Skip to content

Tracking Status

TE18.62 - Construction Staging Area - Yonge Street

Decision Type:
ACTION
Status:
Adopted
Ward:
27 - Toronto Centre-Rosedale

City Council Decision

City Council on October 2, 3 and 4, 2012, adopted the following:

 

1.         City Council approve the closure of the sidewalk and the curb lane on the east side of Yonge Street, between Gould Street and a point 57.2 metres north of Gould Street, from September 24, 2012 to May 31, 2014.

 

2.         City Council approve the removal of the existing "No Parking Anytime" restriction on the east side of Yonge Street, between Gould Street and a point 62.2 metres north of Gould Street.

 

3.         City Council approve the removal of the existing "No Stopping, 3:30 p.m. to 6:30 p.m., except Saturdays, Sundays and Public Holidays" restriction on the east side of Yonge Street, between Gould Street and a point 62.2 metres north of Gould Street.

 

4.         City Council approve the implementation of a "No Stopping Anytime" restriction on the east side of Yonge Street, between Gould Street and a point 62.2 metres north of Gould Street.

 

5.         City Council direct that Yonge Street be returned to its pre-construction traffic and parking regulations when the project is complete.

 

6.         City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from the 20 metres and on all elevations from the construction site.

 

7.         City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spot lighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

Background Information (Community Council)

(August 21, 2012) Report from the Acting Director, Transportation Services, Toronto and East York District - Construction Staging Area - Yonge Street
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-49511.pdf
Drawing No. 421G-0816 - Construction Staging Area - Yonge Street
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-49512.pdf

Motions (City Council)

Motion to Adopt Item (Carried)

Vote (Adopt Item) Oct-03-2012 2:30 PM

Result: Carried Majority Required - TE18.62 - Adopt the item
Total members that voted Yes: 39 Members that voted Yes are Maria Augimeri, Ana Bailão, Michelle Berardinetti, Shelley Carroll, Raymond Cho, Josh Colle, Gary Crawford, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Rob Ford, Mary Fragedakis, Mark Grimes, Doug Holyday, Norman Kelly, Mike Layton, Chin Lee, Gloria Lindsay Luby, Giorgio Mammoliti, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Peter Milczyn, Frances Nunziata (Chair), Cesar Palacio, John Parker, James Pasternak, Gord Perks, Anthony Perruzza, Jaye Robinson, Karen Stintz, Adam Vaughan, Kristyn Wong-Tam
Total members that voted No: 4 Members that voted No are Denzil Minnan-Wong, Ron Moeser, David Shiner, Michael Thompson
Total members that were Absent: 2 Members that were absent are Paul Ainslie, Doug Ford

TE18.62 - Construction Staging Area - Yonge Street

Decision Type:
ACTION
Status:
Amended
Ward:
27 - Toronto Centre-Rosedale

Community Council Recommendations

The Toronto and East York Community Council recommends that:

 

1.         City Council approve the closure of the sidewalk and the curb lane on the east side of Yonge Street, between Gould Street and a point 57.2 metres north of Gould Street, from September 24, 2012 to May 31, 2014.

 

2.         City Council approve the removal of the existing "No Parking Anytime" restriction on the east side of Yonge Street, between Gould Street and a point 62.2 metres north of Gould Street.

 

3.         City Council approve the removal of the existing "No Stopping, 3:30 p.m. to 6:30 p.m., except Saturdays, Sundays and Public Holidays" restriction on the east side of Yonge Street, between Gould Street and a point 62.2 metres north of Gould Street.

 

4.         City Council approve the implementation of a "No Stopping Anytime" restriction on the east side of Yonge Street, between Gould Street and a point 62.2 metres north of Gould Street.

 

5.         City Council direct that Yonge Street be returned to its pre-construction traffic and parking regulations when the project is complete.

 

6.         City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from the 20 metres and on all elevations from the construction site.

 

7.         City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spot lighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.

Origin

(August 21, 2012) Report from the Acting Director, Transportation Services, Toronto and East York District

Summary

EllisDon Corporation is constructing a 9-storey building at No. 341 Yonge Street, on the northeast corner of Yonge Street and Gould Street.  They need to close the sidewalk and curb lane on the east side of Yonge Street in order to do their work.

 

EllisDon Corporation also needs to close the north sidewalk on Gould Street.  This matter is dealt with in a companion report "Construction Staging Area - Gould Street" requiring Toronto and East York Community Council approval.

Background Information

(August 21, 2012) Report from the Acting Director, Transportation Services, Toronto and East York District - Construction Staging Area - Yonge Street
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-49511.pdf
Drawing No. 421G-0816 - Construction Staging Area - Yonge Street
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-49512.pdf

Motions

1 - Motion to Amend Item (Additional) moved by Councillor Kristyn Wong-Tam (Carried)

That the report from the Acting Director, Transportation Services, Toronto and East York District, be amended by adding the following additional recommendations:

 

6.         City Council direct the applicant to post a 24-hour monitored construction hotline number on the hoarding board, which must be prominently placed and legible from the 20 metres and on all elevations from the construction site.

 

7.         City Council direct the applicant to provide and install public art, including mural artwork, onto every elevation of the hoarding board with adequate spot lighting for night-time illumination, at their sole cost, to the satisfaction of the Ward Councillor.