Item - 2010.PW33.13
Tracking Status
- City Council adopted this item on June 8 and 9, 2010 without amendments.
- This item was considered by the Public Works and Infrastructure Committee on May 18, 2010 and adopted without amendment. It will be considered by City Council on June 8 and 9, 2010.
PW33.13 - Authority to Enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc. to Supply, Install, Own and Operate a Biomethane System at the Dufferin Waste Management Facility
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
City Council Decision
City Council on June 8 and 9, 2010, adopted the following:
1. City Council grant authority for the General Manager, Solid Waste Management Services, to enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc to supply, install, own and operate a biomethane system, substantially on the terms set out in Attachment 1 to the report (May 3, 2010) from the General Manager, Solid Waste Management Services, and such other terms as may be satisfactory to the General Manager, Solid Waste Management Services, and in a form satisfactory to the City Solicitor, and that the General Manager, Solid Waste Management Services be authorized to execute the Biogas Pilot Project Agreement on behalf of the City.
2. City Council authorize the General Manager, Solid Waste Management Services, or his delegate, to administer and manage the Biogas Pilot Project Agreement, including the provision of any consents, approvals, notices and notices of termination, provided that the General Manager, Solid Waste Management Services may, at any time, refer consideration of such matters (including their content) to City Council for its determination and direction.
3. City Council request the General Manager, Solid Waste Management Services, to report on the results of the Biogas Pilot Project to City Council.
4. City Council direct that subject to the execution of an agreement between Enbridge Gas Distribution Inc., and the City as set out in Part1 above, the General Manager, Solid Waste Management Services, and the Deputy City Manager and Chief Financial Officer, investigate options for funding the cost of the Pilot Project through cost savings resulting from displacing natural gas with biomethane or some other means.
5. City Council direct that in the event the Biogas Pilot Project Agreement is not executed by September 1st, 2010, the General Manager, Solid Waste Management Services, be authorized, at his sole discretion, to terminate negotiations with Enbridge.
Background Information (Committee)
https://www.toronto.ca/legdocs/mmis/2010/pw/bgrd/backgroundfile-29805.pdf
PW33.13 - Authority to Enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc. - Attachment 1
https://www.toronto.ca/legdocs/mmis/2010/pw/bgrd/backgroundfile-29806.pdf
PW33.13 - Authority to Enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc. - Attachment 2
https://www.toronto.ca/legdocs/mmis/2010/pw/bgrd/backgroundfile-29807.pdf
PW33.13 - Authority to Enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc. - Attachment 3
https://www.toronto.ca/legdocs/mmis/2010/pw/bgrd/backgroundfile-29808.pdf
PW33.13 - Authority to Enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc. - Attachment 4
https://www.toronto.ca/legdocs/mmis/2010/pw/bgrd/backgroundfile-29809.pdf
Motions (City Council)
PW33.13 - Authority to Enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc. to Supply, Install, Own and Operate a Biomethane System at the Dufferin Waste Management Facility
- Decision Type:
- ACTION
- Status:
- Adopted
- Wards:
- All
Committee Recommendations
The Public Works and Infrastructure Committee recommends that:
1. City Council grant authority for the General Manager, Solid Waste Management Services, to enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc to supply, install, own and operate a biomethane system, substantially on the terms set out in Attachment 1 to the report (May 3, 2010) from the General Manager, Solid Waste Management Services, and such other terms as may be satisfactory to the General Manager, Solid Waste Management Services, and in a form satisfactory to the City Solicitor, and that the General Manager, Solid Waste Management Services be authorized to execute the Biogas Pilot Project Agreement on behalf of the City.
2. City Council authorize the General Manager, Solid Waste Management Services, or his delegate, to administer and manage the Biogas Pilot Project Agreement, including the provision of any consents, approvals, notices and notices of termination, provided that the General Manager, Solid Waste Management Services may, at any time, refer consideration of such matters (including their content) to City Council for its determination and direction.
3. City Council request the General Manager, Solid Waste Management Services, to report on the results of the Biogas Pilot Project to City Council.
4. City Council direct that subject to the execution of an agreement between Enbridge Gas Distribution Inc., and the City as set out in Recommendation 1, the General Manager, Solid Waste Management Services, and the Deputy City Manager and Chief Financial Officer, investigate options for funding the cost of the Pilot Project through cost savings resulting from displacing natural gas with biomethane or some other means.
5. City Council direct that in the event the Biogas Pilot Project Agreement is not executed by September 1st, 2010, the General Manager, Solid Waste Management Services, be authorized, at his sole discretion, to terminate negotiations with Enbridge.
Origin
Summary
The purpose of this staff report is to obtain City Council authority to enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc. (“Enbridge”) to supply, install, own and operate a biomethane system (“BMS”) at the Dufferin Waste Management Facility. The pilot project will determine if biogas produced at the Dufferin Organics Processing Facility ("DOPF") can be converted into a refined biogas, via the BMS, that is capable of being distributed across Enbridge's natural gas distribution system (the "Pilot Project").
At its meeting on November 30, December 1, 2, 4 and 7, 2009, City Council directed the General Manager, Solid Waste Management Services to enter into discussions with Enbridge regarding the development of biogas refining systems at the new SSO Facilities and to report back on a recommended course of action for the procurement of a contract to design, build, own and operate biogas refining systems at the SSO Facilities.
Background Information
https://www.toronto.ca/legdocs/mmis/2010/pw/bgrd/backgroundfile-29805.pdf
PW33.13 - Authority to Enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc. - Attachment 1
https://www.toronto.ca/legdocs/mmis/2010/pw/bgrd/backgroundfile-29806.pdf
PW33.13 - Authority to Enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc. - Attachment 2
https://www.toronto.ca/legdocs/mmis/2010/pw/bgrd/backgroundfile-29807.pdf
PW33.13 - Authority to Enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc. - Attachment 3
https://www.toronto.ca/legdocs/mmis/2010/pw/bgrd/backgroundfile-29808.pdf
PW33.13 - Authority to Enter into a Biogas Pilot Project Agreement with Enbridge Gas Distribution Inc. - Attachment 4
https://www.toronto.ca/legdocs/mmis/2010/pw/bgrd/backgroundfile-29809.pdf
Motions
Vote (Adopt Item) May-18-2010
| Result: Carried | Majority Required |
|---|---|
| Total members that voted Yes: 4 | Members that voted Yes are Shelley Carroll, Glenn De Baeremaeker (Chair), Cesar Palacio, Gord Perks |
| Total members that voted No: 0 | Members that voted No are |