Item - 2016.EY14.11
Tracking Status
- This item was considered by Etobicoke York Community Council on May 10, 2016 and was adopted with amendments.
EY14.11 - Preliminary Report - 3415-3499 Weston Road (Phase 2) - Official Plan and Zoning By-law Amendment and Lifting of the (H) Holding Symbol Applications
- Decision Type:
- ACTION
- Status:
- Amended
- Ward:
- 7 - York West
Community Council Decision
Etobicoke York Community Council:
1. Directed that Notice for the public meeting under the Planning Act be given according to the regulations of the Planning Act.
2. Directed the Chief Planner and Executive Director, City Planning, through the process of the review of the current application, to:
a. Undertake a review of the community benefits previously secured in 2002 for the entire four phase development as part of the Master Plan process to confirm what has been provided to date and what remains outstanding as reflected by the current application and future Phases 3 and 4.
b. Identify the following community benefits as a priority: the construction of the public square; pedestrian access across Weston Road; intersection improvements at Weston Road and Finch Avenue including the provision of a turning circle; pedestrian access through this development to Emery Village Collegiate Institute to the south; integration with the proposed path(s) through the abutting hydro corridor; open space improvements in the immediate area; and community space in the development.
Origin
Summary
The applications propose an Official Plan and Zoning By-law Amendment and to lift the (H) Holding Symbol to permit a mixed-use development having a total of 540 residential units within a 27-storey apartment building and a 22-storey apartment building at 3415-3499 Weston Road. The application proposes 185m2 of non-residential space for a community centre in the ground floor of the 22-storey building. This development would have a Floor Space Index of 7.1 times the area of the lot. Vehicular access to the site is proposed from new streets connecting to Weston Road through the Phase 1 lands to the west. A total of 540 parking spaces are proposed in a two storey above grade parking garage.
This application is Phase 2 of a four phased development comprised of 10 buildings, currently planned to contain approximately 1,471 residential units and 4,459 m2 of commercial floor area.
This report provides preliminary information on the above-noted applications and seeks Community Council's directions on further processing of the applications and on the community consultation process.
A community consultation meeting scheduled by staff, in consultation with the Ward Councillor, is targeted to be held in the second quarter of 2016. A Final Report and statutory public meeting under the Planning Act to consider the applications is targeted for the first quarter of 2017. This target assumes the applicant will provide all required information in a timely matter.
Background Information
https://www.toronto.ca/legdocs/mmis/2016/ey/bgrd/backgroundfile-91948.pdf
Communications
https://www.toronto.ca/legdocs/mmis/2016/ey/comm/communicationfile-59839.pdf
Motions
That Etobicoke York Community Council amend the recommendations contained in the report (March 8, 2016) from the Director, Community Planning, Etobicoke York District, by:
1. deleting Recommendations 1 and 2;
2. adopting Recommendation 3; and
3. adding the following new recommendation:
Through the process of the review of the current application, Etobicoke York Community Council direct the Chief Planner and Executive Director, City Planning to:
a. Undertake a review of the community benefits previously secured in 2002 for the entire four phase development as part of the Master Plan process to confirm what has been provided to date and what remains outstanding as reflected by the current application and future Phases 3 and 4.
b. Identify the following community benefits as a priority: the construction of the public square; pedestrian access across Weston Road; intersection improvements at Weston Road and Finch Avenue including the provision of a turning circle; pedestrian access through this development to Emery Village Collegiate Institute to the south; integration with the proposed path(s) through the abutting hydro corridor; open space improvements in the immediate area; and community space in the development.
Vote (Adopt Item as Amended) May-10-2016
| Result: Carried | Majority Required - EY14.11 - Mammoliti - motion 1 |
|---|---|
| Total members that voted Yes: 8 | Members that voted Yes are John Campbell, Justin J. Di Ciano, Sarah Doucette, Mark Grimes (Chair), Stephen Holyday, Giorgio Mammoliti, Frances Nunziata, Cesar Palacio |
| Total members that voted No: 1 | Members that voted No are Frank Di Giorgio |
| Total members that were Absent: 1 | Members that were absent are Vincent Crisanti |