Item - 2017.EX27.27
Tracking Status
- City Council adopted this item on October 2, 3 and 4, 2017 without amendments.
- This item was considered by the Executive Committee on September 26, 2017 and adopted without amendment. It will be considered by City Council on October 2, 3 and 4, 2017.
- See also BU34.12
EX27.27 - Toronto Public Library - 2017 Capital Budget Adjustments (Second Quarter)
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
City Council Decision
City Council on October 2, 3 and 4, 2017, adopted the following:
1. City Council authorize the deferral and acceleration of cash flows within the projects in Toronto Public Library's 2017 Council Approved Capital Budget and future year commitments in the amount of $2.746 million, as set out in Appendix A to the report (August 11, 2017) from the City Librarian, with zero gross and debt budget impact.
2. City Council increase the 2017 capital budget by $1.278 million gross funded by development charges composed of:
a. an increase of $0.300 million gross and a reduction in debt of $0.978 million to the Albion Library project funded by an increase of $1.278 million development charges; and
b. the application of the $0.978 million of debt freed up from the Albion Library project to the Multi-Branch State of Good Repair project, as set out in Appendix B to the report (August 11, 2017) from the City Librarian.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-106637.pdf
(August 11, 2017) Report from the City Librarian on Toronto Public Library - 2017 Capital Budget Adjustments (Second Quarter)
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-106610.pdf
Appendix A - Deferrals/Accelerations - Toronto Public Library 2017 Capital Budget and 2018-2026 Capital Plan Adjustments
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-106611.pdf
Appendix B - Adjustments to Cash Flow and Project Costs - Toronto Public Library 2017 Capital Budget
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-106612.pdf
Motions (City Council)
Vote (Adopt Item) Oct-02-2017 2:22 PM
| Result: Carried | Majority Required - EX27.27 - Adopt the item |
|---|---|
| Total members that voted Yes: 39 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Jon Burnside, John Campbell, Christin Carmichael Greb, Shelley Carroll, Josh Colle, Gary Crawford, Joe Cressy, Janet Davis, Glenn De Baeremaeker, Justin J. Di Ciano, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Michael Ford, Mary Fragedakis, Mark Grimes, Jim Hart, Michelle Holland, Stephen Holyday, Jim Karygiannis, Norman Kelly, Chin Lee, Giorgio Mammoliti, Josh Matlow, Mary-Margaret McMahon, Joe Mihevc, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, Gord Perks, Anthony Perruzza, Neethan Shan, Michael Thompson, John Tory, Kristyn Wong-Tam |
| Total members that voted No: 0 | Members that voted No are |
| Total members that were Absent: 5 | Members that were absent are Vincent Crisanti, Mike Layton, James Pasternak, Jaye Robinson, David Shiner |
Declared Interests (City Council)
Councillor James Pasternak - as his wife, while on leave, remains an employee of the Toronto Public Library.
EX27.27 - Toronto Public Library - 2017 Capital Budget Adjustments (Second Quarter)
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Executive Committee recommends that:
1. City Council authorize the deferral and acceleration of cash flows within the projects in Toronto Public Library's 2017 Council Approved Capital Budget and future year commitments in the amount of $2.746 million, as included in Appendix A to the report (August 11, 2017) from the City Librarian, with zero gross and debt budget impact.
2. City Council increase the 2017 capital budget by $1.278 million gross funded by development charges which is comprised of:
a. an increase of $0.300 million gross and a reduction in debt of $0.978 million to the Albion Library project funded by an increase of $1.278 million development charges.
b. the application of the $0.978 million of debt freed up from Albion Library project to the Multi-Branch State of Good Repair project, as shown in Appendix B to the report (August 11, 2017) from the City Librarian.
Origin
Summary
This report requests City Council's authority to amend the Toronto Public Library (TPL) 2017 Council Approved Capital Budget and 2018-2026 Capital Plan by adjusting cash flows contained within the Budget and Plan, respectively, to align forecasted project accelerations and deferrals. Additional budget reallocations to project costs and cash flows are requested where actual spending exceed the current approved cash flow. The adjustments will have a zero debt impact on the 2017 Capital Budget and 2018-2026 Capital Plan and will align the 2017 Capital Budget to Toronto Public Library's capital project delivery schedule and program requirements.
Background Information
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-106637.pdf
(August 11, 2017) Report from the City Librarian on Toronto Public Library - 2017 Capital Budget Adjustments (Second Quarter)
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-106610.pdf
Appendix A - Deferrals/Accelerations - Toronto Public Library 2017 Capital Budget and 2018-2026 Capital Plan Adjustments
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-106611.pdf
Appendix B - Adjustments to Cash Flow and Project Costs - Toronto Public Library 2017 Capital Budget
https://www.toronto.ca/legdocs/mmis/2017/ex/bgrd/backgroundfile-106612.pdf
Motions
Declared Interests
Councillor James Pasternak - as his spouse is an employee of Toronto Public Library.