Item - 2014.EX43.14

Tracking Status

  • City Council adopted this item on July 8, 2014 without amendments.
  • This item was considered by Executive Committee on July 2, 2014 and was adopted with amendments. It will be considered by City Council on July 8, 2014.

EX43.14 - Pan/Parapan American Games Capital Projects Update

Decision Type:
ACTION
Status:
Adopted
Wards:
All

City Council Decision

City Council on July 8, 9, 10 and 11, 2014, adopted the following:

 

1.         City Council amend the 2014 Approved Capital Budget for Pan Am Games to increase the total project cost for the BMX Track capital sub-project by $2.413 million from $1.547 million to $3.96 million, funded by redirecting up to $1.054 million in City debt funding from the Toronto Pan Am Sports Centre capital sub-project, conditional on the remaining required share of up to $1.359 million being committed by the Government of Canada in order to maintain the 44 percent (City of Toronto) / 56 percent (Government of Canada) cost sharing ratio.

 

2.         City Council amend the 2014 Approved Capital Budget for Pan Am Games to add a new capital sub-project entitled BMX Track – [Concrete Reinforcement] with the total project cost of up to $4.41 million, funded by redirecting up to $0.450 million in unspent City debt funding from the Toronto Pan Am Sports Centre capital sub-project, in order to increase facility security, reduce liability risk and ensure long-term durability of the facility.

Background Information (Committee)

(June 17, 2014) Report from the Deputy City Manager, Cluster A on Pan/Parapan American Games Capital Projects Update
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70768.pdf

Communications (Committee)

(June 26, 2014) E-mail from Romana Marconi (EX.Supp.EX43.14.1)

Motions (City Council)

Motion to Adopt Item (Carried)

Vote (Adopt Item) Jul-10-2014 5:27 PM

Result: Carried Majority Required - EX43.14 - Adopt the item
Total members that voted Yes: 25 Members that voted Yes are Michelle Berardinetti, Shelley Carroll, Raymond Cho, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Mark Grimes, Norman Kelly, Mike Layton, Peter Leon, James Maloney, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Cesar Palacio, James Pasternak, Gord Perks, Ceta Ramkhalawansingh, Karen Stintz, Michael Thompson, Kristyn Wong-Tam
Total members that voted No: 4 Members that voted No are Rob Ford, Josh Matlow, Frances Nunziata (Chair), David Shiner
Total members that were Absent: 16 Members that were absent are Paul Ainslie, Maria Augimeri, Ana Bailão, Josh Colle, Gary Crawford, Vincent Crisanti, Doug Ford, Mary Fragedakis, Chin Lee, Gloria Lindsay Luby, Giorgio Mammoliti, Denzil Minnan-Wong, Ron Moeser, John Parker, Anthony Perruzza, Jaye Robinson

EX43.14 - Pan/Parapan American Games Capital Projects Update

Decision Type:
ACTION
Status:
Amended
Wards:
All

Committee Recommendations

The Executive Committee recommends that:

 

1.         City Council amend the 2014 Approved Capital Budget for Pan Am Games to increase the total project cost for the BMX Track capital sub-project by $2.413 million from $1.547 million to $3.96 million, funded by redirecting up to $1.054 million in City debt funding from the Toronto Pan Am Sports Centre capital sub-project, conditional on the remaining required share of up to $1.359 million being committed by the Government of Canada in order to maintain the 44 percent (City of Toronto) / 56 percent (Government of Canada) cost sharing ratio.

 

2.         City Council amend the 2014 Approved Capital Budget for Pan Am Games to add a new capital sub-project entitled BMX Track – [Concrete Reinforcement] with the total project cost of up to $4.41 million, funded by redirecting up to $0.450 million in unspent City debt funding from the Toronto Pan Am Sports Centre capital sub-project, in order to increase facility security, reduce liability risk and ensure long-term durability of the facility.

Origin

(June 17, 2014) Report from the Deputy City Manager, Cluster A

Summary

This report provides an update on the status of the City’s ten 2015 Pan/Parapan American Games (“2015 Games”) capital projects, and advises Council that there is a budget shortfall for the Pan Am Bicycle Motocross Track construction project at Centennial Park ("BMX Track Project").  Authority is sought to pay for the City’s 44 percent share of the shortfall by redirecting $1.260 million in City debt funding from Toronto Pan Am Sports Centre (“TPASC”) capital sub-project which is projected to be almost $10 million under budget.

