  • This item was considered by Budget Committee on August 9, 2010 and was adopted without amendment.

BU74.2 - Amendment to Purchase Order 6029461 - For the Pre Construction and Construction Services for the Nathan Phillips Square Revitalization Project

Decision Type:
ACTION
Status:
Adopted
Ward:
27 - Toronto Centre-Rosedale

Committee Decision

The Budget Committee recommends to the Executive Committee that:

 

1.         Subject to approval of Recommendation No. 3 in the report (July 29, 2010) from the Chief Corporate Officer and the Director, Purchasing and Materials Management, City Council grant authority to amend Purchase Order No. 6029461 with PCL Constructors Canada Inc. for the construction services and construction implementation of the Nathan Phillips Square Revitalization Project at Toronto City Hall. The total amendment request is $4,897,708.80 net of HST Recoveries ($4,813,000.00 net of all applicable taxes and charges), revising the current contract value from $28,000,000.00 to $32,813,000.00 net of all applicable taxes and charges.

 

2.         City Council authorize an increase to Facilities and Real Estate Approved 2010 Capital Budget and 2011-2019 Capital Plan in the amount of $2,536,819.00, and to allow Facilities Management to receive this funding from a 3rd party contributor, the Toronto Parking Authority (TPA), with a zero net impact.

Origin

(July 29, 2010) Report from the Chief Corporate Officer and the Director, Purchasing and Materials Management

Summary

The purpose of this report is to request authority to amend Purchase Order No. 6029461 with PCL Constructors Canada Inc. for the Construction Services for the Nathan Phillips Square (NPS) Revitalization Project at Toronto City Hall.  The total amendment request is $4,897,708.80 net of HST Recoveries.  Also, this report requests Council’s authority to receive funding from a 3rd party contributor to be applied to construction services for the Nathan Phillips Square Revitalization project.

Background Information

Amendment to Purchase Order No. 6029461 - For the Pre-Construction and Construction Services for the Nathan Phillips Square Revitalization Project
https://www.toronto.ca/legdocs/mmis/2010/bu/bgrd/backgroundfile-32398.pdf

Motions

Motion to Adopt Item moved by Councillor Kyle Rae (Carried)

Vote (Adopt Item) Aug-09-2010

Result: Carried Majority Required
Total members that voted Yes: 5 Members that voted Yes are Maria Augimeri, Shelley Carroll (Chair), Joe Mihevc, Gord Perks, Kyle Rae
Total members that voted No: 1 Members that voted No are Paul Ainslie