PW6.2 - Applying Acceleration and Delay Costs in Construction Contracts

Decision Type:
ACTION
Status:
Adopted
Wards:
All

City Council Decision

City Council on July 7, 8 and 9, 2015, adopted the following:

 

1.   City Council authorize the Executive Director, Engineering and Construction Services and the Director, Purchasing and Materials Management Division to pilot the application of acceleration and delay costs in construction contracts for work within the municipal right-of-way, where the traffic disruption is expected to be significant.

 

2.   City Council authorize the Executive Director, Engineering and Construction Services and the Director, Purchasing and Material Management Division to pilot the application of a cost plus time tender process, for construction projects within the municipal right of way, where traffic disruption is expected to be significant.

 

3.   City Council authorize the Executive Director, Engineering and Construction Services and the Director, Purchasing and Material Management Division to report back to Public Works and Infrastructure Committee in 2017 on the outcomes of Parts 1 and 2 above, including:

 

a.  capital cost impact;

 

b.  reduction in duration of construction schedule;

 

c.  operational issues which may have arisen;

 

d.  competitiveness of the bidding process;

 

e.  response from the construction industry; and

 

f.  recommendations for changes, if any, to the City's construction contract procurement process.

Background Information (Committee)

(May 29, 2015) Report from the Executive Director, Engineering and Construction Services and the Director, Purchasing and Materials Management on Applying Acceleration and Delay Costs in Construction Contracts
https://www.toronto.ca/legdocs/mmis/2015/pw/bgrd/backgroundfile-81105.pdf

Motions (City Council)

Motion to Adopt Item (Carried)

Vote (Adopt Item) Jul-08-2015 2:16 PM

Result: Carried Majority Required - PW6.2 - Adopt the item
Total members that voted Yes: 39 Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Michelle Berardinetti, Jon Burnside, John Campbell, Christin Carmichael Greb, Shelley Carroll, Raymond Cho, Josh Colle, Gary Crawford, Joe Cressy, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Justin J. Di Ciano, Sarah Doucette, Paula Fletcher, Rob Ford, Mary Fragedakis, Stephen Holyday, Jim Karygiannis, Norman Kelly, Mike Layton, Chin Lee, Giorgio Mammoliti, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Denzil Minnan-Wong, Ron Moeser, Frances Nunziata (Chair), Cesar Palacio, Gord Perks, Anthony Perruzza, Jaye Robinson, David Shiner, Michael Thompson, Kristyn Wong-Tam
Total members that voted No: 0 Members that voted No are
Total members that were Absent: 6 Members that were absent are Frank Di Giorgio, John Filion, Mark Grimes, Josh Matlow, James Pasternak, John Tory

PW6.2 - Applying Acceleration and Delay Costs in Construction Contracts

Decision Type:
ACTION
Status:
Adopted
Wards:
All

Committee Recommendations

The Public Works and Infrastructure Committee recommends that:

 

1.   City Council authorize the Executive Director, Engineering and Construction Services and the Director, Purchasing and Materials Management Division to pilot the application of acceleration and delay costs in construction contracts for work within the municipal right-of-way, where the traffic disruption is expected to be significant.

 

2.   City Council authorize the Executive Director, Engineering and Construction Services and the Director of Purchasing and Material Management Division to pilot the application of a cost plus time tender process, for construction projects within the municipal right of way, where traffic disruption is expected to be significant.

 

3.   City Council authorize the Executive Director, Engineering and Construction Services and the Director of Purchasing and Material Management Division to report back to Public Works and Infrastructure Committee in 2017 on the outcomes of Recommendation No. 1 and No. 2 including:

 

a.  capital cost impact;

 

b.  reduction in duration of construction schedule;

 

c.  operational issues which may have arisen;

 

d.  competitiveness of the bidding process;

 

e.  response from the construction industry; and

 

f.  recommendations for changes, if any, to the City's construction contract procurement process.

Origin

(May 29, 2015) Report from the Executive Director, Engineering and Construction Services and the Director, Purchasing and Materials Management

Summary

The construction of sewers, watermains and roads is disruptive to traffic operations because it typically occupies road lanes. When this work is undertaken on major roads with high volumes of vehicular traffic, the disruption can be quite significant.

 

This report proposes to pilot, in 2015 and 2016, the potential benefits of (1) the application of acceleration and delay costs in construction contracts; and (2) a cost plus time tendering approach. Based on experience in other jurisdictions, these contracting methods may help expedite the completion of construction projects within the City's rights-of-way, and thereby reduce traffic impacts.

Background Information

(May 29, 2015) Report from the Executive Director, Engineering and Construction Services and the Director, Purchasing and Materials Management on Applying Acceleration and Delay Costs in Construction Contracts
https://www.toronto.ca/legdocs/mmis/2015/pw/bgrd/backgroundfile-81105.pdf