IN THE MATTER OF THE ONTARIO HERITAGE ACT

R.S.O. 1990, CHAPTER O.18 AND

CITY OF TORONTO, PROVINCE OF ONTARIO

149 COLLEGE STREET

 

NOTICE OF DECISION

 

TAKE NOTICE that the Council of the City of Toronto on December 16 and 17, 2025, has considered an application under Section 33 of the Ontario Heritage Act to alter a building and/or structure on a Property designated under Part IV, Section 29 of the Ontario Heritage Act for the Property municipally known as 149 College Street.

 

The decision of City Council, among other matters, regarding the application under the Ontario Heritage Act is as follows:

 

1. City Council approve the alterations to the designated heritage property at 149 College Street, in accordance with Section 33 of the Ontario Heritage Act to allow for the construction of a 60-storey mixed-use building, with such alterations substantially in accordance with the plans and drawings dated March 11, 2025 prepared by Sweeney Architects Inc. and on file with the Senior Manager, Heritage Planning and the Heritage Impact Assessment prepared by ERA Architects, dated February 24, 2025, and on file with the Senior Manager, Heritage Planning, all subject to and in accordance with the Conservation Plan satisfactory to the Senior Manager, Heritage Planning and subject to conditions as set out below.

  

2. City Council direct that its consent to the application to alter the designated heritage property at 149 College Street, in accordance with Part IV, Section 33 of the Ontario Heritage Act are also subject to the following conditions:

 

a. That the related Zoning By-law Amendment permitting the proposed alterations has been enacted by City Council and has come into full force and effect in a form and with content acceptable to City Council, as determined by Executive Director, Development Review, in consultation with the Senior Manager, Heritage Planning.

 

b. The owner shall:

 

1. Enter into a Heritage Easement Agreement with the City for the property at 149 College Street, substantially in accordance with the plans and drawings dated March 11, 2025 prepared by Sweeney Architects inc. and on file with the Senior Manager, Heritage Planning; and the Heritage Impact Assessment (HIA), dated February 24, 2025 prepared by ERA Architects, all on file with the Senior Manager, Heritage Planning, subject to and in accordance with the Conservation Plan required in Recommendation 2.b.2, to the satisfaction of the Senior Manager, Heritage Planning including execution of such agreement to the satisfaction of the City Solicitor.

 

2. Provide a detailed Conservation Plan, prepared by a qualified heritage consultant that is substantially in accordance with the conservation strategy set out in the Heritage Impact Assessment for the property at 149 College Street, to the satisfaction of the Senior Manager, Heritage Planning.

 

c. That prior to the issuance of any permit for all or any part of the property at 149 College Street, including a heritage permit or a building permit, but excluding permits for repairs and maintenance and usual and minor works for the existing heritage building as are acceptable to the Senior Manager, Heritage Planning, the owner shall:

 

1.  Have entered into a Heritage Easement Agreement with the City required in Recommendation 2.b.1 above for the property at 149 College Street including registration on title of such agreement, to the satisfaction of the City Solicitor.

 

2. Have obtained final approval for the necessary Zoning By-law Amendments, and such Amendments to have come into full force and effect.

 

3. Provide a Heritage Lighting Plan that describes how the exterior of the heritage property will be sensitively illuminated to enhance its heritage character to the satisfaction of the Senior Manager, Heritage Planning and thereafter shall implement such a plan to the satisfaction of the Senior Manager Heritage Planning.

 

4. Provide an Interpretation Plan for the subject property, to the satisfaction of the Senior Manager, Heritage Planning and thereafter shall implement such plan to the satisfaction of the Senior Manager, Heritage Planning.

 

5. Submit a Signage Plan to the satisfaction of the Senior Manager, Heritage Planning.

 

6. Provide a detailed Landscape Plan for the subject property, satisfactory to the Senior Manager, Heritage Planning.

 

7. Provide building permit drawings, including notes and specifications for the conservation and protective measures keyed to the approved Conservation Plans required in Recommendation 2.b.2, including a description of materials and finishes, to be prepared by the project architect and a qualified heritage consultant to the satisfaction of the Senior Manager, Heritage Planning.

 

8. Provide a Letter of Credit, including provision for upwards indexing, in a form and amount and from a bank satisfactory to the Senior Manager, Heritage Planning, to secure all work included in the approved Conservation and Interpretation plans.

 

d. That prior to the release of the Letter of Credit required in Recommendation 2.c.8, the owner shall:

 

1. Provide a letter of substantial completion prepared and signed by a qualified heritage consultant confirming that the required conservation work and the required interpretive work has been completed in accordance with the Conservation and Interpretation Plans and that an appropriate standard of conservation has been maintained, all to the satisfaction of the Senior Manager, Heritage Planning.

 

2. Provide replacement Heritage Easement Agreement photographs to the satisfaction of the Senior Manager, Heritage Planning.

 

IF YOU WISH TO APPEAL TO THE ONTARIO LAND TRIBUNAL:

 

Notice of an appeal of the decision of City Council on the application to alter the Property may be served on the City Clerk, Attention: Registrar Secretariat, City Clerk's Office, Toronto City Hall, 2nd Floor West, 100 Queen Street West, Toronto, Ontario, M5H 2N2.; Email: RegistrarCCO@toronto.ca within thirty (30) days of December 22, 2025, which is January 21, 2026.

 

A Notice of Appeal must:

 

(1)          set out the reasons for the objection to the decision;

(2)          set out the reasons in support of the objection to the decision.

 

Who Can File An Appeal:

Only the owner of the Property may appeal the decision of Council of the City of Toronto to the Ontario Land Tribunal under Part IV, Section 33 of the Ontario Heritage Act, and only where City Council has consented to an application to alter a property with certain terms or conditions or refuses the application to alter a property.

 

Getting Additional Information:

 

Further information in respect of the Decision of Council of the City of Toronto on the matter is available from the City of Toronto at:

 

https://secure.toronto.ca/council/agenda-item.do?item=2025.TE27.7.

 

Dated at the City of Toronto on December 22, 2025.

 

 

John D. Elvidge

City Clerk