EX20.6 - Capital Variance Report for the Year Ended December 31, 2011
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
City Council Decision
City Council on June 6, 7 and 8, 2012, adopted the following:
1. City Council approve additional carry forward funding of $19.893 million for unspent 2011 capital and carry forward funding of $0.285 million for unspent 2010 and prior year capital projects as detailed in Appendix 2 to the report (April 27, 2012) from the Deputy City Manager and Chief Financial Officer, in order to continue work on capital projects, and that the 2012 Approved Capital Budget be adjusted accordingly with no incremental impact on debt.
2. City Council approve in-year budget adjustment of $1.556 million for Toronto Public Library to advance third party donations raised by the Toronto Library Foundation for the Toronto Reference Library capital project to 2011 from 2012 due to the acceleration of Phase II renovations in 2011 as detailed in Appendix 3 to the report (April 27, 2012) from the Deputy City Manager and Chief Financial Officer; and that the 2012 Approved Capital Budget for Toronto Reference Library project be adjusted accordingly to offset the 2011 increase in funding.
3. City Council receive for information Appendix 4 to the report (April 27, 2012) from the Deputy City Manager and Chief Financial Officer, which lists capital projects that have been completed.
4. City Council authorize and direct the appropriate City Officials to take the necessary action to give effect to Council’s decision.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-46905.pdf
(April 27, 2012) Appendices 1 to 5
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-46906.pdf
Background Information (City Council)
https://www.toronto.ca/legdocs/mmis/2012/cc/bgrd/backgroundfile-48161.pdf
(June 5, 2012) Appendix 1 and Appendix 2 - fully completed and partially completed 2011 capital projects recommended for closure
https://www.toronto.ca/legdocs/mmis/2012/cc/bgrd/backgroundfile-48162.pdf
Motions (City Council)
Vote (Adopt Item) Jun-06-2012 6:54 PM
| Result: Carried | Majority Required - EX20.6 - Adopt the item |
|---|---|
| Total members that voted Yes: 29 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Shelley Carroll, Raymond Cho, Josh Colle, Gary Crawford, Vincent Crisanti, Janet Davis, Mike Del Grande, Frank Di Giorgio, Sarah Doucette, Rob Ford, Mary Fragedakis, Doug Holyday, Norman Kelly, Mike Layton, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Peter Milczyn, Denzil Minnan-Wong, Frances Nunziata (Chair), John Parker, James Pasternak, Jaye Robinson, David Shiner, Michael Thompson, Adam Vaughan, Kristyn Wong-Tam |
| Total members that voted No: 0 | Members that voted No are |
| Total members that were Absent: 16 | Members that were absent are Ana Bailão, Michelle Berardinetti, Glenn De Baeremaeker, John Filion, Paula Fletcher, Doug Ford, Mark Grimes, Chin Lee, Gloria Lindsay Luby, Giorgio Mammoliti, Joe Mihevc, Ron Moeser, Cesar Palacio, Gord Perks, Anthony Perruzza, Karen Stintz |
6a - Budget Committee Decision Letter - Capital Variance Report for the Year Ended December 31, 2011
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-47068.pdf
EX20.6 - Capital Variance Report for the Year Ended December 31, 2011
- Decision Type:
- ACTION
- Status:
- Amended
- Wards:
- All
Committee Recommendations
The Executive Committee recommends that:
1. City Council approve additional carry forward funding of $19.893 million for unspent 2011 capital and carry forward funding of $0.285 million for unspent 2010 and prior year capital projects as detailed in Appendix 2 of the report (April 27, 2012) from the Deputy City Manager and Chief Financial Officer, in order to continue work on capital projects, and that the 2012 Approved Capital Budget be adjusted accordingly with no incremental impact on debt.
2. City Council approve in-year budget adjustment of $1.556 million for Toronto Public Library to advance third party donations raised by the Toronto Library Foundation for the Toronto Reference Library capital project to 2011 from 2012 due to the acceleration of Phase II renovations in 2011 as detailed in Appendix 3 of the report (April 27, 2012) from the Deputy City Manager and Chief Financial Officer; and that the 2012 Approved Capital Budget for Toronto Reference Library project be adjusted accordingly to offset the 2011 increase in funding.
3. City Council receive for information Appendix 4 of the report (April 27, 2012) from the Deputy City Manager and Chief Financial Officer, which lists capital projects that have been completed.
4. City Council authorize and direct the appropriate City Officials to take the necessary action to give effect thereto.
Decision Advice and Other Information
The Executive Committee requested the Deputy City Manager and Chief Financial Officer to report directly to City Council on Capital Projects recommended for closure, including total numbers of projects and total numbers of dollars in the under-spent category, total numbers of projects and numbers of dollars in the over-spent category and any possible recommended courses of action emerging from these totals.
Origin
Summary
The purpose of this report is to provide the 2011 Capital Variance for the year-ended December 31, 2011 and to seek Council’s approval for 2011 in-year budget adjustments and 2011 and prior year carry forward funding with no incremental impact on debt.
Capital expenditures for the twelve months ended December 31, 2011 totalled $2.330 billion or 61.3% of the 2011 Approved Capital Budget of $3.797 billion (see Chart 1). This spending pattern is consistent with prior years. As detailed by City Program and Agency in Appendix 1, it is noted that 16 of 36 City Programs and Agencies spent in excess of 60% of their respective 2011 Approved Capital Budget.
(Refer to Chart 1 titled "2011 Capital Budget vs. Actual Expenditures for the Year Ended December 31, 2011" in the report from the Deputy City Manager and Chief Financial Officer).
Background Information
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-46905.pdf
(April 27, 2012) Appendices 1 to 5
https://www.toronto.ca/legdocs/mmis/2012/ex/bgrd/backgroundfile-46906.pdf
Motions
That the recommendations from the Budget Committee be adopted (Item EX20.6a).
6a - Budget Committee Decision Letter - Capital Variance Report for the Year Ended December 31, 2011
Origin
Summary
The purpose of this report is to provide the 2011 Capital Variance for the year-ended December 31, 2011 and to seek Council’s approval for 2011 in-year budget adjustments and 2011 and prior year carry forward funding with no incremental impact on debt.
Capital expenditures for the twelve months ended December 31, 2011 totalled $2.330 billion or 61.3% of the 2011 Approved Capital Budget of $3.797 billion (see Chart 1). This spending pattern is consistent with prior years. As detailed by City Program and Agency in Appendix 1, it is noted that 16 of 36 City Programs and Agencies spent in excess of 60% of their respective 2011 Approved Capital Budget.
(Refer to Chart 1 titled "2011 Capital Budget vs. Actual Expenditures for the Year Ended December 31, 2011" in the report from the Deputy City Manager and Chief Financial Officer).