Skip to content

Tracking Status

  • City Council adopted this item on June 6, 7 and 8, 2012 with amendments.
  • This item was considered by Toronto and East York Community Council on May 15, 2012 and was adopted with amendments. It will be considered by City Council on June 6, 7 and 8, 2012.

TE16.4 - Final Report - 5 Eireann Quay - Site Plan Control Application

Decision Type:
ACTION
Status:
Amended
Ward:
20 - Trinity-Spadina

City Council Decision

City Council on June 6, 7 and 8, 2012, adopted the following:

 

1.         City Council replace Attachment 3: Proposed Short Stay Parking Protocol, attached to the report (May 9, 2012) from the Director, Community Planning, Toronto and East York District, with the Revised Short Stay Parking Protocol from the Toronto Port Authority dated May 11, 2012, and direct that Item A.8 in Attachment 2 to the report (May 9, 2012) from the Director, Community Planning, Toronto and East York District, be amended to refer to the Toronto Port Authority's Short Stay Parking Protocol dated May 11, 2012.

 

2.         City Council approve in principle the conditions set out in Attachment No. 2 to the report (May 9, 2012) from the Director, Community Planning, Toronto and East York District, as revised by Part 1 above, for the proposal for a temporary taxi management area, commercial parking and construction staging area for a pedestrian tunnel to the Billy Bishop Toronto City Airport on a portion of the lands at 5 Eireann Quay, with the following additional conditions as requirements of Site Plan Approval:

 

a.         That the Toronto Port Authority submit a letter to the City agreeing not to use or allow its contractors to use Eireann Quay for trucks to deliver pre-mixed concrete for the purposes of the construction of the pedestrian tunnel or any related works, until other practical measures can be presented to the Construction Liaison Committee which will minimize the use of Eireann Quay by all trucks.

 

b.         That the Toronto Port Authority be required to provide paid-duty officers on Eireann Quay for the first month after the taxi staging area becomes operational.

 

c.         That the Site Plan Approval terminates at the end of the lease of this property to the Toronto Port Authority, on June 30, 2015.

 

3.         City Council delegate back to the Acting Chief Planner or his designate the authority to issue final Site Plan Approval and that final Site Plan Approval not be issued until all the pre-approval conditions are satisfied.

 

4.         City Council:

 

a.         Receive for information the report (May 4, 2012) from the City Solicitor, headed "5 Eireann Quay - Environmental Approval Requirements for Concrete Batch Plant at Billy Bishop Airport", and the confidential information in Attachment 1 to this report.

 

b.         Direct that the confidential information in Attachment 1 to the report (May 4, 2012) from the City Solicitor not be made public.

 

5.         City Council:

 

a.         Receive the report (April 12, 2012) and confidential instructions to staff in Attachment 1 to the report from the City Solicitor, headed "5 Eireann Quay - Site Plan Control Application - Supplementary Report".

 

b.         Direct that the confidential information in Attachment 1 to the report (April 12, 2012) from the City Solicitor remain confidential.

 

6.         City Council receive the following reports for information:

 

a.         Report (May 7, 2012) from the Director and Deputy Chief Building Official, Toronto Building, Toronto and East York District, and Director, Community Planning, Toronto and East York District, headed "5 Eireann Quay - Information Report - Concrete Batching Plant."

 

b.         Report (March 9, 2012) from the Director, Community Planning, Toronto and East York District, headed "Final Report - 5 Eireann Quay - Site Plan Control Application."

 

c.         Report (March 29, 2012) from the Director, Community Planning, Toronto and East York District, headed "Supplementary Report - 5 Eireann Quay - Site Plan Control Application."

 

d.         Report (April 12, 2012) from the Treasurer, headed "5 Eireann Quay - Supplementary Report - Property Taxes and Payments in Lieu of Taxes."

 

Confidential Attachment 1 to the report (May 4, 2012) from the City Solicitor, remains confidential in its entirety in accordance with the provisions of the City of Toronto Act, 2006, as it contains advice or communications that are subject to solicitor-client privilege.

