Item - 2011.TE6.6
Tracking Status
- City Council adopted this item on May 17, 18 and 19, 2011 with amendments.
- This item was considered by Toronto and East York Community Council on April 21, 2011 and was adopted with amendments. It will be considered by City Council on May 17, 18 and 19, 2011.
- See also By-law 79-2015
TE6.6 - 355 King Street West - Alteration of a Designated Heritage Property
- Decision Type:
- ACTION
- Status:
- Amended
- Ward:
- 20 - Trinity-Spadina
City Council Decision
City Council on May 17, 18 and 19, 2011, adopted the following:
1. City Council approve the proposed alterations to the heritage property at 355 King Street West (Canadian Westinghouse Building) under Section 33 of the Ontario Heritage Act.
2. City Council direct that the approval of the alterations to the heritage property at 355 King Street West (Canadian Westinghouse Building) under Section 33 of the Ontario Heritage Act in accordance with the plans and drawings prepared by ERA Architects dated February 2, 2011, and on file with the Manager, Heritage Preservation Services, be subject to the following conditions as outlined in the report (May 11, 2011) from the Chief Planner and Executive Director, City Planning [TE6.6b]:
a. prior to Site Plan approval, the owner shall:
i. submit a Conservation Plan substantially in accordance with the Heritage Impact Assessment prepared by ERA Architects, dated February 2, 2011 to include drawings, to the satisfaction of the Manager of Heritage Preservation Services that provide enlarged elevations and sections of the retained heritage building façades at 1:50 scale including, but not limited to, the following: (1) street level design and entries; (2) window specifications for all heritage facade elevations; (3) return side wall details; (4) façade retention plan, including demolition plans and drawings related to removal of the south and east walls, the shoring of the north and west walls and all protective measures for the heritage façades during construction; (5) a restoration plan (including any required repair work and masonry conservation) for the retained portion of the heritage building; and
ii. enter into a Heritage Easement Agreement for the retained portion of 355 King Street West with the City.
b. prior to the issuance of any building permit, including a permit for the demolition, excavation, and/or shoring on the subject property, the owner shall:
i. provide a Letter of Credit in a form and in an amount satisfactory to the Manager, Heritage Preservation Services to secure all work included in the Conservation Plan; and
ii. provide final plans satisfactory to the Manager of Heritage Preservation Services.
c. prior to the release of the Letter of Credit the applicant shall:
i. provide a certificate of completion, prepared by a qualified heritage consultant, satisfactory to the Manager of Heritage Preservation Services.
3. City Council grant authority for the execution of a Heritage Easement Agreement under Section 37 of the Ontario Heritage Act with the owners of 355 King Street West.
4. The City Solicitor be authorized to introduce the necessary bill in Council authorizing the entering into of a Heritage Easement Agreement.
5. City Council receive the report (March 17, 2011) from the Acting Director, Policy and Research, City Planning Division, respecting 355 King Street West – Alteration of a Designated Heritage Property.
Background Information (Community Council)
https://www.toronto.ca/legdocs/mmis/2011/te/bgrd/backgroundfile-37172.pdf
Background Information (City Council)
https://www.toronto.ca/legdocs/mmis/2011/cc/bgrd/backgroundfile-38188.pdf
Motions (City Council)
City Council direct that the approval of the alterations to the heritage property at 355 King Street West (Canadian Westinghouse Building) under Section 33 of the Ontario Heritage Act in accordance with the plans and drawings prepared by ERA Architects dated February 2, 2011, and on file with the Manager, Heritage Preservation Services, be subject to the following conditions as outlined in the report (May 11, 2011) from the Chief Planner and Executive Director, City Planning [TE6.6b]:
1. Approval be subject to the following conditions:
a. prior to Site Plan approval, the owner shall:
i. submit a Conservation Plan substantially in accordance with the Heritage Impact Assessment prepared by ERA Architects, dated February 2, 2011 to include drawings, to the satisfaction of the Manager of Heritage Preservation Services that provide enlarged elevations and sections of the retained heritage building façades at 1:50 scale including, but not limited to, the following: (1) street level design and entries; (2) window specifications for all heritage facade elevations; (3) return side wall details; (4) façade retention plan, including demolition plans and drawings related to removal of the south and east walls, the shoring of the north and west walls and all protective measures for the heritage façades during construction; (5) a restoration plan (including any required repair work and masonry conservation) for the retained portion of the heritage building;
ii. enter into a Heritage Easement Agreement for the retained portion of 355 King Street West with the City.
b. prior to the issuance of any building permit, including a permit for the demolition, excavation, and/or shoring on the subject property, the owner shall:
i. provide a Letter of Credit in a form and in an amount satisfactory to the Manager, Heritage Preservation Services to secure all work included in the Conservation Plan;
ii. provide final plans satisfactory to the Manager of Heritage Preservation Services.
c. prior to the release of the Letter of Credit the applicant shall:
i. a certificate of completion, prepared by a qualified heritage consultant, satisfactory to the Manager of Heritage Preservation Services.
2. City Council grant authority for the execution of a Heritage Easement Agreement under Section 37 of the Ontario Heritage Act with the owners of 355 King Street West.
3. The City Solicitor be authorized to introduce the necessary bill in Council authorizing the entering into of a Heritage Easement Agreement.
