Item - 2012.TE19.33
Tracking Status
- City Council adopted this item on October 30, 31 and November 1, 2012 without amendments.
- This item was considered by Toronto and East York Community Council on October 10, 2012 and was adopted with amendments. It will be considered by City Council on October 30, 31 and November 1, 2012.
- See also By-laws 1422-2012, 1423-2012
TE19.33 - Construction Staging Area - No. 21 Avenue Road
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- 20 - Trinity-Spadina, 27 - Toronto Centre-Rosedale
City Council Decision
City Council on October 30, 31 and November 1, 2012, adopted the following:
1. City Council approve the closure of the sidewalk, curb lane and second lane on the east side of Avenue Road, between Cumberland Street and a point 68 metres north, from November 1, 2012 to December 31, 2014.
2. City Council approve the implementation of a "No Stopping Anytime" regulation on the east side of Avenue Road, between Cumberland Street and Yorkville Avenue, from November 1, 2012 to December 31, 2014.
3. City Council adjust the existing "No Parking Anytime" regulation on the east side of Avenue Road, from Bloor Street West to a point 293 metres north of Yorkville Avenue, to be in effect from Bloor Street West to Cumberland Street, and from Yorkville Avenue to a point 293 metres further north, from November 1, 2012 to December 31, 2014.
4. City Council adjust the existing "No Stopping, 7:30 a.m. to 9:30 a.m. and 3:30 p.m. to 6:30 p.m., Monday to Friday, except Public Holidays" regulation on the east side of Avenue Road, from Bloor Street West to a point 158 metres north of Yorkville Avenue, to be in effect from Bloor Street West to Cumberland Street, and from Yorkville Avenue to a point 158 metres further north, from November 1, 2012 to December 31, 2014.
5. City Council direct that Avenue Road be returned to its pre-construction traffic and parking regulations when the project is complete.
6. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
7. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
Background Information (Community Council)
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-50225.pdf
Drawing No. 421G-0830 - Construction Staging Area - No. 21 Avenue Road
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-50226.pdf
Motions (City Council)
Vote (Adopt Item) Oct-31-2012 1:48 PM
| Result: Carried | Majority Required - TE19.33 - Adopt the item |
|---|---|
| Total members that voted Yes: 35 | Members that voted Yes are Paul Ainslie, Ana Bailão, Shelley Carroll, Raymond Cho, Josh Colle, Gary Crawford, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Doug Ford, Rob Ford, Mary Fragedakis, Mark Grimes, Doug Holyday, Norman Kelly, Mike Layton, Chin Lee, Giorgio Mammoliti, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Frances Nunziata (Chair), Cesar Palacio, John Parker, Gord Perks, Anthony Perruzza, Karen Stintz, Michael Thompson, Adam Vaughan, Kristyn Wong-Tam |
| Total members that voted No: 1 | Members that voted No are David Shiner |
| Total members that were Absent: 9 | Members that were absent are Maria Augimeri, Michelle Berardinetti, Gloria Lindsay Luby, Josh Matlow, Peter Milczyn, Denzil Minnan-Wong, Ron Moeser, James Pasternak, Jaye Robinson |
TE19.33 - Construction Staging Area - No. 21 Avenue Road
- Decision Type:
- ACTION
- Status:
- Amended
- Wards:
- 20 - Trinity-Spadina, 27 - Toronto Centre-Rosedale
Community Council Recommendations
The Toronto and East York Community Council recommends that:
1. City Council approve the closure of the sidewalk, curb lane and second lane on the east side of Avenue Road, between Cumberland Street and a point 68 metres north, from November 1, 2012 to December 31, 2014.
2. City Council approve the implementation of a "No Stopping Anytime" regulation on the east side of Avenue Road, between Cumberland Street and Yorkville Avenue, from November 1, 2012 to December 31, 2014.
3. City Council adjust the existing "No Parking Anytime" regulation on the east side of Avenue Road, from Bloor Street West to a point 293 metres north of Yorkville Avenue, to be in effect from Bloor Street West to Cumberland Street, and from Yorkville Avenue to a point 293 metres further north, from November 1, 2012 to December 31, 2014.
4. City Council adjust the existing "No Stopping, 7:30 a.m. to 9:30 a.m. and 3:30 p.m. to 6:30 p.m., Monday to Friday, except Public Holidays" regulation on the east side of Avenue Road, from Bloor Street West to a point 158 metres north of Yorkville Avenue, to be in effect from Bloor Street West to Cumberland Street, and from Yorkville Avenue to a point 158 metres further north, from November 1, 2012 to December 31, 2014.
5. City Council direct that Avenue Road be returned to its pre-construction traffic and parking regulations when the project is complete.
6. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
7. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.
Origin
Summary
21 Avenue Building Group Inc. is converting a 31-storey hotel into a mixed use building at No. 21 Avenue Road. It is also constructing a 39-storey mixed use building on the northeast corner of Avenue Road and Cumberland Street and constructing a 10-storey mixed use building on the southeast corner of Avenue Road and Yorkville Avenue. Undertaking this work requires the closure of a section of the east sidewalk and northbound curb and second lane on Avenue Road. A pedestrian walkway will be built in the northbound curb lane.
This work also requires closing sections of the sidewalk and road on Cumberland Street and Yorkville Avenue. These matters are dealt with in a companion report "Construction Staging Area - Cumberland Street and Yorkville Avenue" requiring Toronto and East York Community Council approval.
Background Information
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-50225.pdf
Drawing No. 421G-0830 - Construction Staging Area - No. 21 Avenue Road
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-50226.pdf
Motions
That the Toronto and East York Community Council recommend that City Council adopt the recommendations in the report (September 14, 2012) from the Acting Director, Transportation Services, Toronto and East York District, subject to adding the following additional recommendations:
6. City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from 20 metres and on all elevations from the construction site.
7. City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spotlighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.