- This item was considered by Toronto and East York Community Council on April 17, 2012. The Toronto and East York Community Council postponed consideration of this item. Consult the text of the decision for further information on the deferral.
TE15.6 - Final Report - 5 Eireann Quay - Site Plan Control Application
- Decision Type:
- ACTION
- Status:
- Deferred
- Ward:
- 20 - Trinity-Spadina
Community Council Decision
The Toronto and East York Community Council:
1. Deferred consideration of Item TE15.6 until such time as:
a. The Construction Management Plan for any works is approved to the satisfaction of the Acting General Manager, Transportation Services and the Ward Councillor, and including the requirement that:
i. the applicant consult with the Facilities Department of the Toronto District School Board; and
ii. the applicant submit details of the plans for community access to the short-stay parking spaces.
b. The applicant submits a revised Landscape Plan detailing plantings at the north end of the site to act as a buffer to the schools, daycare and community centre to the north, to the satisfaction of Urban Forestry and the Ward Councillor.
c. The applicant submits revised plans that will retain Trees Nos. 29, 30, 31, 32 and 33, to the satisfaction of the Supervisor, Tree Protection and Plan Review, Manager, Technical Services and Director, Community Planning, Toronto and East York District.
2. Requested the Supervisor, Tree Protection and Plan Review to revise the Tree Removal Permit for 5 Eireann Quay to reflect any revisions made to the plans by the Applicant.
3. Requested the City Solicitor, in consultation with appropriate staff, to report to the May 15, 2012 meeting of the Toronto and East York Community Council on the environmental approval requirements for the concrete batch plant proposed in the draft Construction Management Plan.
4. Requested the Director of Toronto Building and Deputy Chief Building Official, in consultation with the Director, Community Planning, Toronto and East York District, to submit a report to the Toronto and East York Community Council on May 15, 2012 on whether the batching plant complies with the existing zoning on the site.
5. Requested the Acting Chief Planner and Executive Director, City Planning Division to report to the May 15, 2012 meeting of Toronto and East York Community Council on revisions to the plans and conditions.
Origin
Summary
This application proposes a temporary taxi management area, commercial parking lot and construction staging area for a pedestrian tunnel to the Billy Bishop Toronto City Airport at 5 Eireann Quay. The proposed commercial parking lot consists of 18 short stay parking spaces and 26 long stay spaces. The City has agreed to lease portions of the property to the applicant for its use during construction of the pedestrian tunnel. The Toronto Port Authority (TPA) is the applicant for the Site Plan Control application, while the tenant of the leased lands will be 2315155 ONTARIO INC., a subsidiary corporation of the TPA.
The proposed uses are permitted by the Zoning By-law and contemplated by the City's Official Plan. Through the Site Plan Control process, City staff have worked with the applicant and their consultants to identify and address issues raised.
This report reviews and recommends approval, in principle, of the Site Plan Control application for the leased portions of the City-owned property.
Background Information
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-46257.pdf
Communications
(March 19, 2012) E-mail from Bob Rasmussen, Co-Chair, York Quay Neighbourhood Association (TE.Main.TE15.6.2)
(March 20, 2012) E-mail from Shirley Bush (TE.Main.TE15.6.3)
(April 8, 2012) E-mail from Stephanie Tjelios (TE.Supp.TE15.6.4)
(March 22, 2012) E-mail from Corrie Galloway and written by Joan Prowse, Bathurst Quay Neighbourhood Association (TE.Supp.TE15.6.5)
(April 16, 2012) E-mail from Joan Prowse, Arcadian Housing Co-op Representative, Bathurst Quay Neighbourhood Association (TE.Supp.TE15.6.6)
(April 16, 2012) E-mail from Beverly Dywan (TE.Supp.TE15.6.7)
(April 17, 2012) Submission from Gord Petch, Toronto District School Board (TE.Supp.TE15.6.8)
Speakers
Geoffrey Wilson, President and Chief Executive Officer, Toronto Port Authority
Gord Petch, Solicitor, Municipal Law Chambers, on behalf of Toronto District School Board
Mario Silva, Planning Officer, Toronto District School Board
Max Moore, Harbourfront Community Association
Kathryn Exner
Brenda Roman
Motions
That the Toronto and East York Community Council recess its public session at 2:10 p.m. to meet in closed session in accordance with the City of Toronto Act, to consider Item TE15.6b - Report from the City Solicitor on 5 Eireann Quay - Site Plan Control Application - Supplementary Report, in that the matter pertains to litigation or potential litigation, including matters before administrative tribunals, affecting the municipality or local board; and the receiving of advice that is subject to solicitor-client privilege.
