EX43.29 - Capital Variance Report for the Year Ended December 31, 2013

Decision Type:
ACTION
Status:
Amended
Wards:
All

City Council Decision

City Council on July 8, 9, 10 and 11, 2014, adopted the following:

 

1.         City Council approve in-year budget adjustments to the Toronto Water's 2013 Approved Capital Budget and Plan detailed in Appendix 2 to the report (June 4, 2014) from the Deputy City Manager and Chief Financial Officer with no incremental impact on debt funding.

 

2.         City Council approve additional carry forward funding of $0.046 million in unspent capital funding from 2013 for Children Services as detailed in Appendix 3 to the report (June 4, 2014) from the Deputy City Manager and Chief Financial Officer, in order to continue work on previously approved capital project, and that the 2014 Approved Capital Budget be adjusted accordingly with no incremental impact on debt.

 

3.         City Council receive for information Appendix 4 to the report (June 4, 2014) from the Deputy City Manager and Chief Financial Officer which lists 67 capital projects/sub-projects that have been completed and are to be closed, having a total project budget saving of $35.354 million, including savings of $31.660 million in debt funding.

 

4.         In order to increase the completion rate for capital projects, City Council direct the Executive Director, Human Resources in collaboration with the Executive Director, Engineering and Construction Services; General Manager, Toronto Water; General Manager, Transportation Services; and the Chief Corporate Officer to undertake a review of salary compensation for professional engineer and project management professionals within GTA municipalities and within the private sector, and report to the Employee and Labour Relations Committee, in the first quarter of 2015, with recommendations to consider possible adjustments to current salary ranges for these types of positions, to ensure that salaries offered by the City of Toronto are not an impediment to recruitment and staff retention.

 

5.         City Council authorize and direct the appropriate City Officials to take the necessary action to give effect to City Council's decision.

Background Information (Committee)

(June 20, 2014) Letter from the Budget Committee on Capital Variance Report for the Year Ended December 31, 2013
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70893.htm
(June 4, 2014) Report from the Deputy City Manager and Chief Financial Officer on Capital Variance Report for the Year Ended December 31, 2013
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70921.pdf
Appendix 1 - 2013 Consolidated Capital Variance Report for the Year Ended December 31, 2013
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70919.pdf
Appendix 2 - In-Year adjustments
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70920.pdf
Appendix 3 - 2013 Carry Forwards Funding Adjustments
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70917.pdf
Appendix 4 - Closed Capital Projects
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70922.pdf
Appendix 5 - Capital Variance Explanation - Programs/Agencies
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70918.pdf
Appendix 5 - REVISED Capital Variance Explanation - Programs/Agencies
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-71021.pdf

Motions (City Council)

1 - Motion to Amend Item (Additional) moved by Councillor Gord Perks (Carried)

That:

 

1.         In order to increase the completion rate for capital projects, City Council direct the Executive Director, Human Resources in collaboration with the Executive Director, Engineering and Construction Services; General Manager, Toronto Water; General Manager, Transportation Services; and the Chief Corporate Officer to undertake a review of salary compensation for professional engineer and project management professionals within GTA municipalities and within the private sector, and report to the Employee and Labour Relations Committee, in the first quarter of 2015, with recommendations to consider possible adjustments to current salary ranges for these types of positions, to ensure that salaries offered by the City of Toronto are not an impediment to recruitment and staff retention.

Vote (Amend Item (Additional)) Jul-10-2014 7:34 PM

Result: Carried Majority Required - EX43.29 - Perks - motion 1
Total members that voted Yes: 26 Members that voted Yes are Maria Augimeri, Michelle Berardinetti, Shelley Carroll, Josh Colle, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Sarah Doucette, John Filion, Paula Fletcher, Mark Grimes, Norman Kelly, Mike Layton, Chin Lee, Peter Leon, James Maloney, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Frances Nunziata (Chair), Gord Perks, Ceta Ramkhalawansingh, David Shiner, Michael Thompson, Kristyn Wong-Tam
Total members that voted No: 2 Members that voted No are Rob Ford, Denzil Minnan-Wong
Total members that were Absent: 17 Members that were absent are Paul Ainslie, Ana Bailão, Raymond Cho, Gary Crawford, Vincent Crisanti, Frank Di Giorgio, Doug Ford, Mary Fragedakis, Gloria Lindsay Luby, Giorgio Mammoliti, Ron Moeser, Cesar Palacio, John Parker, James Pasternak, Anthony Perruzza, Jaye Robinson, Karen Stintz

Motion to Adopt Item as Amended (Carried)

