EX42.27 - Toronto Public Library - 2014 Capital Budget Adjustment for Maryvale Branch
- Decision Type:
- ACTION
- Status:
- Amended
- Wards:
- All
City Council Decision
City Council on June 10, 11, 12 and 13, 2014, adopted the following:
1. City Council approve a $60,000 gross, $0 net, increase to the 2014 project cost and cash flow for the Multi-Branch State of Good Repair project (CLB175), funded by a $20,000 landlord contribution and a $40,000 draw from the Library’s Development Charges Reserve Fund, for the renovation of an additional 577 square feet of space at the Maryvale Branch.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-69093.htm
(April 15, 2014) Report from the City Librarian on Toronto Public Library - 2014 Capital Budget Adjustment for Maryvale Branch
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-69119.pdf
(March 17, 2014) Attachment 1 - Communication from Councillor Michael Thompson to Michael Foderick, Chair, Toronto Public Library Board, dated March 17, 2014, regarding Maryvale Branch Lease - Amendment and Extension
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-69120.pdf
Motions (City Council)
Vote (Adopt Item) Jun-10-2014 11:32 AM
| Result: Carried | Majority Required - EX42.27 - Adopt the item |
|---|---|
| Total members that voted Yes: 36 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Michelle Berardinetti, Josh Colle, Gary Crawford, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Mary Fragedakis, Mark Grimes, Norman Kelly, Mike Layton, Chin Lee, Peter Leon, Gloria Lindsay Luby, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Peter Milczyn, Denzil Minnan-Wong, Ron Moeser, Frances Nunziata (Chair), Cesar Palacio, John Parker, Gord Perks, Anthony Perruzza, Jaye Robinson, David Shiner, Kristyn Wong-Tam |
| Total members that voted No: 1 | Members that voted No are Giorgio Mammoliti |
| Total members that were Absent: 7 | Members that were absent are Shelley Carroll, Raymond Cho, Doug Ford, Rob Ford, James Pasternak, Karen Stintz, Michael Thompson |
Declared Interests (City Council)
Councillor James Pasternak - as his spouse is an employee of the Toronto Public Library.
EX42.27 - Toronto Public Library - 2014 Capital Budget Adjustment for Maryvale Branch
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Executive Committee recommends that:
1. City Council approve a $60,000 gross, $0 net, increase to the 2014 project cost and cash flow for the Multi-Branch State of Good Repair project (CLB175), funded by a $20,000 landlord contribution and a $40,000 draw from the Library’s Development Charges Reserve Fund, for the renovation of an additional 577 square feet of space at the Maryvale Branch.
Origin
Summary
The purpose of this report is to seek approval for an in-year capital budget adjustment to increase the 2014 Multi-Branch State of Good Repair capital project by $60,000 gross, $0 net, for the renovation of an additional 577 square feet of space at the Maryvale Branch.
Background Information
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-69093.htm
(April 15, 2014) Report from the City Librarian on Toronto Public Library - 2014 Capital Budget Adjustment for Maryvale Branch
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-69119.pdf
(March 17, 2014) Attachment 1 - Communication from Councillor Michael Thompson to Michael Foderick, Chair, Toronto Public Library Board, dated March 17, 2014, regarding Maryvale Branch Lease - Amendment and Extension
https://www.toronto.ca/legdocs/mmis/2014/ex/bgrd/backgroundfile-69120.pdf