 

Confidential Attachment 1 to the report (April 12, 2012) from the City Solicitor, remains confidential in its entirety in accordance with the provisions of the City of Toronto Act, 2006, as it pertains to litigation or potential litigation and contains advice or communications that are subject to solicitor-client privilege.

Confidential Attachment - Litigation or potential litigation, including matters before administrative tribunals, affecting the municipality or local board; and the receiving of advice that is subject to solicitor-client privilege

Background Information (Community Council)

(May 9, 2012) Report from the Director, Community Planning, Toronto and East York District - 5 Eireann Quay - Site Plan Control Application - Final Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47164.pdf
(May 23, 2012) Report from the Director, Community Planning, Toronto and East York District - 5 Eireann Quay - Site Plan Control Application - Further Report - Notice of Pending Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-46846.pdf
(May 11, 2012) Revised Attachment 3 to Report (May 9, 2012) from the Director of Community Planning, Toronto and East York District - Letter from K.A. Lundy, Director, Infrastructure, Planning and Environment, Toronto Port Authority - 5 Eireann Quay, Community Access to the Short-Stay Parking Spaces (Attached to Motion from Councillor Adam Vaughan)
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47310.pdf

Communications (Community Council)

(March 19, 2012) E-mail from Hal Beck (TE.Supp.TE16.4.1)
(March 19, 2012) E-mail from Bob Rasmussen, Co-Chair, York Quay Neighbourhood Association (TE.Supp.TE16.4.2)
(March 20, 2012) E-mail from Shirley Bush (TE.Supp.TE16.4.3)
(April 8, 2012) E-mail from Stephanie Tjelios (TE.Supp.TE16.4.4)
(March 22, 2012) E-mail from Corrie Galloway and written by Joan Prowse, Bathurst Quay Neighbourhood Association (TE.Supp.TE16.4.5)
(April 16, 2012) E-mail from Joan Prowse, Arcadian Housing Co-op Representative, Bathurst Quay Neighbourhood Association (TE.Supp.TE16.4.6)
(April 16, 2012) E-mail from Beverly Dywan (TE.Supp.TE16.4.7)
(April 17, 2012) Submission from Gordon E. Petch, Counsel to the Toronto District School Board (TE.Supp.TE16.4.8)
(May 11, 2012) Letter from Gordon E. Petch, Municipal Law Chambers (TE.Supp.TE16.4.9)
(May 11, 2012) E-mail from Max Moore, Harbourfront Community Association (TE.Supp.TE16.4.10)
(May 14, 2012) Letter from Gordon E. Petch, Municipal Law Chambers, forwarding the Air Quality and Noise Report, completed by TEM on behalf of the Toronto District School Board (TE.Supp.TE16.4.11)
(May 14, 2012) E-mail from Charlotte Sam, Child Care Manager, Harbourfront Child Care Centre (TE.Supp.TE16.4.12)
(May 14, 2012) E-mail from Hal Beck (TE.Supp.TE16.4.13)
(May 15, 2012) Letter from Gordon E. Petch, Municipal Law Chambers (TE.Supp.TE16.4.14)

Motions (City Council)

1 - Motion to Amend Item moved by Councillor Adam Vaughan (Carried)

That City Council amend Toronto and East York Community Council Recommendation 2a by adding  words "to the City" after the word "letter" and the words "until other practical measures can be presented to the Construction Liaison Committee which will minimize the use of Eireann Quay by all trucks" after the word "works" so it now reads as follows:

 

a.         That the Toronto Port Authority submit a letter to the City agreeing not to use or allow its contractors to use Eireann Quay for trucks to deliver pre-mixed concrete for the purposes of the construction of the pedestrian tunnel or any related works, until other practical measures can be presented to the Construction Liaison Committee which will minimize the use of Eireann Quay by all trucks.

