EX45.39 - Solar Photovoltaic Program for City Facilities

Decision Type:
ACTION
Status:
Amended
Wards:
All

City Council Decision

 City Council on July 6, 7 and 8, 2010, adopted the following:

 

1.         City Council grant authority for the City to enter into an agreement with Toronto Hydro Electricity System Limited for a solar photovoltaic (PV) program substantially on the terms described in the report (June 2, 2010) from the Chief Corporate Officer, and as set out in Attachment 1 to the report (June 2, 2010) from the Chief Corporate Officer, and other such terms and conditions as may be deemed appropriate by the Chief Corporate Officer, and in a form satisfactory to the City Solicitor, and that the Chief Corporate Officer be authorized to execute any related agreements on behalf of the City.

 

2.         City Council authorize the reallocation of funds in the 2010 Approved Capital Budget and 2011 to 2019 Capital Plan from the Energy Conservation Reserve Fund to a new project, the Solar Photovoltaic Program, within the Sustainable Energy Plan in the amount of $4 million in 2010 and $4 million in 2011, as set out in Attachment 2 to the report (June 2, 2010) from the Chief Corporate Officer.

 

3.         City Council direct that Licenses to community-based solar co-operative groups for the installation of solar PV panels on City-owned facilities, be granted for nominal value.

 

4.         City Council direct the General Managers of Toronto Employment and Social Services and Economic Development and the Chief Corporate Officer to develop a training and employment pilot program, and an engagement program for local solar manufacturers, substantially as outlined in the report (June 30, 2010) from the Chief Corporate Officer and the General Manager, Toronto Employment and Social Services (EX45.39a) and report back on how the lessons learned from this pilot will inform future initiatives and approaches in this area.

Background Information (Committee)

Solar Photovoltaic Program for City Facilities
https://www.toronto.ca/legdocs/mmis/2010/ex/bgrd/backgroundfile-30927.pdf
Attachment 1. Term Sheet for Business Arrangement
https://www.toronto.ca/legdocs/mmis/2010/ex/bgrd/backgroundfile-30928.pdf
Attachment 2. Budget Adjustment to create new capital project
https://www.toronto.ca/legdocs/mmis/2010/ex/bgrd/backgroundfile-30929.pdf

Background Information (City Council)

(June 30, 2010) supplementary report from the Chief Corporate Officer and the General Manager, Toronto Employment and Social Services (EX45.39a)
https://www.toronto.ca/legdocs/mmis/2010/cc/bgrd/backgroundfile-31851.pdf

Motions (City Council)

1 - Motion to Amend Item (Additional) moved by Councillor Gord Perks (Carried)

That City Council adopt the following recommendation contained in the report (June 30, 2010) from the Chief Corporate Officer and the General Manager, Toronto Employment and Social Services [EX45.39a]:

 

1.         The General Managers of Toronto Employment and Social Services and Economic Development and the Chief Corporate Officer develop a training and employment pilot program, and an engagement program for local solar manufacturers, substantially as outlined in this report, and report back on how the lessons learned from this pilot will inform future initiatives and approaches in this area.

Vote (Amend Item (Additional)) Jul-07-2010 10:16 AM

Result: Carried Majority Required - EX45.39 - Perks - Motion 1
Total members that voted Yes: 31 Members that voted Yes are Paul Ainslie, Sandra Bussin (Chair), Shelley Carroll, Raymond Cho, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, Mike Feldman, Mark Grimes, Suzan Hall, A.A. Heaps, Cliff Jenkins, Norman Kelly, Gloria Lindsay Luby, Giorgio Mammoliti, Pam McConnell, Joe Mihevc, Peter Milczyn, Denzil Minnan-Wong, Ron Moeser, Howard Moscoe, Frances Nunziata, Cesar Palacio, Gord Perks, Anthony Perruzza, Kyle Rae, Bill Saundercook, David Shiner, Karen Stintz, Adam Vaughan, Michael Walker
Total members that voted No: 3 Members that voted No are Rob Ford, Doug Holyday, Case Ootes
Total members that were Absent: 11 Members that were absent are Brian Ashton, Maria Augimeri, Janet Davis, John Filion, Paula Fletcher, Adam Giambrone, Chin Lee, David Miller, Joe Pantalone, John Parker, Michael Thompson

Motion to Adopt Item as Amended (Carried)