 

The BMX Track Project was originally estimated by TO2015 at $1.547 million.  The City agreed to include the project in its 2015 Games capital projects, with the City contributing $0.678 million or 44 percent  of total project costs.   In May 2014, the Request for Proposals (RFP) process for this project closed and the preferred, low-cost, proponent was identified. Based on the preferred proponent’s submission, the total cost for the BMX Track Project cost is now anticipated to be $4.410 million.  Should this project proceed, the City's contribution would be $1.940 million or $1.262 million more than the City’s current budgeted contribution of $0.678 million. In addition, the Government of Canada's contribution would be required to increase from $0.866 million to $2.469 million.

 

In 2011, City Council approved a capital project called Pan Am Aquatic Centre/Canadian Sport Institute for Ontario now named the Toronto Pan Am Sports Centre (“TPASC”).  The approved TPASC project cost was $248.93 million, $54.765 million of which represented the City's contribution.  As a result of lower tenders, the guaranteed price of the Infrastructure Ontario (“IO”) managed TPASC contract is $205 million and the City’s contribution has been reduced to $45.10 million, resulting in budget savings of $9.67 million (the “TPASC Budget Savings”).  In July 2013, Council approved the reallocation of $2.42 million of the Toronto Pan Am Sports Centre Budget Savings to fund the West Channel, a new Pan Am Games project.  Council’s authority is now sought to redirect up to $1.262 million of the remaining TPASC Budget Savings to fund the additional BMX Track Project costs.

 

This matter is urgent in nature because, in order to complete the BMX Track venue in time for adequate testing prior to the 2015 Games, project construction must commence before the end of July 2014.

Background Information

(June 17, 2014) Report from the Deputy City Manager, Cluster A on Pan/Parapan American Games Capital Projects Update
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-70768.pdf

Communications

(June 26, 2014) E-mail from Romana Marconi (EX.Supp.EX43.14.1)

Speakers

Councillor Doug Ford

Motions

Motion to Amend Item moved by Councillor Peter Leon (Carried)

Delete recommendation 1 of the report and replace it with the following:

 

1.         City Council amend the 2014 Approved Capital Budget for Pan Am Games to increase the total project cost for the BMX Track capital sub-project by $2.413 million from $1.547 million to $3.96 million, funded by redirecting up to $1.054 million in City debt funding from the Toronto Pan Am Sports Centre capital sub-project, conditional on the remaining required share of up to $1.359 million being committed by the Government of Canada in order to maintain the 44% (City of Toronto) / 56% (Government of Canada) cost sharing ratio.

 

2.         City Council amend the 2014 Approved Capital Budget for Pan Am Games to add a new capital sub-project entitled BMX Track – [Concrete Reinforcement] with the total project cost of up to $4.41 million, funded by redirecting up to $0.450 million in unspent City debt funding from the Toronto Pan Am Sports Centre capital sub-project, in order to increase facility security, reduce liability risk and ensure long-term durability of the facility.

 

Vote (Amend Item) Jul-02-2014

Result: Carried Majority Required - Motion to Amend Item by Councillor Leon
Total members that voted Yes: 7 Members that voted Yes are Gary Crawford, Frank Di Giorgio, Norman Kelly (Chair), Peter Leon, Denzil Minnan-Wong, Cesar Palacio, Michael Thompson
Total members that voted No: 2 Members that voted No are Vincent Crisanti, Rob Ford
Total members that were Absent: 3 Members that were absent are Giorgio Mammoliti, Anthony Perruzza, David Shiner

Motion to Adopt Item as Amended moved by Deputy Mayor Norman Kelly (Carried)

Vote (Adopt Item as Amended) Jul-02-2014

Result: Carried Majority Required - Adopt Item as Amended
Total members that voted Yes: 7 Members that voted Yes are Gary Crawford, Frank Di Giorgio, Norman Kelly (Chair), Peter Leon, Denzil Minnan-Wong, Cesar Palacio, Michael Thompson
Total members that voted No: 2 Members that voted No are Vincent Crisanti, Rob Ford
Total members that were Absent: 3 Members that were absent are Giorgio Mammoliti, Anthony Perruzza, David Shiner
Source: Toronto City Clerk at www.toronto.ca/council