Vote (Amend Item) Jun-07-2012 6:03 PM

Result: Carried Majority Required - TE16.4 - Vaughan - motion 1
Total members that voted Yes: 32 Members that voted Yes are Paul Ainslie, Ana Bailão, Shelley Carroll, Raymond Cho, Josh Colle, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Doug Ford, Rob Ford, Mary Fragedakis, Doug Holyday, Norman Kelly, Mike Layton, Gloria Lindsay Luby, Giorgio Mammoliti, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Peter Milczyn, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, Gord Perks, Anthony Perruzza, Karen Stintz, Michael Thompson, Adam Vaughan
Total members that voted No: 0 Members that voted No are
Total members that were Absent: 13 Members that were absent are Maria Augimeri, Michelle Berardinetti, Gary Crawford, Mike Del Grande, Mark Grimes, Chin Lee, Josh Matlow, Ron Moeser, John Parker, James Pasternak, Jaye Robinson, David Shiner, Kristyn Wong-Tam

Motion to Adopt Item as Amended (Carried)

Vote (Adopt Item as Amended) Jun-07-2012 6:04 PM

Result: Carried Majority Required - TE16.4 - Adopt the item as amended
Total members that voted Yes: 32 Members that voted Yes are Paul Ainslie, Ana Bailão, Shelley Carroll, Raymond Cho, Josh Colle, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Frank Di Giorgio, Sarah Doucette, John Filion, Paula Fletcher, Doug Ford, Rob Ford, Mary Fragedakis, Doug Holyday, Norman Kelly, Mike Layton, Gloria Lindsay Luby, Giorgio Mammoliti, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Peter Milczyn, Denzil Minnan-Wong, Frances Nunziata (Chair), Cesar Palacio, Gord Perks, Anthony Perruzza, Karen Stintz, Michael Thompson, Adam Vaughan
Total members that voted No: 0 Members that voted No are
Total members that were Absent: 13 Members that were absent are Maria Augimeri, Michelle Berardinetti, Gary Crawford, Mike Del Grande, Mark Grimes, Chin Lee, Josh Matlow, Ron Moeser, John Parker, James Pasternak, Jaye Robinson, David Shiner, Kristyn Wong-Tam

4a - 5 Eireann Quay - Information Report - Concrete Batching Plant

Background Information (Community Council)
(May 1, 2012) Report from the Director and Deputy Chief Building Official, Toronto Building, Toronto and East York District and the Director, Community Planning, Toronto and East York District - 5 Eireann Quay - Information Report - Concrete Batching Plant
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-46928.pdf
(May 1, 2012) Report from the Director and Deputy Chief Building Official, Toronto Building, Toronto and East York District - 5 Eireann Quay - Site Plan Control Application - Further Report - Notice of Pending Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47159.pdf

4b - 5 Eireann Quay - Environmental Approval Requirements for Concrete Batch Plant at Billy Bishop Airport

Confidential Attachment - The receiving of advice that is subject to solicitor-client privilege
Background Information (Community Council)
(May 4, 2012) Report from the City Solicitor - 5 Eireann Quay - Environmental Approval Requirements for Concrete Batch Plant at Billy Bishop Airport
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47154.pdf
(May 1, 2012) Report from the City Solicitor - 5 Eireann Quay - Environmental Approval Requirements for Proposed Concrete Batch Plant - Notice of Pending Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-46873.pdf

4c - Final Report - 5 Eireann Quay - Site Plan Control Application

Background Information (Community Council)
(March 9, 2012) Report from the Director, Community Planning, Toronto and East York District - 5 Eireann Quay - Site Plan Control Application - Final Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47166.pdf

4d - Supplementary Report - 5 Eireann Quay - Site Plan Control Application

Background Information (Community Council)
(March 29, 2012) Report from the Director, Community Planning, Toronto and East York District - 5 Eireann Quay - Site Plan Control Application - Supplementary Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47167.pdf

4e - 5 Eireann Quay - Site Plan Control Application - Supplementary Report

Confidential Attachment - Litigation or potential litigation, including matters before administrative tribunals, affecting the municipality or local board; and the receiving of advice that is subject to solicitor-client privilege
Background Information (Community Council)
(April 12, 2012) Report from the City Solicitor - 5 Eireann Quay - Site Plan Control Application - Supplementary Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47165.pdf

