Item - 2013.TE24.46
Tracking Status
- City Council adopted this item on June 11, 12 and 13, 2013 without amendments.
- This item was considered by Toronto and East York Community Council on May 14, 2013 and was adopted with amendments. It will be considered by City Council on June 11, 12 and 13, 2013.
- See also By-laws 752-2013, 753-2013, 67-2019
TE24.46 - Construction Staging Areas - Harbour Street and York Street
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- 20 - Trinity-Spadina, 28 - Toronto Centre-Rosedale
City Council Decision
City Council on June 11, 12 and 13, 2013, adopted the following:
1. City Council approve the closure of the north sidewalk and part of the curb lane on Harbour Street, between York Street and a point 173 metres east, from June 12, 2013 to December 31, 2015.
2. City Council approve the closure of the east sidewalk and part of the curb lane on York Street, between Harbour Street and Lake Shore Boulevard West, from June 12, 2013 to December 31, 2015.
3. City Council rescind the existing "No Standing Anytime" regulation on the north side of Harbour Street, between a point 92 metres east of York Street and a point 18 metres further east.
4. City Council approve a "No Stopping Anytime" regulation on the north side of Harbour Street, between a point 92 metres east of York Street and a point 18 metres further east.
5. City Council authorize the General Manager, Transportation Services to request the alteration and/or removal of the proposed staging area if required to accommodate the Pan Am requirements during the months of July and August 2015.
6. City Council direct that Harbour Street and York Street be returned to their pre-construction traffic and parking regulations when the project is complete.
7. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
8. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
Background Information (Community Council)
https://www.toronto.ca/legdocs/mmis/2013/te/bgrd/backgroundfile-57763.pdf
Drawing No. 421G-1056 - Construction Staging Areas - Harbour Street and York Street
https://www.toronto.ca/legdocs/mmis/2013/te/bgrd/backgroundfile-57764.pdf
Motions (City Council)
Vote (Adopt Item) Jun-13-2013 9:48 AM
| Result: Carried | Majority Required - TE24.46 - Adopt the item |
|---|---|
| Total members that voted Yes: 28 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Michelle Berardinetti, Shelley Carroll, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Frank Di Giorgio, Sarah Doucette, Paula Fletcher, Doug Holyday, Mike Layton, Chin Lee, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Peter Milczyn, Denzil Minnan-Wong, Frances Nunziata (Chair), James Pasternak, Gord Perks, Jaye Robinson, David Shiner, Michael Thompson, Adam Vaughan, Kristyn Wong-Tam |
| Total members that voted No: 0 | Members that voted No are |
| Total members that were Absent: 17 | Members that were absent are Raymond Cho, Josh Colle, Gary Crawford, Mike Del Grande, John Filion, Doug Ford, Rob Ford, Mary Fragedakis, Mark Grimes, Norman Kelly, Gloria Lindsay Luby, Giorgio Mammoliti, Ron Moeser, Cesar Palacio, John Parker, Anthony Perruzza, Karen Stintz |
TE24.46 - Construction Staging Areas - Harbour Street and York Street
- Decision Type:
- ACTION
- Status:
- Amended
- Wards:
- 20 - Trinity-Spadina, 28 - Toronto Centre-Rosedale
Community Council Recommendations
The Toronto and East York Community Council recommends that:
1. City Council approve the closure of the north sidewalk and part of the curb lane on Harbour Street, between York Street and a point 173 metres east, from June 12, 2013 to December 31, 2015.
2. City Council approve the closure of the east sidewalk and part of the curb lane on York Street, between Harbour Street and Lake Shore Boulevard West, from June 12, 2013 to December 31, 2015.
3. City Council rescind the existing "No Standing Anytime" regulation on the north side of Harbour Street, between a point 92 metres east of York Street and a point 18 metres further east.
4. City Council approve a "No Stopping Anytime" regulation on the north side of Harbour Street, between a point 92 metres east of York Street and a point 18 metres further east.
5. City Council authorize the General Manager of Transportation Services to request the alteration and/or removal of the proposed staging area if required to accommodate the Pan Am requirements during the months of July and August 2015.
6. City Council direct that Harbour Street and York Street be returned to their pre-construction traffic and parking regulations when the project is complete.
7. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
8. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
Origin
Summary
Transportation Services is requesting authority to temporarily close the north sidewalk and part of the curb lane on Harbour Street, between York Street and a point 173 metres east. The existing three eastbound lanes would be maintained by narrowing all lanes to 3.3 metres. Pedestrians would be diverted one block north to Lake Shore Boulevard because there is no sidewalk on the south side of Harbour Street.
We are also requesting authority to temporarily close the east sidewalk and part of the curb lane on York Street, between Harbour Street and Lake Shore Boulevard West, and establish a temporary pedestrian walkway in the closed lane. The existing two northbound and two southbound lanes on York Street would be maintained by narrowing all lanes to 3.3 metres.
Menkes Developments Ltd. is constructing a 37-storey building and two 70-storey buildings at No. 90 Harbour Street and No. 1 York Street. This project requires the above closures for a period of 31 months to enable construction to proceed.
Background Information
https://www.toronto.ca/legdocs/mmis/2013/te/bgrd/backgroundfile-57763.pdf
Drawing No. 421G-1056 - Construction Staging Areas - Harbour Street and York Street
https://www.toronto.ca/legdocs/mmis/2013/te/bgrd/backgroundfile-57764.pdf
Motions
That the Toronto and East York Community Council recommend that City Council adopt the recommendations in the report (April 22, 2013) from the Acting Director, Transportation Services, Toronto and East York District, subject to adding the following new Recommendations 7 and 8:
7. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
8. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.