  • City Council adopted this item on December 16, 17 and 18, 2013 without amendments.
  • This item was considered by the Toronto and East York Community Council on November 19, 2013 and adopted without amendment. It will be considered by City Council on December 16, 17 and 18, 2013.

TE28.45 - Construction Staging Area Time Extension - No. 195 Davenport Road

Decision Type:
ACTION
Status:
Adopted
Ward:
27 - Toronto Centre-Rosedale

City Council Decision

City Council on December 16, 17 and 18, 2013, adopted the following:

 

1.         City Council approve the continuation of the closure of  the south curb lane, sidewalk and bicycle lane on Davenport Road, between Hazelton Avenue and a point 37 metres east, from December 16, 2013 to November 30, 2014.

Background Information (Community Council)

(October 24, 2013) Report from the Director, Transportation Services, Toronto and East York District - Construction Staging Area Time Extension - No. 195 Davenport Road
https://www.toronto.ca/legdocs/mmis/2013/te/bgrd/backgroundfile-63207.pdf
Drawing No. 421G-0826 - Construction Staging Area Time Extension - No. 195 Davenport Road
https://www.toronto.ca/legdocs/mmis/2013/te/bgrd/backgroundfile-63208.pdf

Motions (City Council)

Motion to Adopt Item (Carried)

Vote (Adopt Item) Dec-17-2013 2:23 PM

Result: Carried Majority Required - TE28.45 - Adopt the item
Total members that voted Yes: 34 Members that voted Yes are Paul Ainslie, Maria Augimeri, Michelle Berardinetti, Shelley Carroll, Gary Crawford, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, Sarah Doucette, John Filion, Doug Ford, Mary Fragedakis, Mark Grimes, Norman Kelly, Mike Layton, Chin Lee, Peter Leon, Gloria Lindsay Luby, Josh Matlow, Mary-Margaret McMahon, Joe Mihevc, Peter Milczyn, Denzil Minnan-Wong, Ron Moeser, Frances Nunziata (Chair), John Parker, James Pasternak, Gord Perks, Anthony Perruzza, Jaye Robinson, Michael Thompson, Adam Vaughan, Kristyn Wong-Tam
Total members that voted No: 1 Members that voted No are David Shiner
Total members that were Absent: 10 Members that were absent are Ana Bailão, Raymond Cho, Josh Colle, Vincent Crisanti, Paula Fletcher, Rob Ford, Giorgio Mammoliti, Pam McConnell, Cesar Palacio, Karen Stintz

TE28.45 - Construction Staging Area Time Extension - No. 195 Davenport Road

Decision Type:
ACTION
Status:
Adopted
Ward:
27 - Toronto Centre-Rosedale

Community Council Recommendations

The Toronto and East York Community Council recommends that:

 

1.         City Council approve the continuation of the closure of  the south curb lane, sidewalk and bicycle lane on Davenport Road, between Hazelton Avenue and a point 37 metres east, from December 16, 2013 to November 30, 2014.

Origin

(October 24, 2013) Report from the Director, Transportation Services, Toronto and East York District

Summary

Laughlin Solutions Incorporated is constructing a 9-storey condominium at No. 195 Davenport Road.  They need to continue to close the south curb lane, sidewalk and bicycle lane on Davenport Road in order to complete their work.

 

They also need to continue to close sections of the sidewalk on Hazelton Avenue.  This matter is dealt within a companion report entitled "Construction Staging Area Time Extension – Hazelton Avenue" requiring Toronto and East York Community Council approval.

Background Information

(October 24, 2013) Report from the Director, Transportation Services, Toronto and East York District - Construction Staging Area Time Extension - No. 195 Davenport Road
https://www.toronto.ca/legdocs/mmis/2013/te/bgrd/backgroundfile-63207.pdf
Drawing No. 421G-0826 - Construction Staging Area Time Extension - No. 195 Davenport Road
https://www.toronto.ca/legdocs/mmis/2013/te/bgrd/backgroundfile-63208.pdf

Motions

1 - Motion to Adopt Item moved by Councillor Kristyn Wong-Tam (Carried)