4f - 5 Eireann Quay - Supplementary Report - Property Taxes and Payments in Lieu of Taxes

Background Information (Community Council)
(April 12, 2012) Report from the Treasurer - 5 Eireann Quay - Supplementary Report - Property Taxes and Payments in Lieu of Taxes
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47168.pdf

TE16.4 - Final Report - 5 Eireann Quay - Site Plan Control Application

Decision Type:
ACTION
Status:
Amended
Ward:
20 - Trinity-Spadina

Community Council Recommendations

The Toronto and East York Community Council recommends that:

 

1.         City Council replace Attachment 3: Proposed Short Stay Parking Protocol, attached to the report (May 9, 2012) from the Director, Community Planning, Toronto and East York District, with the Revised Short Stay Parking Protocol from the Toronto Port Authority dated May 11, 2012, and direct that Item A.8 in Attachment 2 to the report (May 9, 2012) from the Director, Community Planning, Toronto and East York District, be amended to refer to the Toronto Port Authority's Short Stay Parking Protocol dated May 11, 2012.

 

2.         City Council approve in principle the conditions set out in Attachment No. 2, to the report (May 9, 2012) from the Director, Community Planning, Toronto and East York District, as revised by Recommendation 1, for the proposal for a temporary taxi management area, commercial parking and construction staging area for a pedestrian tunnel to the Billy Bishop Toronto City Airport on a portion of the lands at 5 Eireann Quay, with the following additional conditions as requirements of Site Plan Approval:

 

a.         That the Toronto Port Authority submit a letter agreeing not to use or allow its contractors to use Eireann Quay for trucks to deliver pre-mixed concrete for the purposes of the construction of the pedestrian tunnel or any related works.

 

b.         That the Toronto Port Authority be required to provide paid-duty officers on Eireann Quay for the first month after the taxi staging area becomes operational.

 

c.         That the Site Plan Approval terminates at the end of the lease of this property to the Toronto Port Authority, on June 30, 2015.

 

3.         City Council delegate back to the Chief Planner or his designate the authority to issue final Site Plan Approval and that final Site Plan Approval not be issued until all the pre-approval conditions are satisfied.

 

4.         City Council:

 

a.         Receive for information the report (May 4, 2012) from the City Solicitor, headed "5 Eireann Quay - Environmental Approval Requirements for Concrete Batch Plant at Billy Bishop Airport", and the confidential information in Attachment 1 to this report.

 

b.         Authorize that the confidential information in Attachment 1 to the report (May 4, 2012) from the City Solicitor not be made public.

 

5.         City Council:

 

a.         Receive the report (April 12, 2012) and confidential instructions to staff in Attachment 1 to the report from the City Solicitor, headed "5 Eireann Quay - Site Plan Control Application - Supplementary Report".

 

b.         Authorize that the confidential information in Attachment 1 to the report (April 12, 2012) from the City Solicitor remain confidential.

 

6.         City Council receive the following reports for information:

 

a.         Report (May 7, 2012) from the Director and Deputy Chief Building Official, Toronto Building, Toronto and East York District, and Director, Community Planning, Toronto and East York District, headed "5 Eireann Quay - Information Report - Concrete Batching Plant."

 

b.         Report (March 9, 2012) from the Director, Community Planning, Toronto and East York District, headed "Final Report - 5 Eireann Quay - Site Plan Control Application."

 

c.         Report (March 29, 2012) from the Director, Community Planning, Toronto and East York District, headed "Supplementary Report - 5 Eireann Quay - Site Plan Control Application."

 

d.         Report (April 12, 2012) from the Treasurer, headed "5 Eireann Quay - Supplementary Report - Property Taxes and Payments in Lieu of Taxes."

