  • This item was considered by Toronto and East York Community Council on March 20, 2012. The Toronto and East York Community Council postponed consideration of this item. Consult the text of the decision for further information on the deferral.

TE14.1 - Final Report - 5 Eireann Quay - Site Plan Control Application

Decision Type:
ACTION
Status:
Deferred
Ward:
20 - Trinity-Spadina

Community Council Decision

The Toronto and East York Community Council

 

1.         Deferred consideration of the report (March 9, 2012) from the Director, Community Planning, Toronto and East York District, respecting the Final Report - 5 Eireann Quay - Site Plan Control Application, until such time as:

 

a.         The Chief Planner and Executive Director, City Planning Division reports back with conditions imposing the following:

 

i.          That the applicant submit a Construction Management Plan for any works in the area by the applicant, to the satisfaction of the General Manager, Transportation Services and the Ward Councillor.

 

ii.         That the applicant ensure members of the neighbouring community will have access to the short stay parking spaces.

 

iii.        That the applicant be required to plant trees at the north end of the site to act as a buffer to the schools, daycare and community centre to the north, to the satisfaction of Urban Forestry and the Ward Councillor.

 

b.         Speed bumps are installed on Eireann Quay, as per Toronto and East York Community Council approval on August 17, 2010.

 

2.         Requested the Executive Director of Municipal Licensing and Standards and the City Solicitor to undertake an investigation and ensure that the terms of the lease with the Toronto Port Authority are enforced.

 

3.         Requested the Deputy City Manager and Chief Financial Officer to submit an information report to the Toronto and East York Community Council on any outstanding taxes and/or payments in lieu of taxes owed by the Toronto Port Authority and proposed terms of payment with respect to 5 Eireann Quay, such report to be submitted at the time the Chief Planner and Executive Director, City Planning Division, reports back on the conditions requested in Recommendation 1a. with respect to the Final Report - 5 Eireann Quay - Site Plan Control Application.

Decision Advice and Other Information

The Toronto and East York Community Council considered this item together with Item TE14.31 - Parking Amendment - Eireann Quay.

Origin

(March 9, 2012) Report from the Director, Community Planning, Toronto and East York District

Summary

This application proposes a temporary taxi management area, commercial parking lot and construction staging area for a pedestrian tunnel to the Billy Bishop Toronto City Airport at 5 Eireann Quay.  The proposed commercial parking lot consists of 18 short stay parking spaces and 26 long stay spaces.  The City has agreed to lease portions of the property to the applicant for its use during construction of the pedestrian tunnel.  The Toronto Port Authority (TPA) is the applicant for the Site Plan Control application, while the tenant of the leased lands will be 2315155 ONTARIO INC., a subsidiary corporation of the TPA. 

 

The proposed uses are permitted by the Zoning By-law and contemplated by the City's Official Plan.  Through the Site Plan Control process, City staff have worked with the applicant and their consultants to identify and address issues raised.

 

This report reviews and recommends approval, in principle, of the Site Plan Control application for the leased portions of the City-owned property. 

Background Information

(March 9, 2012) Report from the Director, Community Planning, Toronto and East York District - 5 Eireann Quay - Site Plan Control Application - Final Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-45409.pdf
Report from the Director, Community Planning, Toronto and East York District - Final Report - 5 Eireann Quay - Site Plan Control Application - Notice of Pending Report
https://www.toronto.ca/legdocs/mmis/2012/te/bgrd/backgroundfile-45912.pdf

Communications

(March 19, 2012) E-mail from Hal Beck (TE.Supp.TE14.1.1)
(March 19, 2012) E-mail from Bob Rasmussen, Co-Chair, York Quay Neighbourhood Association (TE.Supp.TE14.1.2)
(March 20, 2012) E-mail from Shirley Bush (TE.Supp.TE14.1.3)

Speakers

Brian Iler, Chair, CommunityAIR
Gene Cabral, Airport Director, Billy Bishop Toronto City Airport
Bill Freeman, Community AIR
Kathryn Exner
Corrie Galloway
Max Moore, Harbourfront Community Association
Brenda Roman
Ulla Colgrass, York Quay Neighbourhood Association
Laura Cooper

Motions

1 - Motion to Defer Item moved by Councillor Adam Vaughan (Carried)

That the Toronto and East York Community Council defer consideration of the report (March 9, 2012) from the Director, Community Planning, Toronto and East York District, respecting the Final Report - 5 Eireann Quay - Site Plan Control Application, until such time as:

 

a.         The Chief Planner and Executive Director, City Planning Division reports back with conditions imposing the following:

 

i.          That the applicant submit a Construction Management Plan for any works in the area by the applicant, to the satisfaction of the General Manager, Transportation Services and the Ward Councillor.

 

ii.         That the applicant ensure members of the neighbouring community will have access to the short stay parking spaces.

 

iii.        That the applicant be required to plant trees at the north end of the site to act as a buffer to the schools, daycare and community centre to the north, to the satisfaction of Urban Forestry and the Ward Councillor.

 

b.         Speed bumps are installed on Eireann Quay, as per Toronto and East York Community Council approval on August 17, 2010.


2 - Motion to Amend Item (Additional) moved by Councillor Adam Vaughan (Carried)

That the Executive Director of Municipal Licensing and Standards and the City Solicitor be requested to undertake an investigation and ensure that the terms of the lease with the Toronto Port Authority are enforced.


3 - Motion to Amend Item (Additional) moved by Councillor Paula Fletcher (Carried)

That the Deputy City Manager and Chief Financial Officer be requested to submit an information report to the Toronto and East York Community Council on any outstanding taxes and/or payments in lieu of taxes owed by the Toronto Port Authority and proposed terms of payment with respect to 5 Eireann Quay, such report to be submitted at the time the Chief Planner and Executive Director, City Planning Division, reports back on the conditions requested in Recommendation 1a. with respect to the Final Report - 5 Eireann Quay - Site Plan Control Application.


4 - Motion to Adopt Item as Amended moved by Councillor Gord Perks (Carried)

Vote (Adopt Item as Amended) Mar-20-2012

Result: Carried Majority Required
Total members that voted Yes: 10 Members that voted Yes are Janet Davis, Paula Fletcher, Mary Fragedakis, Mike Layton, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Gord Perks (Chair), Adam Vaughan, Kristyn Wong-Tam
Total members that voted No: 0 Members that voted No are
Total members that were Absent: 2 Members that were absent are Ana Bailão, Josh Matlow