Vote (Adopt Item as Amended) Jul-07-2010 10:17 AM

Result: Carried Majority Required - Ex45.39 - Adopt the Item, as amended
Total members that voted Yes: 31 Members that voted Yes are Paul Ainslie, Sandra Bussin (Chair), Shelley Carroll, Raymond Cho, Glenn De Baeremaeker, Mike Del Grande, Frank Di Giorgio, Mike Feldman, Mark Grimes, Suzan Hall, A.A. Heaps, Cliff Jenkins, Norman Kelly, Gloria Lindsay Luby, Giorgio Mammoliti, Pam McConnell, Joe Mihevc, Peter Milczyn, Denzil Minnan-Wong, Ron Moeser, Howard Moscoe, Frances Nunziata, Cesar Palacio, Gord Perks, Anthony Perruzza, Kyle Rae, Bill Saundercook, David Shiner, Karen Stintz, Adam Vaughan, Michael Walker
Total members that voted No: 3 Members that voted No are Rob Ford, Doug Holyday, Case Ootes
Total members that were Absent: 11 Members that were absent are Brian Ashton, Maria Augimeri, Janet Davis, John Filion, Paula Fletcher, Adam Giambrone, Chin Lee, David Miller, Joe Pantalone, John Parker, Michael Thompson

EX45.39 - Solar Photovoltaic Program for City Facilities

Decision Type:
ACTION
Status:
Amended
Wards:
All

Committee Recommendations

 The Executive Committee recommends that:

 

1.         City Council grant authority for the City to enter into an agreement with Toronto Hydro Electricity System Limited for a solar photovoltaic (PV) program substantially on the terms described in the report (June 2, 2010) from the Chief Corporate Officer, and as set out in Attachment 1 to the report (June 2, 2010) from the Chief Corporate Officer, and other such terms and conditions as may be deemed appropriate by the Chief Corporate Officer, and in a form satisfactory to the City Solicitor, and that the Chief Corporate Officer be authorized to execute any related agreements on behalf of the City.

 

2.         City Council authorize the reallocation of funds in the 2010 Approved Capital Budget and 2011 to 2019 Capital Plan from the Energy Conservation Reserve Fund to a new project, the Solar Photovoltaic Program, within the Sustainable Energy Plan in the amount of $4 million in 2010 and $4 million in 2011, as set out in Attachment 2 to the report (June 2, 2010) from the Chief Corporate Officer.

 

3.         City Council direct that Licenses to community-based solar co-operative groups for the installation of solar PV panels on City-owned facilities, be granted for nominal value.

Decision Advice and Other Information

The Executive Committee requested the Chief Corporate Officer and the General Manager of Toronto Employment and Social Services, in consultation with Toronto Hydro and the Central Ontario Building Trades, to report directly to Council on July 6, 2010, on the development of:

 

a.         A training and employment program related to the Solar Photovoltaic Program that would provide opportunities for local green sector job training and employment for Toronto youth.

 

b.         A strategy to engage local manufacturers of products required for the program.

Origin

(June 2, 2010) Report from the Chief Corporate Officer

Summary

This report recommends the approval of a pilot program between the City and Toronto Hydro Electric Services Ltd. for the installation of solar photovoltaic panels on City‑owned buildings.  Under the program, the City would own up to 49% of the panels, with Toronto Hydro owning the balance.  The report requests Council’s authority to amend the Sustainable Energy Plan 2010 Approved Capital Budget and the 2011 to 2019 Capital Plan by reallocating $8 million included in the Toronto Energy Conservation Fund to a new project, the Solar Photovoltaic Program, with zero net impact corporately.

 

This report advises that a competitive process will be utilized to licence the use of City‑owned roof space to private sector solar developers on buildings not selected for the City-Toronto Hydro pilot program.  This report also advises that, depending on the availability of funds, the City may in the future continue to install its own solar installations on City facilities.  In addition, this report recommends that roof space on smaller City-owned facilities be made available at a nominal fee to community-based solar co-operative groups.

Background Information

Solar Photovoltaic Program for City Facilities
https://www.toronto.ca/legdocs/mmis/2010/ex/bgrd/backgroundfile-30927.pdf
Attachment 1. Term Sheet for Business Arrangement
https://www.toronto.ca/legdocs/mmis/2010/ex/bgrd/backgroundfile-30928.pdf
Attachment 2. Budget Adjustment to create new capital project
https://www.toronto.ca/legdocs/mmis/2010/ex/bgrd/backgroundfile-30929.pdf

Motions

1 - Motion to Amend Item (Additional) moved by Councillor Janet Davis (Carried)

That the Executive Committee request the Chief Corporate Officer and the General Manager of Toronto Employment and Social Services, in consultation with Toronto Hydro and the Central Ontario Building Trades, to submit a report directly to Council on July 6, 2010, on the development of:

 

a.         A training and employment program related to the Solar Photovoltaic Program that would provide opportunities for local green sector job training and employment for Toronto youth.

 

b.         A strategy to engage local manufacturers of products required for the program.


2 - Motion to Adopt Item as Amended moved by Councillor Janet Davis (Carried)