Origin

(May 9, 2012) Report from the Director, Community Planning, Toronto and East York District

Summary

At its meeting on April 17, 2012, Toronto and East York Community Council (TEYCC) deferred consideration of Item TE15.6 Final Report - 5 Eireann Quay - Site Plan Control Application from the Director, Community Planning (dated March 22, 2012).  TEYCC requested a further report from the Acting Chief Planner for the May 15, 2012 TEYCC meeting.  The decision document can be accessed at this link: http://app.toronto.ca/tmmis/viewAgendaItemHistory.do?item=2012.TE15.6

 

This report reviews and recommends approval in principle of the Site Plan Control application.

Background Information

(May 9, 2012) Report from the Director, Community Planning, Toronto and East York District - 5 Eireann Quay - Site Plan Control Application - Final Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47164.pdf
(May 23, 2012) Report from the Director, Community Planning, Toronto and East York District - 5 Eireann Quay - Site Plan Control Application - Further Report - Notice of Pending Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-46846.pdf
(May 11, 2012) Revised Attachment 3 to Report (May 9, 2012) from the Director of Community Planning, Toronto and East York District - Letter from K.A. Lundy, Director, Infrastructure, Planning and Environment, Toronto Port Authority - 5 Eireann Quay, Community Access to the Short-Stay Parking Spaces (Attached to Motion from Councillor Adam Vaughan)
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47310.pdf

Communications

(March 19, 2012) E-mail from Hal Beck (TE.Supp.TE16.4.1)
(March 19, 2012) E-mail from Bob Rasmussen, Co-Chair, York Quay Neighbourhood Association (TE.Supp.TE16.4.2)
(March 20, 2012) E-mail from Shirley Bush (TE.Supp.TE16.4.3)
(April 8, 2012) E-mail from Stephanie Tjelios (TE.Supp.TE16.4.4)
(March 22, 2012) E-mail from Corrie Galloway and written by Joan Prowse, Bathurst Quay Neighbourhood Association (TE.Supp.TE16.4.5)
(April 16, 2012) E-mail from Joan Prowse, Arcadian Housing Co-op Representative, Bathurst Quay Neighbourhood Association (TE.Supp.TE16.4.6)
(April 16, 2012) E-mail from Beverly Dywan (TE.Supp.TE16.4.7)
(April 17, 2012) Submission from Gordon E. Petch, Counsel to the Toronto District School Board (TE.Supp.TE16.4.8)
(May 11, 2012) Letter from Gordon E. Petch, Municipal Law Chambers (TE.Supp.TE16.4.9)
(May 11, 2012) E-mail from Max Moore, Harbourfront Community Association (TE.Supp.TE16.4.10)
(May 14, 2012) Letter from Gordon E. Petch, Municipal Law Chambers, forwarding the Air Quality and Noise Report, completed by TEM on behalf of the Toronto District School Board (TE.Supp.TE16.4.11)
(May 14, 2012) E-mail from Charlotte Sam, Child Care Manager, Harbourfront Child Care Centre (TE.Supp.TE16.4.12)
(May 14, 2012) E-mail from Hal Beck (TE.Supp.TE16.4.13)
(May 15, 2012) Letter from Gordon E. Petch, Municipal Law Chambers (TE.Supp.TE16.4.14)

Speakers

Gordon E. Petch, Municipal Law Chambers
Mario Silva, Land Use Planning Officer, Toronto District School Board
Barry Lipton

Motions

1 - Motion to Amend Item moved by Councillor Adam Vaughan (Carried)

That:

  

1.         City Council approve in principle the conditions set out in Attachment No. 2, to the report (May 9, 2012) from the Director, Community Planning, Toronto and East York District, as revised by Recommendation 1, for the proposal for a temporary taxi management area, commercial parking and construction staging area for a pedestrian tunnel to the Billy Bishop Toronto City Airport on a portion of the lands at 5 Eireann Quay, with the following additional conditions as requirements of Site Plan Approval:

 

a.         That the Toronto Port Authority submit a letter agreeing not to use or allow its contractors to use Eireann Quay for trucks to deliver pre-mixed concrete for the purposes of the construction of the pedestrian tunnel or any related works.

