AU9.17 - Associated Costs and Benefits Reported by Toronto Water on the Deep Lake Water Cooling Project
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
City Council Decision
City Council on November 27, 28 and 29, 2012, adopted the following:
1. City Council receive the report (October 10, 2012) from the General Manager, Toronto Water, for information.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2012/au/bgrd/backgroundfile-50864.pdf
Motions (City Council)
Vote (Adopt Item) Nov-27-2012 2:36 PM
| Result: Carried | Majority Required - AU9.17 - Adopt the item |
|---|---|
| Total members that voted Yes: 42 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Michelle Berardinetti, Shelley Carroll, Raymond Cho, Josh Colle, Gary Crawford, Vincent Crisanti, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, John Filion, Doug Ford, Rob Ford, Mary Fragedakis, Mark Grimes, Doug Holyday, Norman Kelly, Mike Layton, Chin Lee, Gloria Lindsay Luby, Giorgio Mammoliti, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Peter Milczyn, Denzil Minnan-Wong, Ron Moeser, Frances Nunziata (Chair), Cesar Palacio, John Parker, Gord Perks, Anthony Perruzza, Jaye Robinson, David Shiner, Karen Stintz, Michael Thompson, Adam Vaughan, Kristyn Wong-Tam |
| Total members that voted No: 0 | Members that voted No are |
| Total members that were Absent: 3 | Members that were absent are Sarah Doucette, Paula Fletcher, James Pasternak |
AU9.17 - Associated Costs and Benefits Reported by Toronto Water on the Deep Lake Water Cooling Project
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Audit Committee recommends that:
1. City Council receive the report (October 10, 2012) from the General Manager, Toronto Water, for information.
Origin
Summary
This report responds to a February 6, 2012, City Council decision for the General Manager, Toronto Water to account for all operating and capital costs incurred by Toronto Water on the Deep Lake Water Cooling project along with the estimated benefits. The review provides a final and complete disclosure of all project related costs and benefits, particularly the associated energy transfer fees and additional operating costs that were not adequately included in previous reports.
In summary, the costs incurred by Toronto Water as a direct result of the Deep Lake Water Cooling project since the start of the project up to 2011 year-end is $18.1 million. The total revenue generated from Enwave Energy Corporation during this time period has been $15.2 million ($3.5 million in net operating income and $11.7 million in Energy Transfer Agreement fees). In addition, approximately $61.5 million of new capital infrastructure has been transferred in title from Enwave to the City.
Background Information
https://www.toronto.ca/legdocs/mmis/2012/au/bgrd/backgroundfile-50864.pdf