City Council on December 13, 14 and 15, 2016, adopted the following:
1. City Council approve the 2017 Interim Operating Estimates totalling $2.506 billion as detailed by City Program and Agency in Appendix 1 to the report (November 23, 2016) from the Deputy City Manager and Chief Financial Officer.
2. City Council approve the 2017 Interim Capital Estimates totalled $929.952 million in gross expenditures and financing of $349.399 million in debt funding; $188.283 million in Provincial and Federal funding; $225.633 million in Reserve/Reserve Funds funding; $66.406 million in Development Charges and $100.231 million in Third Party and Other funding as detailed by City Program and Agency in Appendix 2 to the report (November 23, 2016) from the Deputy City Manager and Chief Financial Officer.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2016/ex/bgrd/backgroundfile-98677.pdf
Motions (City Council)
Vote (Adopt Item) Dec-14-2016 2:12 PM
| Result: Carried | Majority Required - EX20.45 - Adopt the item |
|---|---|
| Total members that voted Yes: 39 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Jon Burnside, John Campbell, Josh Colle, Gary Crawford, Joe Cressy, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Justin J. Di Ciano, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Michael Ford, Mary Fragedakis, Mark Grimes, Michelle Holland, Stephen Holyday, Jim Karygiannis, Norman Kelly, Mike Layton, Chin Lee, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, Gord Perks, Anthony Perruzza, Jaye Robinson, David Shiner, Michael Thompson, John Tory, Kristyn Wong-Tam |
| Total members that voted No: 1 | Members that voted No are Giorgio Mammoliti |
| Total members that were Absent: 4 | Members that were absent are Christin Carmichael Greb, Shelley Carroll, Ron Moeser, James Pasternak |
EX20.45 - 2017 Interim Estimates
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Executive Committee recommends that:
1. City Council approve the 2017 Interim Operating Estimates totalling $2.506 billion as detailed by City Program and Agency in Appendix 1 to the report (November 23, 2016) from the Deputy City Manager and Chief Financial Officer.
2. City Council approve the 2017 Interim Capital Estimates totalled $929.952 million in gross expenditures and financing of $349.399 million in debt funding; $188.283 million in Provincial and Federal funding; $225.633 million in Reserve/Reserve Funds funding; $66.406 million in Development Charges and $100.231 million in Third Party and Other funding as detailed by City Program and Agency in Appendix 2 to the report (November 23, 2016) from the Deputy City Manager and Chief Financial Officer.
Origin
Summary
In accordance with the City of Toronto Act (CoTA) and Financial Control By-Law, Interim Budget Estimates must be approved prior to January 1, 2017 to ensure that appropriate Council approval is granted to fund the continuance of the City's business until 2017 Operating and Capital Budgets are approved by City Council.
The 2017 Tax supported Operating and Capital Budgets are scheduled to be approved by City Council on February 15 and 16, 2017. The purpose of this report is to establish the 2017 Interim Operating and Capital Estimates in order to enable City Programs and Agencies to have necessary spending authority to carry out their ongoing base operations and to continue work on previously approved urgent capital projects until the 2017 Operating and Capital Budgets are approved by City Council and uploaded in the City financial system.
The 2017 Tax Supported Interim Operating Estimates are $2.506 billion gross and requires cash outflow funding of $2.139 billion. The 2017 Tax Supported Interim Capital Estimates total $929.952 million gross expenditures that require debenture financing of $349.399 million.