 

b.         That the Toronto Port Authority be required to provide paid-duty officers on Eireann Quay for the first month after the taxi staging area becomes operational.

 

c.         That the Site Plan Approval terminates at the end of the lease of this property to the Toronto Port Authority, on June 30, 2015.

 

2.         City Council replace Attachment 3: Proposed Short Stay Parking Protocol, attached to the report (May 9, 2012) from the Director, Community Planning, Toronto and East York District, with the Revised Short Stay Parking Protocol from the Toronto Port Authority dated May 11, 2012, and direct that Item A.8 in Attachment 2 to the report (May 9, 2012) from the Director, Community Planning, Toronto and East York District, be amended to refer to the Toronto Port Authority's Short Stay Parking Protocol dated May 11, 2012.


2 - Motion to Amend Item (Additional) moved by Councillor Gord Perks (Carried)

That the item be amended by adding the following additional recommendations:

 

4.         City Council:

 

a.         Receive for information the report (May 4, 2012) from the City Solicitor, headed "5 Eireann Quay – Environmental Approval Requirements for Concrete Batch Plant at Billy Bishop Airport", and the confidential information in Attachment 1 to this report.

 

b.         Authorize that the confidential information in Attachment 1 to the report (May 4, 2012) from the City Solicitor not be made public.

 

5.         City Council:

 

a.         Receive the report (April 12, 2012) and confidential instructions to staff in Attachment 1 to the report from the City Solicitor, headed "5 Eireann Quay – Site Plan Control Application - Supplementary Report".

 

b.         Authorize that the confidential information in Attachment 1 to the report (April 12, 2012) from the City Solicitor remain confidential.

 

6.         City Council receive the following reports for information:

 

a.         Report (May 7, 2012) from the Director and Deputy Chief Building Official, Toronto Building, Toronto and East York District, and Director, Community Planning, Toronto and East York District, headed "5 Eireann Quay - Information Report - Concrete Batching Plant."

 

b.         Report (March 9, 2012) from the Director, Community Planning, Toronto and East York District, headed "Final Report - 5 Eireann Quay - Site Plan Control Application."

 

c.         Report (March 29, 2012) from the Director, Community Planning, Toronto and East York District, headed "Supplementary Report - 5 Eireann Quay - Site Plan Control Application."

 

d.         Report (April 12, 2012) from the Treasurer, headed "5 Eireann Quay – Supplementary Report – Property Taxes and Payments in Lieu of Taxes."


3 - Motion to Adopt Item as Amended moved by Councillor Adam Vaughan (Carried)

4a - 5 Eireann Quay - Information Report - Concrete Batching Plant

Origin
(May 7, 2012) Report from the Director and Deputy Chief Building Official, Toronto Building, Toronto and East York District and Director, Community Planning, Toronto and East York District
Summary

At its meeting on April 17, 2012, Toronto and East York Community Council (TEYCC) requested the Director of Toronto Building and Deputy Chief Building Official, in consultation with the Director, Community Planning, Toronto and East York District, to submit a report to the May 15, 2012 TEYCC meeting on whether a batching plant complies with the existing zoning on the site. The purpose of this report is to provide information related this request.

 

Based on the information provided by the applicant on the proposed temporary mobile concrete batching facility and an analysis of the existing zoning on the site, it is staff’s opinion that the proposal complies with current zoning permissions.

Background Information
(May 1, 2012) Report from the Director and Deputy Chief Building Official, Toronto Building, Toronto and East York District and the Director, Community Planning, Toronto and East York District - 5 Eireann Quay - Information Report - Concrete Batching Plant
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-46928.pdf
(May 1, 2012) Report from the Director and Deputy Chief Building Official, Toronto Building, Toronto and East York District - 5 Eireann Quay - Site Plan Control Application - Further Report - Notice of Pending Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47159.pdf

4b - 5 Eireann Quay - Environmental Approval Requirements for Concrete Batch Plant at Billy Bishop Airport

Confidential Attachment - The receiving of advice that is subject to solicitor-client privilege
Origin
(May 4, 2012) Report from the City Solicitor
Summary

This report outlines environmental approvals for the concrete batch plant proposed in the Toronto Port Authority's draft Construction Management Plan for the Billy Bishop Airport tunnel project.