Vote (Adopt Item as Amended) Jul-10-2014 7:35 PM

Result: Carried Majority Required - EX43.29 - Adopt the item as amended
Total members that voted Yes: 29 Members that voted Yes are Maria Augimeri, Michelle Berardinetti, Shelley Carroll, Raymond Cho, Josh Colle, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Sarah Doucette, John Filion, Paula Fletcher, Mark Grimes, Norman Kelly, Mike Layton, Chin Lee, Peter Leon, James Maloney, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Denzil Minnan-Wong, Frances Nunziata (Chair), Gord Perks, Ceta Ramkhalawansingh, Jaye Robinson, David Shiner, Michael Thompson, Kristyn Wong-Tam
Total members that voted No: 1 Members that voted No are Rob Ford
Total members that were Absent: 15 Members that were absent are Paul Ainslie, Ana Bailão, Gary Crawford, Vincent Crisanti, Frank Di Giorgio, Doug Ford, Mary Fragedakis, Gloria Lindsay Luby, Giorgio Mammoliti, Ron Moeser, Cesar Palacio, John Parker, James Pasternak, Anthony Perruzza, Karen Stintz

EX43.29 - Capital Variance Report for the Year Ended December 31, 2013

Decision Type:
ACTION
Status:
Adopted
Wards:
All

Committee Recommendations

The Executive Committee recommends that:

 

1.         City Council approve in-year budget adjustments to the Toronto Water's 2013 Approved Capital Budget and Plan detailed in Appendix 2 to the report (June 4, 2014) from the Deputy City Manager and Chief Financial Officer with no incremental impact on debt funding

 

2.         City Council approve additional carry forward funding of $0.046 million in unspent capital funding from 2013 for Children Services as detailed in Appendix 3 to the report (June 4, 2014) from the Deputy City Manager and Chief Financial Officer, in order to continue work on previously approved capital project, and that the 2014 Approved Capital Budget be adjusted accordingly with no incremental impact on debt.

 

3.         City Council receive for information Appendix 4 to the report (June 4, 2014) from the Deputy City Manager and Chief Financial Officer which lists 67 capital projects/sub-projects that have been completed and are to be closed, having a total project budget saving of $35.354 million, including savings of $31.660 million in debt funding.

 

4.         City Council authorize and direct the appropriate City Officials to take the necessary action to give effect thereto.

Origin

(June 20, 2014) Letter from the Budget Committee

Summary

The purpose of this report is to provide Council with the City of Toronto Capital Variance for the year-ended December 31, 2013, to seek Council’s approval for in-year budget and 2013 carry forward funding adjustments that have no incremental impact on debt.

 

Capital expenditures for the twelve months ended December 31, 2013 totalled $2.386 billion or 57.9 percent of the 2013 Approved Capital Budget of $4.125 billion (see Table 1).  This spending pattern is consistent with prior years.  As detailed by City Program and Agency in Appendix 1, it is noted that 14 of 33 City Programs and Agencies spent in excess of 60 percent of their respective 2013 Approved Capital Budget.

 

For the twelve-months period ended December 31, 2013, Tax Supported Programs and Agencies reported capital expenditures of $1.837 billion representing 55.7 percent of their collective 2013 Approved Capital Budget of $3.298 billion; Rate Supported Programs reported capital expenditures of $548.752 million, representing 66.3 percent of their collective 2013 Approved Capital Budget of $827.125 million.

 

(See Table 1 of the Report dated June 4, 2014 from the Deputy City Manager and Chief Financial Officer)

 

The rate of spending in 2013  was driven largely by difficulty in finding and securing suitable sites for constructions in accordance with initially planned timeframes; delays in securing funds from cost-sharing partners; longer than planned timelines to obtain necessary approvals or required permits; extensive community consultations; delays in tendering contracts; unanticipated delays in construction start-up; and resources constraints.  Unspent funds for projects that have not been completed have been carried forward to 2014 on an as needed basis, in accordance with the City's Carry Forward Policy. 

 

In addition, several projects were completed under-budget. Through this report staff recommends closing 67 projects which have came in under budget by $35.354 million.

Background Information

(June 20, 2014) Letter from the Budget Committee on Capital Variance Report for the Year Ended December 31, 2013
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70893.htm
(June 4, 2014) Report from the Deputy City Manager and Chief Financial Officer on Capital Variance Report for the Year Ended December 31, 2013
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70921.pdf
Appendix 1 - 2013 Consolidated Capital Variance Report for the Year Ended December 31, 2013
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70919.pdf
Appendix 2 - In-Year adjustments
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70920.pdf
Appendix 3 - 2013 Carry Forwards Funding Adjustments
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70917.pdf
Appendix 4 - Closed Capital Projects
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70922.pdf
Appendix 5 - Capital Variance Explanation - Programs/Agencies
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70918.pdf
Appendix 5 - REVISED Capital Variance Explanation - Programs/Agencies
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-71021.pdf

Motions

Motion to Adopt Item moved by Councillor Frank Di Giorgio (Carried)