continue posting a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.

 

3.   Directed the applicant to continue providing and installing public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

 

4.  Directed the applicant to sweep the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe.


 5.  Directed the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe.


 6.  Direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes.


 7.  In areas where no cycling lanes exist, directed the applicant, in consultation with Transportation Services, to install sharrow markings onto the roadway and display appropriate signage on the hoarding board to inform motorists and cyclist to safely share the road.


 8.  Directed the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night.


 9.  Directed the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications.


10.  Directed the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

11.  Directed the applicant to establish a construction management working group that meets monthly and invite local stakeholders including Transportation Services, Municipal Licensing and Standards, Toronto Building, adjacent neighbours, local resident groups, and local Business Improvement Areas.

 

12.  Directed the applicant to create a publicly accessible website with regular construction updates and post the website address on the site.

 

13.   Directed Dundonald Street be returned to its pre-construction traffic and parking regulations when the project is complete.

Origin

(August 14, 2017) Report from the Acting Director, Transportation Services, Toronto and East York District

Summary

This staff report is about a matter that Community Council has delegated authority to make a final decision provided that it is not amended so that it varies with City policy or by-laws.

 

Plazacorp Investments Limited is constructing a 37-storey residential condominium building and 10 townhomes at 31-35 Dundonald Street. The site is also known by "50 Wellesley Street East". The sidewalk and a portion of the westbound lane on Dundonald Street fronting the site are currently closed to accommodate construction staging operations for the development.

 

Toronto and East York Community Council, at its meeting on January 19, 2016, approved the subject construction staging area on Dundonald Street, from December 1, 2015 to September 30, 2017. Transportation Services is requesting approval to extend the duration of the subject construction staging area from October 1, 2017 to December 31, 2019 in order to complete the construction of the development.

Background Information

(August 14, 2017) Report and Drawing No. 421G-2642 from the Acting Director, Transportation Services, Toronto and East York District on Construction Staging Area Time Extension - 31-35 Dundonald Street
https://www.toronto.ca/legdocs/mmis/2017/te/bgrd/backgroundfile-106278.pdf

Motions

1 - Motion to Amend Item (Additional) moved by Councillor Kristyn Wong-Tam (Carried)

That the Toronto and East York Community Council:

 

1.  Direct the applicant to sweep the construction site daily and nightly, or more frequently as needed to be cleared of any construction debris and made safe.


 2.  Direct the applicant to pressure wash the construction site and adjacent sidewalks and roadways weekly, or more frequently as needed to be cleared of any construction debris and made safe.


 3.  Direct the applicant, in consultation with Transportation Services, to maintain any bike lanes, and install appropriate signage to inform drivers and cyclists of any changes to the cycling lanes.


 4.  In areas where no cycling lanes exist, direct the applicant, in consultation with Transportation Services, to install sharrow markings onto the roadway and display appropriate signage on the hoarding board to inform motorists and cyclist to safely share the road.


 5.  Direct the applicant to ensure that the existing sidewalks or the proposed pedestrian walkway have proper lighting to ensure safety and visibility at all times of the day and night.


 6.  Direct the applicant to clearly consult and communicate all construction, parking and road occupancy impacts with local business improvement areas and resident associations in advance of any physical road modifications.


 7.  Direct the applicant to install appropriate signage and converging mirrors to ensure that pedestrians, cyclists and motorists safety is considered at all times.

 

8.  Direct the applicant to establish a construction management working group that meets monthly and invite local stakeholders including Transportation Services, Municipal Licensing & Standards, Toronto Buildings, adjacent neighbours, local resident groups, and local BIAs.

 

9.  Direct the applicant to create a publicly accessible website with regular construction updates and post the website address on the site.

 


2 - Motion to Adopt Item as Amended moved by Councillor Kristyn Wong-Tam (Carried)

Vote (Adopt Item as Amended) Sep-06-2017

Result: Carried Majority Required
Total members that voted Yes: 9 Members that voted Yes are Joe Cressy, Janet Davis, Paula Fletcher, Mike Layton, Josh Matlow, Mary-Margaret McMahon, Joe Mihevc, Gord Perks, Kristyn Wong-Tam (Chair)
Total members that voted No: 1 Members that voted No are Mary Fragedakis
Total members that were Absent: 1 Members that were absent are Ana Bailão