Background Information
(May 4, 2012) Report from the City Solicitor - 5 Eireann Quay - Environmental Approval Requirements for Concrete Batch Plant at Billy Bishop Airport
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47154.pdf
(May 1, 2012) Report from the City Solicitor - 5 Eireann Quay - Environmental Approval Requirements for Proposed Concrete Batch Plant - Notice of Pending Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-46873.pdf

4c - Final Report - 5 Eireann Quay - Site Plan Control Application

Origin
(March 9, 2012) Report from the Director, Community Planning, Toronto and East York District
Summary

This application proposes a temporary taxi management area, commercial parking lot and construction staging area for a pedestrian tunnel to the Billy Bishop Toronto City Airport at 5 Eireann Quay.  The proposed commercial parking lot consists of 18 short stay parking spaces and 26 long stay spaces.  The City has agreed to lease portions of the property to the applicant for its use during construction of the pedestrian tunnel.  The Toronto Port Authority (TPA) is the applicant for the Site Plan Control application, while the tenant of the leased lands will be 2315155 ONTARIO INC., a subsidiary corporation of the TPA. 

 

The proposed uses are permitted by the Zoning By-law and contemplated by the City's Official Plan.  Through the Site Plan Control process, City staff have worked with the applicant and their consultants to identify and address issues raised.

 

This report reviews and recommends approval, in principle, of the Site Plan Control application for the leased portions of the City-owned property. 

Background Information
(March 9, 2012) Report from the Director, Community Planning, Toronto and East York District - 5 Eireann Quay - Site Plan Control Application - Final Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47166.pdf

4d - Supplementary Report - 5 Eireann Quay - Site Plan Control Application

Origin
(March 29, 2012) Report from the Director, Community Planning, Toronto and East York District
Summary

At its meeting on March 20, 2012, Toronto and East York Community Council (TEYCC) deferred consideration of the Final Report - 5 Eireann Quay - Site Plan Control Application from the Director, Community Planning (dated March 9, 2012 - Item TE14.1).  TEYCC requested a report from the Chief Planner and Executive Director, City Planning Division, which imposes additional conditions on the Site Plan Approval application.  This report responds to the request.

 

The application proposes a temporary taxi management area, commercial parking lot and construction staging area for a pedestrian tunnel to the Billy Bishop Toronto City Centre Airport on a portion of 5 Eireann Quay.

Background Information
(March 29, 2012) Report from the Director, Community Planning, Toronto and East York District - 5 Eireann Quay - Site Plan Control Application - Supplementary Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47167.pdf

4e - 5 Eireann Quay - Site Plan Control Application - Supplementary Report

Confidential Attachment - Litigation or potential litigation, including matters before administrative tribunals, affecting the municipality or local board; and the receiving of advice that is subject to solicitor-client privilege
Origin
(April 12, 2012) Report from the City Solicitor
Summary

This report provides additional information and legal advice regarding the Site Plan Control Application and the requests arising from the March 20, 2012 Toronto and East York Community Council (TEYCC) meeting.

Background Information
(April 12, 2012) Report from the City Solicitor - 5 Eireann Quay - Site Plan Control Application - Supplementary Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47165.pdf

4f - 5 Eireann Quay - Supplementary Report - Property Taxes and Payments in Lieu of Taxes

Origin
(April 12, 2012) Report from the Treasurer
Summary

This report provides information on the amount of any outstanding property taxes or payments in lieu of taxes owed by the Toronto Port Authority with respect to 5 Eireann Quay.

Background Information
(April 12, 2012) Report from the Treasurer - 5 Eireann Quay - Supplementary Report - Property Taxes and Payments in Lieu of Taxes
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-47168.pdf