Vote (Amend Item (Additional)) May-17-2011 2:12 PM
| Result: Carried | Majority Required - TE6.6 - Vaughan - motion 1 |
|---|---|
| Total members that voted Yes: 36 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Michelle Berardinetti, Shelley Carroll, Raymond Cho, Josh Colle, Gary Crawford, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, Sarah Doucette, Doug Ford, Rob Ford, Mary Fragedakis, Mark Grimes, Doug Holyday, Norman Kelly, Mike Layton, Chin Lee, Gloria Lindsay Luby, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Denzil Minnan-Wong, Ron Moeser, Frances Nunziata (Chair), James Pasternak, Gord Perks, Anthony Perruzza, Karen Stintz, Michael Thompson, Adam Vaughan, Kristyn Wong-Tam |
| Total members that voted No: 0 | Members that voted No are |
| Total members that were Absent: 9 | Members that were absent are Vincent Crisanti, John Filion, Paula Fletcher, Giorgio Mammoliti, Peter Milczyn, Cesar Palacio, John Parker, Jaye Robinson, David Shiner |
Vote (Adopt Item as Amended) May-17-2011 2:13 PM
| Result: Carried | Majority Required - TE6.6 - Adopt the item as amended |
|---|---|
| Total members that voted Yes: 35 | Members that voted Yes are Paul Ainslie, Maria Augimeri, Ana Bailão, Michelle Berardinetti, Shelley Carroll, Raymond Cho, Josh Colle, Gary Crawford, Janet Davis, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, Sarah Doucette, Doug Ford, Rob Ford, Mary Fragedakis, Mark Grimes, Doug Holyday, Norman Kelly, Mike Layton, Chin Lee, Gloria Lindsay Luby, Josh Matlow, Pam McConnell, Mary-Margaret McMahon, Joe Mihevc, Denzil Minnan-Wong, Ron Moeser, Frances Nunziata (Chair), James Pasternak, Gord Perks, Anthony Perruzza, Michael Thompson, Adam Vaughan, Kristyn Wong-Tam |
| Total members that voted No: 0 | Members that voted No are |
| Total members that were Absent: 10 | Members that were absent are Vincent Crisanti, John Filion, Paula Fletcher, Giorgio Mammoliti, Peter Milczyn, Cesar Palacio, John Parker, Jaye Robinson, David Shiner, Karen Stintz |
6a - 355 King Street West - Alteration of a Designated Heritage Property
Background Information (Community Council)
https://www.toronto.ca/legdocs/mmis/2011/te/bgrd/backgroundfile-37173.pdf
TE6.6 - 355 King Street West - Alteration of a Designated Heritage Property
- Decision Type:
- ACTION
- Status:
- Amended
- Ward:
- 20 - Trinity-Spadina
Community Council Recommendations
The Toronto and East York Community Council recommends that:
1. City Council approve the proposed alterations to the heritage property at 355 King Street West (Canadian Westinghouse Building) under Section 33 of the Ontario Heritage Act.
2. City Council receive the report dated March 17, 2011, from the Acting Director, Policy and Research, City Planning Division, respecting 355 King Street West – Alteration of a Designated Heritage Property.
Decision Advice and Other Information
The Toronto and East York Community Council requested the Manager, Heritage Preservation Services to report directly to City Council for its meeting on May 17 and 18, 2011, recommending appropriate conditions to secure the conservation strategy as proposed by the applicant and described in the Heritage Impact Assessment for 355 King Street West, dated February 2, 2011.
Origin
Summary
This report recommends that City Council refuse the application for the proposed alterations to the heritage property at 355 King Street West. This property was designated under Part IV of the Ontario Heritage Act by Toronto City Council on January 13, 1992, by By-law 115-92.
An application has been made by the owner to obtain a heritage permit under Section 33 of the Ontario Heritage Act. Under the Act, Council must respond to a heritage permit application within 90 days from the issuance of a Notice of Receipt of a complete application. As of the date of this report, the applicant has not met all of the requirements of a complete application set out under Section 103 of the Municipal Code. The applicant has been advised of these requirements, but at present wishes the City to process the application for a Council decision. The applicant will be advised that a deferral can be requested pending submission of the requested material.
Staff have not received convincing reasons from the applicant as to why the building at 355 King Street West needs to be altered to the extent that only two façades will be retained. Major alteration of this building is not an appropriate or desirable outcome of the application to obtain a heritage permit. City staff encourage the applicant to adaptively re-use this significant heritage resource as a part of the property's development.
Background Information
https://www.toronto.ca/legdocs/mmis/2011/te/bgrd/backgroundfile-37172.pdf
Speakers
Motions
That the Toronto and East York Community Council adopt the following recommendation of the Toronto Preservation Board contained in Item TE6.6a.
"That:
1. City Council approve the proposed alterations to the heritage property at 355 King Street West (Canadian Westinghouse Building) under Section 33 of the Ontario Heritage Act."
That the Toronto and East York Community Council request the Manager, Heritage Preservation Services, to report directly to City Council for its meeting on May 17 and 18, 2011, recommending appropriate conditions to secure the conservation strategy as proposed by the applicant and described in the Heritage Impact Assessment for 355 King Street West, dated February 2, 2011.
6a - 355 King Street West - Alteration of a Designated Heritage Property
Origin
Summary
The Toronto Preservation Board on April 1, 2011, considered the following:
1. Report (March 17, 2011) from the Acting Director, Policy and Research, City Planning, respecting 355 King Street - Alteration of a Designated Heritage Property;
2. Letter (April 12, 2010) from Michael McClelland, Principal, E.R.A. Architects Inc. and Philip Evans, Associate, E.R.A. Architects Inc.; and
3. Submission (February 2, 2011) from E.R.A. Architects Inc.
The following persons addressed the Toronto Preservation Board:
- Patrick Devine, Fraser Milner Casgrain LLP
- Shirley Blumber, Kuwabara Payne McKenna Blumberg Architects
- Philip Evans, E.R.A. Architects Inc. and filed a submission.
Background Information
https://www.toronto.ca/legdocs/mmis/2011/te/bgrd/backgroundfile-37173.pdf