That the Toronto and East York Community Council:
1. Defer consideration of Item TE15.6 until such time as:
a. The Construction Management Plan for any works is approved to the satisfaction of the Acting General Manager, Transportation Services and the Ward Councillor, and including the requirement that:
i. the applicant consult with the Facilities Department of the Toronto District School Board; and
ii. the applicant submit details of the plans for community access to the short-stay parking spaces.
b. The applicant submits a revised Landscape Plan detailing plantings at the north end of the site to act as a buffer to the schools, daycare and community centre to the north, to the satisfaction of Urban Forestry and the Ward Councillor.
c. The applicant submits revised plans that will retain Trees Nos. 29, 30, 31, 32 and 33, to the satisfaction of the Supervisor, Tree Protection and Plan Review, Manager, Technical Services and Director, Community Planning, Toronto and East York District.
That the Toronto and East York Community Council request the:
1. Supervisor, Tree Protection and Plan Review to revise the Tree Removal Permit for 5 Eireann Quay to reflect any revisions made to the plans by the Applicant.
2. City Solicitor, in consultation with appropriate staff, to report to the May 15, 2012 meeting of the Toronto and East York Community Council on the environmental approval requirements for the concrete batch plant proposed in the draft Construction Management Plan.
3. Director of Toronto Building and Deputy Chief Building Official, in consultation with the Director, Community Planning, Toronto and East York District, to submit a report to the Toronto and East York Community Council on May 15, 2012 on whether the batching plant complies with the existing zoning on the site.
4. Acting Chief Planner and Executive Director, City Planning Division to report to the May 15, 2012 meeting of Toronto and East York Community Council on revisions to the plans and conditions.
Vote (Adopt Item as Amended) Apr-17-2012
| Result: Carried | Majority Required |
|---|---|
| Total members that voted Yes: 11 | Members that voted Yes are Janet Davis, Paula Fletcher, Mary Fragedakis, Mike Layton, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Gord Perks (Chair), Adam Vaughan, Kristyn Wong-Tam |
| Total members that voted No: 0 | Members that voted No are |
| Total members that were Absent: 1 | Members that were absent are Ana Bailão |
6a - Supplementary Report - 5 Eireann Quay - Site Plan Control Application
Origin
Summary
At its meeting on March 20, 2012, Toronto and East York Community Council (TEYCC) deferred consideration of the Final Report - 5 Eireann Quay - Site Plan Control Application from the Director, Community Planning (dated March 9, 2012 - Item TE14.1). TEYCC requested a report from the Chief Planner and Executive Director, City Planning Division, which imposes additional conditions on the Site Plan Approval application. This report responds to the request.
The application proposes a temporary taxi management area, commercial parking lot and construction staging area for a pedestrian tunnel to the Billy Bishop Toronto City Centre Airport on a portion of 5 Eireann Quay.
Background Information
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-46274.pdf
6b - 5 Eireann Quay - Site Plan Control Application - Supplementary Report
Confidential Attachment - Litigation or potential litigation, including matters before administrative tribunals, affecting the municipality or local board; and the receiving of advice that is subject to solicitor-client privilege
Origin
Summary
This report provides additional information and legal advice regarding the Site Plan Control Application and the requests arising from the March 20, 2012 Toronto and East York Community Council (TEYCC) meeting.
Background Information
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-46446.pdf
6c - 5 Eireann Quay - Supplementary Report - Property Taxes and Payments in Lieu of Taxes
Origin
Summary
This report provides information on the amount of any outstanding property taxes or payments in lieu of taxes owed by the Toronto Port Authority with respect to 5 Eireann Quay.
Background Information
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-46440.pdf