PW2.12 - Modernizing Toronto's Streetlights
- Decision Type:
- ACTION
- Status:
- Amended
- Wards:
- All
City Council Decision
City Council on March 31, April 1 and 2, 2015, adopted the following:
1. City Council direct the General Manager, Transportation Services to engage with Toronto Hydro to develop a plan to convert Toronto's streetlights to more energy efficient technologies and report to the Public Works and Infrastructure Committee by the second quarter of 2015, such report to include:
a. business case and strategies to fund conversion of Toronto's existing streetlights including incentives and grants from other levels of government;
b. survey of new street lighting technologies;
c. potential energy savings from conversion;
d. capital and operational costs of conversion;
e. potential roll out strategies and timing for conversion of Toronto's existing streetlights; and
f. options to replace old transit poles that are now being used by Toronto Hydro for electrical services and street lighting.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2015/pw/bgrd/backgroundfile-76410.pdf
Motions (City Council)
That City Council amend the Public Works and Infrastructure Committee recommendation by adding a new part f. so that it now reads as follows:
1. City Council direct the General Manager of Transportation Services to engage with Toronto Hydro to develop a plan to convert Toronto's streetlights to more energy efficient technologies and report to the Public Works and Infrastructure Committee by the second quarter of 2015. The report will include:
a. business case and strategies to fund conversion of Toronto's existing streetlights including incentives and grants from other levels of government;
b. survey of new street lighting technologies;
c. potential energy savings from conversion;
d. capital and operational costs of conversion;
e. potential roll out strategies and timing for conversion of Toronto's existing streetlights; and
f. options to replace old transit poles that are now being used by Toronto Hydro for electrical services and street lighting.
Vote (Amend Item) Mar-31-2015 2:24 PM
| Result: Carried | Majority Required - PW2.12 - Shiner - motion 1 |
|---|---|
| Total members that voted Yes: 39 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Jon Burnside, John Campbell, Christin Carmichael Greb, Shelley Carroll, Raymond Cho, Josh Colle, Gary Crawford, Joe Cressy, Janet Davis, Glenn De Baeremaeker, Justin J. Di Ciano, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Rob Ford, Mary Fragedakis, Stephen Holyday, Jim Karygiannis, Mike Layton, Chin Lee, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Denzil Minnan-Wong, Ron Moeser, Frances Nunziata (Chair), Cesar Palacio, Gord Perks, Anthony Perruzza, Jaye Robinson, David Shiner, Michael Thompson, John Tory, Kristyn Wong-Tam |
| Total members that voted No: 0 | Members that voted No are |
| Total members that were Absent: 6 | Members that were absent are Michelle Berardinetti, Vincent Crisanti, Mark Grimes, Norman Kelly, Giorgio Mammoliti, James Pasternak |
Vote (Adopt Item as Amended) Mar-31-2015 2:25 PM
| Result: Carried | Majority Required - PW2.12 - Adopt the item as amended |
|---|---|
| Total members that voted Yes: 39 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Jon Burnside, John Campbell, Christin Carmichael Greb, Shelley Carroll, Raymond Cho, Josh Colle, Gary Crawford, Joe Cressy, Janet Davis, Glenn De Baeremaeker, Justin J. Di Ciano, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Rob Ford, Mary Fragedakis, Stephen Holyday, Jim Karygiannis, Mike Layton, Chin Lee, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Denzil Minnan-Wong, Ron Moeser, Frances Nunziata (Chair), Cesar Palacio, Gord Perks, Anthony Perruzza, Jaye Robinson, David Shiner, Michael Thompson, John Tory, Kristyn Wong-Tam |
| Total members that voted No: 0 | Members that voted No are |
| Total members that were Absent: 6 | Members that were absent are Michelle Berardinetti, Vincent Crisanti, Mark Grimes, Norman Kelly, Giorgio Mammoliti, James Pasternak |
PW2.12 - Modernizing Toronto's Streetlights
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Public Works and Infrastructure Committee recommends that:
1. City Council direct the General Manager of Transportation Services to engage with Toronto Hydro to develop a plan to convert Toronto's streetlights to more energy efficient technologies and report to the Public Works and Infrastructure Committee by the second quarter of 2015. The report will include:
a. business case and strategies to fund conversion of Toronto's existing streetlights including incentives and grants from other levels of government;
b. survey of new street lighting technologies;
c. potential energy savings from conversion;
d. capital and operational costs of conversion; and
e. potential roll out strategies and timing for conversion of Toronto's existing streetlights.
Origin
Summary
It has been 22 years since the City of Toronto updated its streetlights, in that time technological advances have created lights that last longer, provide enhanced illumination, and are more energy efficient. Our streetlights currently use costly and inefficient metal halide and high-pressure sodium light bulbs to illuminate our streets and sidewalks. Conversion to light-emitting diode (L.E.D.) and other energy-efficient lighting technology has been proven to save money and reduce energy consumption in cities such as Los Angeles, Philadelphia, and Mississauga.
The Service Level Agreement between Toronto Hydro and the City of Toronto will be re-negotiated in 2016 which provides an opportunity to modernize our wasteful and costly streetlight infrastructure. Therefore, I am requesting that Transportation Services and Toronto Hydro study the issue and develop a plan to covert our streetlights to a more financially and environmentally sustainable technology in time for the 2016 budget cycle.